Found 5 inspections:

# 762005259490
Unscheduled inspection
Start date: 2020-12-11, end date: 2020-12-24, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu na osnovanii izvescheniya ob okonchanii stroitelstva obekta kapitalnogo stroitelstva ot 01122020 vh 1803Zadachami nastoyaschei proverki yavlyayutsya opredelenie sootvetstviya postroennogo obekta kapitalnogo stroitelstva trebovaniyam proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyasoblyudenie obyazatelnyh trebovanii


# 762004478461
Unscheduled inspection
Start date: 2020-08-07, end date: 2020-08-07, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The purpose of this audit is to determine, based on the verification program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of the design documentation. The purpose of this audit is to comply with mandatory requirements


# 762004271130
Unscheduled inspection
Start date: 2020-02-11, end date: 2020-02-11, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The purpose of this audit is to determine, based on the verification program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of the design documentation. The purpose of this audit is to comply with mandatory requirements


# 761903936007
Unscheduled inspection
Start date: 2019-11-08, end date: 2019-11-08, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The inspection is carried out in order to determine, on the basis of the inspection program, the objectives of this inspection are to determine whether the work performed during the construction of a capital construction facility meets the requirements of project documentation. The subject of this inspection is compliance with mandatory requirements


# 761902925274
Unscheduled inspection
Start date: 2019-08-07, end date: 2019-08-07, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The inspection is carried out in order to determine, on the basis of the inspection program, the objectives of this inspection are to determine whether the work performed during the construction of a capital construction facility meets the requirements of project documentation. The subject of this inspection is compliance with mandatory requirements


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.