Found 3 inspections:

# 372004453997
Unscheduled inspection
Start date: 2020-07-09, end date: 2020-07-10, duration: 2
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora Ivanovskoi oblasti
Purpose of inspection: Assessment of compliance of the performed works and applied building materials with the requirements of the design documentation and the inspection program Prevention detection and suppression of violations of the legislation on urban development and project documentation committed by the developer or the person carrying out construction Compliance with mandatory requirements and or requirements established by municipal legal acts


# 47170803018020
Unscheduled inspection
Start date: 2017-12-21, end date: 2018-01-25, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for energy resources used to meet the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 47170701338207
Unscheduled inspection
Start date: 2017-01-30, end date: 2017-02-28, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the work on the start of construction reconstruction of the capital construction facility specified in the notice of the developer or technical customer on the start of construction reconstruction The subject of this check is compliance with mandatory requirements including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation including energy efficiency requirements and requirements for the equipment of the capital construction facility with accounting devices for the energy resources used, compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.