# 162004429373
Unscheduled inspection
Start date: 2020-06-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004403653
Unscheduled inspection
Start date: 2020-05-07, end date: 2020-05-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 20112019 case 141120150054 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004409554
Unscheduled inspection
Start date: 2020-05-21, end date: 2020-05-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 21012020 case 140420190013 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004399020
Unscheduled inspection
Start date: 2020-04-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004260978
Unscheduled inspection
Start date: 2020-02-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903890639
Unscheduled inspection
Start date: 2019-10-28, end date: 2019-11-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied in the process of construction of the capital construction facility of building materials and the results of such works with the requirements of the design documentation prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, compliance with mandatory requirements or requirements established by municipal legal acts
# 161903890153
Unscheduled inspection
Start date: 2019-10-28, end date: 2019-10-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied in the process of construction of the capital construction facility of building materials and the results of such works with the requirements of the design documentation prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, compliance with mandatory requirements or requirements established by municipal legal acts
# 161903014597
Unscheduled inspection
Start date: 2019-08-28, end date: 2019-08-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied in the process of construction of the capital construction facility of building materials and the results of such works with the requirements of the design documentation prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, compliance with mandatory requirements or requirements established by municipal legal acts
# 161902761383
Unscheduled inspection
Start date: 2019-06-10, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161902744590
Unscheduled inspection
Start date: 2019-06-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902645183
Unscheduled inspection
Start date: 2019-04-17, end date: 2019-04-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied in the process of construction of the capital construction facility of building materials and the results of such works with the requirements of the design documentation prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, compliance with mandatory requirements or requirements established by municipal legal acts
# 161902644046
Unscheduled inspection
Start date: 2019-04-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902526989
Unscheduled inspection
Start date: 2019-02-27, end date: 2019-02-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied in the process of construction of the capital construction facility of building materials and the results of such works with the requirements of the design documentation prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, compliance with mandatory requirements or requirements established by municipal legal acts