Found 118 inspections:

# 662101419919
Unscheduled inspection
Start date: 2021-12-07, end date: —, duration:
Authority:
Purpose of inspection:


# 662101420483
Unscheduled inspection
Start date: 2021-12-07, end date: —, duration:
Authority:
Purpose of inspection:


# 662101350433
Unscheduled inspection
Start date: 2021-11-22, end date: 2021-12-17, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Ustanovit, chto nastoyaschaya proverka provoditsya s celyu realizacii programmy proverok № 29-19-24/257-21 ot 13.09.2021, zadachei nastoyaschei proverki yavlyaetsya: osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora. Predmetom nastoyaschei proverki yavlyaetsya: proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «3-h etazhnyi mnogokvartirnyi zhiloi dom», raspolozhennogo po adresu: Sverdlovskaya oblast, Novolyalinskii raion, p. Lobva, ul. Kuznecova, 6a, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; nalichiya razresheniya na stroitelstvo; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii.


# 662100961237
Unscheduled inspection
Start date: 2021-10-04, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 662100954040
Unscheduled inspection
Start date: 2021-10-04, end date: 2021-10-29, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel - realizacii programmy provedeniya proverok № 29-19-17/285-20 ot 2020-10-08; Zadachi - osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora; Predmet - proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva: Mnogokvartirnyi zhiloi dom, raspolozhennyi po adresu: Sverdlovskaya oblast, g. Krasnoturinsk, raspolozhennyi primerno v 20 metrah ot orientira ul. Oktyabrskaya, 52 na vostok. 2 etap , raspolozhennogo po adresu: Sverdlovskaya oblast, g. Krasnoturinsk, ustanovleno otnositelno orientira, raspolozhennogo za predelami uchastka. Orientir zhiloi dom. Uchastok nahoditsya primerno v 20 metrah ot orientira po napravleniyu na vostok. Pochtovyi adres orientira: Sverdlovskaya oblast, g. Krasnoturinsk, ul. Oktyabrskaya, d. 52, rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii, v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; nalichiya razresheniya na stroitelstvo; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii.


# 662101045746
Unscheduled inspection
Start date: 2021-10-05, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 662101236377
Unscheduled inspection
Start date: 2021-10-22, end date: —, duration:
Authority:
Purpose of inspection:


# 662101236317
Unscheduled inspection
Start date: 2021-10-22, end date: 2021-11-22, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Ustanovit, chto nastoyaschaya proverka provoditsya na osnovanii izvescheniya ob okonchanii stroitelstva obekta kapitalnogo stroitelstva vh. № 29-01-41/45910 ot 18.10.2021, v sootvetstvii s programmoi provedeniya proverok ot 05.10.2020 № 29-19-17/284-20 zadachei nastoyaschei proverki yavlyaetsya: osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora. Predmetom nastoyaschei proverki yavlyaetsya: proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «ZHiloi kompleks, raspolozhennyi po adresu: Sverdlovskaya oblast, g. Krasnouralsk, ul. CHehova. I etap stroitelstva », raspolozhennogo po adresu: Sverdlovskaya oblast, g. Krasnouralsk, ul. CHehova, dom 15/1, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; nalichiya razresheniya na stroitelstvo; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii.


# 662100555049
Unscheduled inspection
Start date: 2021-09-01, end date: —, duration:
Authority:
Purpose of inspection:


# 662100438770
Unscheduled inspection
Start date: 2021-08-12, end date: 2021-09-08, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel - realizacii programmy provedeniya proverok № 29-19-17/166-20 ot 2020-09-30; Zadachi - osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora; Predmet - proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva: 3-h etazhnyi mnogokvartirnyi zhiloi dom, raspolozhennogo po adresu: Sverdlovskaya oblast, Novolyalinskii raion, p. Lobva, ul. Bazhova, 12 (korpus 2), rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii, v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; nalichiya razresheniya na stroitelstvo; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii.


# 662100254368
Unscheduled inspection
Start date: 2021-06-07, end date: 2021-07-05, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel - realizacii programmy provedeniya proverok № 29-19-17/196-20 ot 2020-07-24; Zadachi - osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora; Predmet - proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva: Mnogokvartirnyi zhiloi dom, raspolozhennyi po adresu: Sverdlovskaya oblast, g. Krasnoturinsk, raspolozhennyi primerno v 20 metrah ot orientira ul. Oktyabrskaya, 52 na vostok. 1 etap, raspolozhennogo po adresu: Sverdlovskaya oblast, g. Krasnoturinsk, ustanovleno otnositelno orientira, raspolozhennogo za predelami uchastka. Orientir zhiloi dom. Uchastok nahoditsya primerno v 20 metrah ot orientira po napravleniyu na vostok. Pochtovyi adres orientira: Sverdlovskaya oblast, g. Krasnoturinsk, ul. Oktyabrskaya, d. 52, rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii, v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; nalichiya razresheniya na stroitelstvo; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii.


# 662100254150
Unscheduled inspection
Start date: 2021-06-07, end date: 2021-07-05, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel - realizacii programmy provedeniya proverok № 29-19-17/379-20 ot 2020-12-07; Zadachi - osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora; Predmet - proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva: 3-h etazhnyi mnogokvartirnyi zhiloi dom, raspolozhennogo po adresu: Sverdlovskaya oblast, g. Nizhnyaya Tura, ul. 40 let Oktyabrya, № 21a, rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii, v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; nalichiya razresheniya na stroitelstvo; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii.


# 662100254356
Unscheduled inspection
Start date: 2021-06-07, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 662100254320
Unscheduled inspection
Start date: 2021-06-07, end date: —, duration:
Authority:
Purpose of inspection:


# 662100254331
Unscheduled inspection
Start date: 2021-06-07, end date: —, duration:
Authority:
Purpose of inspection:


# 662100230763
Unscheduled inspection
Start date: 2021-06-07, end date: 2021-06-17, duration: 11
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel - kontrol ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 26.02.2021 № 29-18-29/15.1 vydannogo OOO «ZHilstroikompleks», Zadachi: osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora. Predmet: vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 26.02.2021 № 29-18-29/15.1.


# 662100207501
Unscheduled inspection
Start date: 2021-05-17, end date: 2021-05-28, duration: 10
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to control the execution of a previously issued instruction on the elimination of identified violations; Tasks - the implementation of regional state construction supervision; Subject - the implementation of a previously issued instruction on the elimination of an identified violation of mandatory requirements


# 662100207316
Unscheduled inspection
Start date: 2021-05-17, end date: 2021-06-11, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel - realizacii programmy provedeniya proverok № 29-19-17/284-20 ot 2020-10-05; Zadachi - osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora; Predmet - proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva: ZHiloi kompleks, raspolozhennyi po adresu: Sverdlovskaya oblast, g. Krasnouralsk, ul. CHehova. I etap stroitelstva , raspolozhennogo po adresu: Sverdlovskaya oblast, g. Krasnouralsk, ul. CHehova, dom 15/1, rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii, v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; nalichiya razresheniya na stroitelstvo; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii.


# 662100111291
Unscheduled inspection
Start date: 2021-04-12, end date: 2021-04-23, duration: 12
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to control the execution of a previously issued instruction on the elimination of identified violations; Tasks - the implementation of regional state construction supervision; Subject - the implementation of a previously issued instruction on the elimination of an identified violation of mandatory requirements


# 662100000914
Unscheduled inspection
Start date: 2021-02-15, end date: 2021-03-16, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel - realizacii programmy provedeniya proverok № 29-19-17/284-20 ot 2020-10-05; Zadachi - osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora; Predmet - proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva: ZHiloi kompleks, raspolozhennyi po adresu: Sverdlovskaya oblast, g. Krasnouralsk, ul. CHehova. I etap stroitelstva , raspolozhennogo po adresu: Sverdlovskaya oblast, g. Krasnouralsk, ul. CHehova, dom 15/1, rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii, v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; nalichiya razresheniya na stroitelstvo; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii.


# 662105330953
Unscheduled inspection
Start date: 2021-02-01, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 662105330949
Unscheduled inspection
Start date: 2021-02-01, end date: 2021-03-01, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel - realizacii programmy provedeniya proverok № 29-19-17/285-20 ot 2020-10-08; Zadachi - osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora; Predmet - proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva: Mnogokvartirnyi zhiloi dom, raspolozhennyi po adresu: Sverdlovskaya oblast, g. Krasnoturinsk, raspolozhennyi primerno v 20 metrah ot orientira ul. Oktyabrskaya, 52 na vostok. 2 etap , raspolozhennogo po adresu: Sverdlovskaya oblast, g. Krasnoturinsk, ustanovleno otnositelno orientira, raspolozhennogo za predelami uchastka. Orientir zhiloi dom. Uchastok nahoditsya primerno v 20 metrah ot orientira po napravleniyu na vostok. Pochtovyi adres orientira: Sverdlovskaya oblast, g. Krasnoturinsk, ul. Oktyabrskaya, d. 52, rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii, v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; nalichiya razresheniya na stroitelstvo; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii.


# 662105330957
Unscheduled inspection
Start date: 2021-02-01, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 662005243674
Unscheduled inspection
Start date: 2020-12-01, end date: 2020-12-28, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizacii programmy provedeniya proverok 29191728420 ot 20201005 Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmet proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva ZHiloi kompleks raspolozhennyi po adresu Sverdlovskaya oblast g Krasnouralsk ul CHehova I etap stroitelstva raspolozhennogo po adresu Sverdlovskaya oblast g Krasnouralsk ul CHehova dom 151 rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 662005221074
Unscheduled inspection
Start date: 2020-12-01, end date: —, duration:
Authority:
Purpose of inspection:


# 662005221059
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-12-18, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Proverka provoditsya s celyu realizacii programmy proverok 29191716620 ot 30092020 Izmenenie 1 zadachei nastoyaschei proverki yavlyaetsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «3h etazhnyi mnogokvartirnyi zhiloi dom» raspolozhennogo po adresu Sverdlovskaya oblast Novolyalinskii raion p Lobva ul Bazhova 12 korpus 2 a takzhe rezultatov takih rabot ukazannym v punkte 1 chasti 5 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii trebovaniyam proektnoi dokumentacii vklyuchaya proektnuyu dokumentaciyu v kotoroi uchteny izmeneniya vnesennye v sootvetstvii s chastyami 38 i 39 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov


# 662005214224
Unscheduled inspection
Start date: 2020-11-09, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 662005216757
Unscheduled inspection
Start date: 2020-11-10, end date: 2020-12-07, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizaciya izvescheniya ob okonchanii stroitelstva obekta kapitalnogo stroitelstva 29018240516 ot 29102020 v sootvetstvii s programmoi provedeniya proverok ot 27082019 29180128019 podpunkt «a» punkta 2 chasti 5 stati 54 Gradostroitelnogo kodeksa Rossiiskoi Federacii Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmet proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Kompleks mnogokvartirnyh zhilyh domov korpus 1 i 2 raspolozhennyi v granicah ulic Pushkinskaya CHkalova v g Turinsk Sverdlovskoi oblasti Korpus 2 2 etap stroitelstva» raspolozhennogo po adresu Sverdlovskaya oblast Turinskii raion gorod Turinsk ul Pushkinskaya 6 a takzhe rezultatov takih rabot utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 662005216708
Unscheduled inspection
Start date: 2020-11-10, end date: 2020-12-07, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizaciya izvescheniya ob okonchanii stroitelstva obekta kapitalnogo stroitelstva 29018240515 ot 29102020 v sootvetstvii s programmoi provedeniya proverok ot 20112019 29180139819 podpunkt «a» punkta 2 chasti 5 stati 54 Gradostroitelnogo kodeksa Rossiiskoi Federacii Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmet proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Kompleks mnogokvartirnyh zhilyh domov korpus 3 raspolozhennyi po adresu Sverdlovskaya oblast g Turinsk v granicah ulic Pushkinskaya CHkalova» raspolozhennogo po adresu Sverdlovskaya oblast Turinskii raion gorod Turinsk ul Pushkinskaya 4v a takzhe rezultatov takih rabot utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 662005184499
Unscheduled inspection
Start date: 2020-10-19, end date: 2020-11-16, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizacii programmy provedeniya proverok 29160138119 ot 20191101 Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmet proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva 3h etazhnyi mnogokvartirnyi zhiloi dom raspolozhennyi po adresu Sverdlovskaya oblast SHalinskii gorodskoi okrug rp SHalya ul Lenina 1 metr na sever ot orientira doma 15 po ul Lenina raspolozhennogo po adresu Sverdlovskaya oblast pgt SHalya ul Lenina 15V rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 662005153254
Unscheduled inspection
Start date: 2020-10-05, end date: 2020-10-30, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizacii programmy provedeniya proverok 29190134919 ot 20191011 Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmet proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva 3h etazhnyi mnogokvartirnyi zhiloi dom raspolozhennyi po adresu Sverdlovskaya oblast g Volchansk ul Parkovaya 16 raspolozhennogo po adresu Sverdlovskaya oblast g Volchansk ul Parkovaya 16 rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 662004459125
Unscheduled inspection
Start date: 2020-07-22, end date: —, duration:
Authority:
Purpose of inspection:


# 662004432704
Unscheduled inspection
Start date: 2020-06-18, end date: —, duration:
Authority:
Purpose of inspection:


# 662004432683
Unscheduled inspection
Start date: 2020-06-18, end date: —, duration:
Authority:
Purpose of inspection:


# 662004400890
Unscheduled inspection
Start date: 2020-05-06, end date: 2020-05-29, duration: 17
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizacii programmy provedeniya proverok 29190139719 ot 15112019 Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmet proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva 3h etazhnyi mnogokvartirnyi zhiloi dom raspolozhennogo po adresu Novolyalinskii rn p Lobva ul Bazhova dom 7 rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 662004402253
Unscheduled inspection
Start date: 2020-05-12, end date: —, duration:
Authority:
Purpose of inspection:


# 662004402250
Unscheduled inspection
Start date: 2020-05-12, end date: —, duration:
Authority:
Purpose of inspection:


# 662004400435
Unscheduled inspection
Start date: 2020-04-27, end date: —, duration:
Authority:
Purpose of inspection:


# 662004366882
Unscheduled inspection
Start date: 2020-04-02, end date: —, duration:
Authority:
Purpose of inspection:


# 662004366968
Unscheduled inspection
Start date: 2020-04-02, end date: 2020-04-08, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel kontrol ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 21022020 29182210 Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmet vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 21022020 29182210


# 662004366148
Unscheduled inspection
Start date: 2020-04-02, end date: 2020-04-09, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel kontrol ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 18022020 2918225 Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmet vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 18022020 2918225


# 662004399436
Unscheduled inspection
Start date: 2020-04-21, end date: 2020-05-15, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizaciya programmy provedeniya proverok ot 20112019 29180139819 Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Kompleks mnogokvartirnyh zhilyh domov korpus 3 raspolozhennyi po adresu Sverdlovskaya oblast g Turinsk v granicah ulic Pushkinskaya CHkalova» raspolozhennogo po adresu Sverdlovskaya oblast Turinskii raion gorod Turinsk ulica Pushkinskaya 4v a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 662004367116
Unscheduled inspection
Start date: 2020-03-23, end date: 2020-04-10, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizaciya izvescheniya zastroischika o nachale stroitelstva obekta kapitalnogo stroitelstva vh 38136 ot 20082019 Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmet proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Kompleks mnogokvartirnyh zhilyh domov korpus 1 i 2 raspolozhennyi v granicah ulic Pushkinskaya CHkalova v g Turinsk Sverdlovskoi oblasti Korpus 2 2 etap stroitelstva» raspolozhennogo po adresu Sverdlovskaya oblast Turinskii raion gorod Turinsk ulica Pushkinskaya 6 a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 662004347830
Unscheduled inspection
Start date: 2020-03-10, end date: —, duration:
Authority:
Purpose of inspection:


# 662004256438
Unscheduled inspection
Start date: 2020-02-06, end date: 2020-03-05, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizacii programmy provedeniya proverok 29190130319 ot 20190909 Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmet proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva 5ti etazhnyi mnogokvartirnyi zhiloi dom raspolozhennyi po adresu Sverdlovskaya oblast g Volchansk ul Pionerskaya 2 raspolozhennogo po adresu Sverdlovskaya oblast g Volchansk ul Pionerskaya 2 rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 662004256196
Unscheduled inspection
Start date: 2020-02-06, end date: —, duration:
Authority:
Purpose of inspection:


# 662004220335
Unscheduled inspection
Start date: 2020-02-06, end date: —, duration:
Authority:
Purpose of inspection:


# 662004219903
Unscheduled inspection
Start date: 2020-02-06, end date: 2020-02-13, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel kontrol ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 20122019 291807402 P Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 20122019 291807402 P


# 662004219440
Unscheduled inspection
Start date: 2020-02-03, end date: —, duration:
Authority:
Purpose of inspection:


# 662004285467
Unscheduled inspection
Start date: 2020-02-17, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 662004199400
Unscheduled inspection
Start date: 2020-01-29, end date: 2020-02-18, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizaciya izvescheniya zastroischika o nachale stroitelstva obekta kapitalnogo stroitelstva vh 38136 ot 20082019 Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmet proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Kompleks mnogokvartirnyh zhilyh domov korpus 1 i 2 raspolozhennyi v granicah ulic Pushkinskaya CHkalova v g Turinsk Sverdlovskoi oblasti Korpus 2 2 etap stroitelstva» raspolozhennogo po adresu Sverdlovskaya oblast Turinskii raion gorod Turinsk ulica Pushkinskaya 6 a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 662004212873
Unscheduled inspection
Start date: 2020-01-22, end date: 2020-02-18, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizacii programmy provedeniya proverok 29190139719 ot 20191115 Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmet proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva 3h etazhnyi mnogokvartirnyi zhiloi dom raspolozhennogo po adresu Novolyalinskii rn p Lobva ul Bazhova dom 7 rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 662004194183
Unscheduled inspection
Start date: 2020-01-20, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 661904032361
Unscheduled inspection
Start date: 2019-12-03, end date: 2019-12-11, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel kontrol ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 22102019 291807307 P Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmet vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 22102019 291807307 P


# 661904032820
Unscheduled inspection
Start date: 2019-12-02, end date: 2019-12-20, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizaciya izvescheniya zastroischika o nachale stroitelstva obekta kapitalnogo stroitelstva vh 52594 ot 12112019 Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmet proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Kompleks mnogokvartirnyh zhilyh domov korpus 3 raspolozhennyi po adresu Sverdlovskaya oblast g Turinsk v granicah ulic Pushkinskaya CHkalova» raspolozhennogo po adresu Sverdlovskaya oblast Turinskii raion gorod Turinsk ulica Pushkinskaya 4v a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 661903966019
Unscheduled inspection
Start date: 2019-11-20, end date: 2019-12-17, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel KNM proverka provoditsya s celyu realizacii programmy provedeniya proverok 29190134919 ot 11102019 zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «3h etazhnyi mnogokvartirnyi zhiloi dom raspolozhennyi po adresu Sverdlovskaya oblast g Volchansk ul Parkovaya 16» raspolozhennogo po adresu Sverdlovskaya oblast g Volchansk ul Parkovaya 16 a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 661903965797
Unscheduled inspection
Start date: 2019-11-20, end date: 2019-12-17, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel KNM proverka provoditsya s celyu realizacii programmy provedeniya proverok 29190130319 ot 09092019 zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «5ti etazhnyi mnogokvartirnyi zhiloi dom» raspolozhennogo po adresu Sverdlovskaya oblast g Volchansk ul Pionerskaya 2 a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 661904032769
Unscheduled inspection
Start date: 2019-11-28, end date: —, duration:
Authority:
Purpose of inspection:


# 661903567827
Unscheduled inspection
Start date: 2019-09-17, end date: 2019-10-07, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizaciya izvescheniya zastroischika o nachale stroitelstva obekta kapitalnogo stroitelstva vh 45107 ot 19102018 zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmet proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Kompleks mnogokvartirnyh zhilyh domov korpus 1 i 2 raspolozhennyi v granicah ulic Pushkinskaya CHkalova v g Turinsk Sverdlovskoi oblasti Korpus 1 pervyi etap stroitelstva» raspolozhennogo po adresu Sverdlovskaya oblast Turinskii raion gorod Turinsk ulica Pushkinskaya 6 a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 661903565944
Unscheduled inspection
Start date: 2019-09-17, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 661903623453
Unscheduled inspection
Start date: 2019-09-25, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 661903568387
Unscheduled inspection
Start date: 2019-09-25, end date: —, duration:
Authority:
Purpose of inspection:


# 661903625703
Unscheduled inspection
Start date: 2019-09-24, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 661902815504
Unscheduled inspection
Start date: 2019-07-01, end date: —, duration:
Authority:
Purpose of inspection:


# 661902756344
Unscheduled inspection
Start date: 2019-06-03, end date: 2019-06-17, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel KNM proverka provoditsya s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 29190744 ot 11 marta 2019 goda Predmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 29190744 ot 11 marta 2019 goda zadachei nastoyaschei proverki yavlyaetsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora


# 661902756273
Unscheduled inspection
Start date: 2019-06-03, end date: 2019-06-17, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel KNM proverka provoditsya s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 29190743 ot 11 marta 2019 goda Predmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 29190743 ot 11 marta 2019 goda zadachei nastoyaschei proverki yavlyaetsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora


# 661902815208
Unscheduled inspection
Start date: 2019-06-27, end date: 2019-07-05, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel kontrol ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 30042019 291807116 P zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 30042019 291807116 P so srokom ispolneniya predpisaniya do 17062019


# 661902785816
Unscheduled inspection
Start date: 2019-05-15, end date: 2019-06-11, duration:
Authority: Gosudarstvennaya inspekciya truda v Sverdlovskoi oblasti
Purpose of inspection: zaschity prav i interesov rabotnikov v svyazi s postupleniem obrascheniya 667273319OB


# 661902715020
Unscheduled inspection
Start date: 2019-05-13, end date: 2019-06-07, duration:
Authority: Gosudarstvennaya inspekciya truda v Sverdlovskoi oblasti
Purpose of inspection: protection of the rights and interests of employees in connection with the consideration of an application for violation of labor rights supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms compliance with mandatory requirements and or requirements established by municipal legal acts


# 661902735873
Unscheduled inspection
Start date: 2019-05-27, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 661902629243
Unscheduled inspection
Start date: 2019-04-10, end date: 2019-04-30, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizaciya programmy provedeniya proverok 29180145718 ot 31102018 Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmet proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva «Kompleks mnogokvartirnyh zhilyh domov korpus 1 i 2 raspolozhennyi v granicah ulic Pushkinskaya CHkalova v g Turinsk Sverdlovskoi oblasti Korpus 1 pervyi etap stroitelstva» rezultatov takih rabot trebovaniyam proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov a takzhe nalichiya razresheniya na stroitelstvo i vypolneniya trebovanii chastei 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 661902666944
Unscheduled inspection
Start date: 2019-04-22, end date: 2019-04-26, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel kontrol ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 11032019 29180752 P Zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmet vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 11032019 29180752 P so srokom ispolneniya predpisaniya do 19042019


# 661902667187
Unscheduled inspection
Start date: 2019-04-23, end date: —, duration:
Authority:
Purpose of inspection:


# 661902573518
Unscheduled inspection
Start date: 2019-03-20, end date: 2019-04-16, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: cel realizacii programmy provedeniya proverok 29190153918 ot 20122018 zadacha osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmet proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva «3h etazhnyi mnogokvartirnyi zhiloi dom korpus 1» raspolozhennogo po adresu Sverdlovskaya oblast poselok Lobva ul Bazhova 12 korpus 1 rezultatov takih rabot trebovaniyam proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov a takzhe nalichiya razresheniya na stroitelstvo i vypolneniya trebovanii chastei 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 661902489994
Unscheduled inspection
Start date: 2019-02-11, end date: —, duration:
Authority:
Purpose of inspection:


# 661902495719
Unscheduled inspection
Start date: 2019-02-12, end date: 2019-03-11, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel realizaciya izvescheniya zastroischika o nachale stroitelstva obekta kapitalnogo stroitelstva vh 45107 ot 19102018 zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmet proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva «Kompleks mnogokvartirnyh zhilyh domov korpus 1 i 2 raspolozhennyi v granicah ulic Pushkinskaya CHkalova v g Turinsk Sverdlovskoi oblasti Korpus 1 pervyi etap stroitelstva» rezultatov takih rabot trebovaniyam proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov a takzhe nalichiya razresheniya na stroitelstvo i vypolneniya trebovanii chastei 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 661902495918
Unscheduled inspection
Start date: 2019-02-12, end date: 2019-02-18, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel kontrol ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 20122018 291807399 zadachi osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmet vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii ot 20122018 291807399 so srokom ispolneniya predpisaniya do 08022019


# 661902524227
Unscheduled inspection
Start date: 2019-02-18, end date: 2019-03-18, duration:
Authority: Gosudarstvennaya inspekciya truda v Sverdlovskoi oblasti
Purpose of inspection: protection of the rights and interests of employees in connection with the consideration of an application for violation of labor rights supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms compliance with mandatory requirements and or requirements established by municipal legal acts


# 661802153697
Unscheduled inspection
Start date: 2018-11-23, end date: —, duration:
Authority:
Purpose of inspection:


# 661801951217
Unscheduled inspection
Start date: 2018-10-17, end date: —, duration:
Authority:
Purpose of inspection:


# 661801133129
Unscheduled inspection
Start date: 2018-09-12, end date: 2018-10-09, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel KNM proverka provoditsya na osnovanii izvescheniya ob okonchanii stroitelstva obekta kapitalnogo stroitelstva vh 29018236818 ot 03 sentyabrya 2018 goda v sootvetstvii s polozheniyami podpunkta «a» punkta 2 chasti 5 stati 54 Gradostroitelnogo kodeksa Rossiiskoi Federacii zadachi KNM osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva «3h etazhnyi mnogokvartirnyi dvuhsekcionnyi zhiloi dom korpus 4» raspolozhennogo po adresu Sverdlovskaya oblast gorod Novaya Lyalya ul Sosnovyi bor 15 korpus 4 rezultatov takih rabot trebovaniyam proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov a takzhe nalichiya razresheniya na stroitelstvo i vypolneniya trebovanii chastei 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 661800663726
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-09-07, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: celi proverki kontrol ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii ot 02 iyulya 2018 goda 291907178 zadachi proverki osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora predmet proverki vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii ot 02 iyulya 2018 goda 291907178


# 661800549816
Unscheduled inspection
Start date: 2018-07-17, end date: 2018-07-27, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: cel kontrol ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii ot 10 maya 2018 goda 291907129 zadacha osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmet vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii ot 10 maya 2018 goda 291907129


# 661800585776
Unscheduled inspection
Start date: 2018-07-31, end date: 2018-08-10, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 291607385P1 ot 22 iyunya 2018 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 291607385P1 ot 22 iyunya 2018 goda


# 661800574037
Unscheduled inspection
Start date: 2018-07-26, end date: —, duration:
Authority:
Purpose of inspection:


# 661800400013
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-07-13, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu realizacii programmy provedeniya proverok 2916018161 ot 09 dekabrya 2016 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva «ZHilaya zastroika po adresu Sverdlovskaya oblast g Berezovskii ul Novaya uch 20 1 etap stroitelstva 2 ochered stroitelstva Sekciya 3» raspolozhennogo po adresu Sverdlovskaya obl g Berezovskii ul Novaya d 20 rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov a takzhe nalichiya razresheniya na stroitelstvo i vypolneniya trebovanii chastei 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 661800480290
Unscheduled inspection
Start date: 2018-06-25, end date: 2018-07-06, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu realizacii programmy provedeniya proverok ot 09 dekabrya 2016 goda 2916018161 zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva «ZHilaya zastroika po adresu Sverdlovskaya oblast g Berezovskii ul Novaya uch 20 1 etap stroitelstva 2 ochered stroitelstva Sekciya 3» raspolozhennogo po adresu Sverdlovskaya oblast g Berezovskii ul Novaya dom 20 rezultatov takih rabot trebovaniyam tehnicheskih reglamentov sanitarnoepidemiologicheskim pravilam i normativam pravilam bezopasnosti i gosudarstvennym standartam proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov a takzhe nalichiya razresheniya na stroitelstvo i vypolneniya trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 661800280666
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-04-20, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: cel proverki kontrol ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii ot 05 marta 2018 goda 29190736 zadacha proverki osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora predmet proverki vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii ot 05 marta 2018 goda 29190736


# 661800231650
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-04-27, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 29160776P1 ot 14 marta 2018 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 29160776P1 ot 14 marta 2018 goda


# 661800295877
Unscheduled inspection
Start date: 2018-04-23, end date: 2018-05-23, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Cel KNM proverka provoditsya s celyu realizacii programmy provedeniya proverok ot 07032018 2919018618 Zadachi KNM osuschestvlenie gosudarstvennogo stroitelnogo nadzora Predmet KNM proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva «3h etazhnyi mnogokvartirnyi dvuhsekcionnyi zhiloi dom korpus 4» raspolozhennogo po adresu Sverdlovskaya oblast g Novaya Lyalya ul Sosnovyi bor 15 korpus 4 rezultatov takih rabot trebovaniyam tehnicheskih reglamentov sanitarnoepidemiologicheskim pravilam i normativam trebovaniyam pozharnoi bezopasnosti pravilam bezopasnosti i gosudarstvennym standartam proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov a takzhe nalichiya razresheniya na stroitelstvo i vypolneniya trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 661800049870
Unscheduled inspection
Start date: 2018-02-12, end date: 2018-03-14, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu realizacii programmy provedeniya proverok 2916018161 ot 09 dekabrya 2016 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva «ZHilaya zastroika po adresu Sverdlovskaya oblast g Berezovskii ul Novaya uch 20 1 etap stroitelstva 2 ochered stroitelstva Sekciya 3» raspolozhennogo po adresu Sverdlovskaya oblast gorod Berezovskii ulica Novaya dom 20 rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov a takzhe nalichiya razresheniya na stroitelstvo i vypolneniya trebovanii chastei 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 66170802924681
Unscheduled inspection
Start date: 2017-12-11, end date: 2017-12-22, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 291605684 P1 ot 10 noyabrya 2017 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 291605684 P1 ot 10 noyabrya 2017 goda


# 66170802267740
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-11-10, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu realizacii programmy provedeniya proverok ot 09122016 2916018161 zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva


# 66170802267111
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-11-10, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu realizacii programmy provedeniya proverok ot 21062016 29160119116 zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva


# 66170802422227
Unscheduled inspection
Start date: 2017-09-14, end date: 2017-10-11, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: s celyu realizacii programmy provedeniya proverok 2918015517 ot 02 marta 2017 goda a takzhe na osnovanii izvescheniya ob okonchanii stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva 35484 ot 05 sentyabrya 2017g zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva «5 etazhnyi mnogokvartirnyi 2h sekcionnyi zhiloi dom» raspolozhennogo po adresu Sverdlovskaya oblast g Turinsk ul Puteicev d 26


# 66170802192017
Unscheduled inspection
Start date: 2017-09-12, end date: 2017-09-15, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 291605610P1 ot 08 avgusta 2017 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 291605610P1 ot 08 avgusta 2017 goda


# 66170801934856
Unscheduled inspection
Start date: 2017-09-07, end date: 2017-09-15, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 291605429 P1 ot 11 avgusta 2017 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 291605429 P1 ot 11 avgusta 2017 goda


# 66170801966882
Unscheduled inspection
Start date: 2017-09-05, end date: 2017-10-02, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: checking the completed construction of the object


# 66170701869027
Unscheduled inspection
Start date: 2017-08-08, end date: 2017-08-10, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii 291805254 ot 21 iyunya 2017 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii 291805254 ot 21 iyunya 2017 goda


# 66170701863987
Unscheduled inspection
Start date: 2017-08-08, end date: 2017-08-21, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 291905147 ot 29 iyunya 2017 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 291905147 ot 29 iyunya 2017 goda


# 66170701866431
Unscheduled inspection
Start date: 2017-08-07, end date: 2017-08-18, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Proverka provoditsya s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 29190593 ot 17 maya 2017 goda Predmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii 29190593 ot 17 maya 2017 goda zadachei nastoyaschei proverki yavlyaetsya osuschestvlenie gosudarstvennogo stroitelnogo nadzora


# 66170701737974
Unscheduled inspection
Start date: 2017-07-17, end date: 2017-08-11, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu realizacii programmy provedeniya proverok 29160119116 ot 21 iyunya 2016 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva


# 66170701777638
Unscheduled inspection
Start date: 2017-07-10, end date: 2017-08-04, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: s celyu realizacii programmy provedeniya proverok 29180141016 ot 17 oktyabrya 2016 goda a takzhe na osnovanii izvescheniya ob okonchanii stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva 25423 ot 30 iyunya 2017 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva «5 etazhnyi mnogokvartirnyi 2h sekcionnyi zhiloi dom» raspolozhennogo po adresu Sverdlovskaya oblast g Turinsk ul Lenina d121


# 66170701777687
Unscheduled inspection
Start date: 2017-07-11, end date: 2017-07-24, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: s celyu realizacii programmy provedeniya proverok 2918015517 ot 02 marta 2017 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva «5 etazhnyi mnogokvartirnyi 2h sekcionnoi zhiloi» raspolozhennogo po adresu Sverdlovskaya oblast g Turinsk ul Puteicev d 26 rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov a takzhe nalichiya razresheniya na stroitelstvo i vypolneniya trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 66170701692700
Unscheduled inspection
Start date: 2017-06-08, end date: 2017-06-15, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: kontrol ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii 291805105 ot 26 aprelya 2017 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii 291805105 ot 26 aprelya 2017 goda


# 66170701692758
Unscheduled inspection
Start date: 2017-06-08, end date: 2017-06-15, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: kontrol ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii 291805104 ot 25 aprelya 2017 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzoraPredmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii 291805104 ot 25 aprelya 2017 goda


# 66170701692558
Unscheduled inspection
Start date: 2017-06-07, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 66170701692632
Unscheduled inspection
Start date: 2017-06-07, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 66170701653223
Unscheduled inspection
Start date: 2017-06-01, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 66170701545718
Unscheduled inspection
Start date: 2017-04-18, end date: —, duration:
Authority:
Purpose of inspection:


# 66170701545792
Unscheduled inspection
Start date: 2017-04-18, end date: —, duration:
Authority:
Purpose of inspection:


# 66170701529686
Unscheduled inspection
Start date: 2017-04-24, end date: —, duration:
Authority:
Purpose of inspection:


# 66170701458962
Unscheduled inspection
Start date: 2017-03-16, end date: 2017-03-21, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii 29170523 ot 30 yanvarya 2017 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora Predmetom nastoyaschei proverki yavlyaetsya vypolnenie ranee vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovanii 29180523 ot 30 yanvarya 2017 goda


# 66170701458832
Unscheduled inspection
Start date: 2017-03-16, end date: 2017-03-29, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: realizaciya programmy provedeniya proverok 29180141016 ot 17 oktyabrya 2016 goda zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie regionalnogo gosudarstvennogo stroitelnogo nadzora7Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenimyh stroitelnyh materialov pri stroitelstve obekta kapitalnogo stroitelstva «5 etazhnyi mnogokvartirnyi 2h sekcionnoi zhiloi» raspolozhennogo po adresu Sverdlovskaya oblast g Turinsk ul Lenina d121 rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov a takzhe nalichiya razresheniya na stroitelstvo i vypolneniya trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 66170701458478
Unscheduled inspection
Start date: 2017-03-16, end date: —, duration:
Authority:
Purpose of inspection:


# 66170701293900
Unscheduled inspection
Start date: 2017-01-11, end date: 2017-01-20, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Dlya dostizheniya celei provedeniya proverki obekta kapitalnogo stroitelstva dolzhnostnomu licu upolnomochennomu na provedenie proverkia rassmotret predstavlennye zastroischikom zakazchikom licom osuschestvlyayuschim stroitelstvo dlya provedeniya proverki obekta kapitalnogo stroitelstva dokumenty svyazannye s vypolneniem rabot vklyuchaya otdelnye raboty stroitelnye konstrukcii uchastki setei inzhenernotehnicheskogo obespecheniya a takzhe primeneniem stroitelnyh materialov izdelii a imenno obschii i ili specialnyi zhurnaly v kotoryh vedetsya uchet vypolneniya rabot ispolnitelnuyu dokumentaciyu v tom chisle akty osvidetelstvovaniya rabot konstrukcii uchastkov setei inzhenernotehnicheskogo obespecheniya okazyvayuschih vliyanie na bezopasnost kontrol za vypolneniem kotoryh ne mozhet byt proveden posle vypolneniya drugih rabot a takzhe bez razborki ili povrezhdeniya stroitelnyh konstrukcii i uchastkov setei inzhenernotehnicheskogo obespecheniya akty ispytaniya i oprobovaniya tehnicheskih ustroistv sistem akty predpisaniya izvescheniya ob ustranenii narushenii nedostatkov vyyavlennyh pri osuschestvlenii gosudarstvennogo stroitelnogo nadzora i provedenii stroitelnogo kontrolya rezultaty ekspertiz obsledovanii laboratornyh i inyh ispytanii vypolnennyh rabot provedennyh v processe stroitelnogo kontrolya dokumenty podtverzhdayuschie provedenie kontrolya za kachestvom primenyaemyh stroitelnyh materialov dokumenty podtverzhdayuschie ispolnenie postanovlenii po delam ob administrativnyh pravonarusheniyah a takzhe uchreditelnye i organizacionnorasporyaditelnye dokumenty yuridicheskih lic individualnyh predprinimatelei svyazannye s osuschestvleniem deyatelnosti po stroitelstvu obekta kapitalnogo stroitelstva dokumenty podtverzhdayuschie polnomochiya predstaviteleib provesti vizualnyi osmotr vypolnennyh rabot obekta kapitalnogo stroitelstva v polnom obeme vklyuchaya otdelnye vypolnennye raboty stroitelnye konstrukcii uchastki setei inzhenernotehnicheskogo obespecheniya i primenennye stroitelnye materialy izdeliya proveriv soblyudenie trebovanii tehnicheskih reglamentov norm i pravil inyh normativnyh pravovyh aktov i proektno


# 66170701293914
Unscheduled inspection
Start date: 2017-01-10, end date: —, duration:
Authority:
Purpose of inspection:


# 66160701086629
Unscheduled inspection
Start date: 2016-11-09, end date: 2016-11-22, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: To achieve the objectives of the audit of the facility officer authorized to conduct proverbia to consider the developer of customer entity engaged in construction for inspection of the completed construction of the facility documents related to the execution of works including construction design engineering networking sites security as well as the use of construction materials, products namely General or special log which is a record of work of the Executive documentation including acts of examination work structures engineering networking sites provide an impact on the security control over the performance of which could not be carried out after performing other work as well without disassembly or damage of building structures and network parts technical security acts of trials and testing of technical devices, systems acts regulations notice of elimination of violations of the shortcomings identified in the implementation of state construction supervision and construction control of the results of expert examinations and other laboratory tests performed works conducted in the process of construction control documents confirming the performance of quality control of construction materials used documents confirming the execution of decisions on cases of administrative offences and organizationalanalytical and the constituent documents of legal entities and individual entrepreneurs associated with the implementation of the construction of the object of capital construction documents confirming the powers of predstavitelei to conduct a visual inspection of completed works of the object of capital construction in full, including a separate work performed construction and design areas of networking technical support and application of building materials products checking compliance with the requirements of technical regulations of the rules and regulations other regulations and project documentation Prim


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.