Found 8 inspections:

# 782100219210
Unscheduled inspection
Start date: 2021-06-02, end date: —, duration:
Authority: Severo-Zapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 782100178252
Unscheduled inspection
Start date: 2021-04-28, end date: —, duration: 8
Authority: Severo-Zapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: osuschestvlenie kontrolya za soblyudeniem yuridicheskimi licami trebovanii zakonodatelstva o gradostroitelnoi deyatelnosti, obyazatelnyh norm i pravil


# 002005246658
Unscheduled inspection
Start date: 2020-11-30, end date: 2020-12-25, duration: 20
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Celyu nastoyaschei proverki yavlyayutsya kontrol deyatelnosti yuridicheskih licindividualnyh predprinimatelei po soblyudeniyu trebovanii zakonodatelstva o gradostroitelnoi deyatelnosti obyazatelnyh norm i pravil pri rekonstrukcii obekta kapitalnogo stroitelstva v sootvetstvii s programmoi proverok ot 07102020 bnZadachami nastoyaschei proverki yavlyayutsya osuschestvlenie kontrolya za soblyudeniem yuridicheskimi licami individualnymi predprinimatelyami trebovanii zakonodatelstva o gradostroitelnoi deyatelnosti obyazatelnyh norm i pravil preduprezhdenie vyyavlenie i presechenie dopuschennyh narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyasoblyudenie obyazatelnyh trebovanii zakonodatelstva o gradostroitelnoi deyatelnostisootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvovypolnenie licami osuschestvlyayuschimi stroitelstvo trebovanii chastei 2 3 i 31 stati 52 Gradostroitelnogo kodeksa RF


# 002004452435
Unscheduled inspection
Start date: 2020-07-16, end date: 2020-08-12, duration: 20
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Celyu nastoyaschei proverki yavlyayutsya proverka v sootvetstvii s izvescheniem ob ustranenii narushenii ot 02042020 2 po predpisaniyu ot 08112019 23108360773074PR440Zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie kontrolya za soblyudeniem yuridicheskimi licami individualnymi predprinimatelyami trebovanii zakonodatelstva o gradostroitelnoi deyatelnosti obyazatelnyh norm i pravil preduprezhdenie vyyavlenie i presechenie dopuschennyh narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyavypolnenie predpisanii organov gosudarstvennogo stroitelnogo kontrolya nadzora


# 002004283986
Unscheduled inspection
Start date: 2020-02-17, end date: 2020-03-10, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of this audit is to monitor the activities of legal entities and individual entrepreneurs in compliance with the requirements of legislation on urban development mandatory norms and rules during the reconstruction of a capital construction facility in accordance with the inspection program from 20012020 BN The objectives of this audit are to monitor compliance by legal entities and individual entrepreneurs with the requirements of legislation on urban development mandatory norms and rules prevention detection and suppression of violations of legislation on urban planning activities, including design documentationthe subject of this audit is to comply with the mandatory requirements of legislation on urban planning activities, compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements of equipment of the facility capital construction with metering devices for energy resources used, the presence of a construction permit for persons carrying out construction to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 002004268539
Unscheduled inspection
Start date: 2020-02-13, end date: 2020-02-26, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Celyu nastoyaschei proverki yavlyayutsya proverka ispolneniya predpisaniya ot 12112019 23125761373096PR443Zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie kontrolya za soblyudeniem yuridicheskimi licami individualnymi predprinimatelyami trebovanii zakonodatelstva o gradostroitelnoi deyatelnosti obyazatelnyh norm i pravil preduprezhdenie vyyavlenie i presechenie dopuschennyh narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyavypolnenie predpisanii organov gosudarstvennogo stroitelnogo kontrolya nadzora


# 001903873270
Unscheduled inspection
Start date: 2019-10-21, end date: 2019-11-12, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Celyu nastoyaschei proverki yavlyayutsya kontrol deyatelnosti yuridicheskih licindividualnyh predprinimatelei po soblyudeniyu trebovanii zakonodatelstva o gradostroitelnoi deyatelnosti obyazatelnyh norm i pravil pri rekonstrukcii obekta kapitalnogo stroitelstva v sootvetstvii s programmoi proverok ot 30112018 bnZadachami nastoyaschei proverki yavlyayutsya osuschestvlenie kontrolya za soblyudeniem yuridicheskimi licami individualnymi predprinimatelyami trebovanii zakonodatelstva o gradostroitelnoi deyatelnosti obyazatelnyh norm i pravil preduprezhdenie vyyavlenie i presechenie dopuschennyh narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyasoblyudenie obyazatelnyh trebovanii zakonodatelstva o gradostroitelnoi deyatelnostisootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvovypolnenie licami osuschestvlyayuschimi stroitelstvo trebovanii chastei 2 3 i 31 stati 52 Gradostroitelnogo kodeksa RF


# 001902559296
Unscheduled inspection
Start date: 2019-03-14, end date: 2019-04-10, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring of compliance with the requirements of urban planning legislation


Information about inspections