Found 10 inspections:

# 77190803480088
Unscheduled inspection
Start date: 2019-08-19, end date: 2019-09-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the fulfillment by the person carrying out the construction of the requirements of part 3 of Article 52 of the Urban Planning Code is the compliance of the work and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for used energy resources


# 77190803444903
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-07-25, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the fulfillment by the person carrying out the construction of the requirements of part 3 of Article 52 of the Urban Planning Code is the compliance of the work and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for used energy resources


# 77190803432956
Unscheduled inspection
Start date: 2019-06-07, end date: 2019-06-25, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the fulfillment by the person carrying out the construction of the requirements of part 3 of Article 52 of the Urban Planning Code is the compliance of the work and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for used energy resources


# 77190803384709
Unscheduled inspection
Start date: 2019-04-15, end date: 2019-04-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803365412
Unscheduled inspection
Start date: 2019-03-21, end date: 2019-03-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803362664
Unscheduled inspection
Start date: 2019-03-05, end date: 2019-03-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803338422
Unscheduled inspection
Start date: 2019-02-18, end date: —, duration:
Authority:
Purpose of inspection:


# 161902437911
Unscheduled inspection
Start date: 2019-01-18, end date: 2019-01-30, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 12092018 case 121120180093 The objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out the reconstruction on the basis of a contract with the developer or the customer of the work performed during the construction of the capital construction facility. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts


# 161802221602
Unscheduled inspection
Start date: 2018-12-13, end date: 2018-12-14, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules for determining the fact of execution of the order, as well as for the purpose of drawing up an act on the elimination of violations of the order based on the notice received by the Inspectorate from 29112018 9255 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by The objectives of this audit are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts, and the compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations and other regulatory legal acts. According to the project documentation, the subject of this audit is to select the necessary fulfillment of the instructions of the state control bodies, supervision bodies of municipal control


# 161802092491
Unscheduled inspection
Start date: 2018-11-19, end date: 2018-11-21, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 12092018 case 121120180093 The objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out the reconstruction on the basis of a contract with the developer or the customer of the work performed during the construction of the capital construction facility. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts


Information about inspections