# 702100362031
Unscheduled inspection
Start date: 2021-07-26, end date: 2021-08-20, duration: 20
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: Objectives: prevention, as well as detection and suppression of violations of urban planning legislation during an unscheduled on-site inspection based on the notice of completion of construction No. 3-m dated 07.07.2021 (ex. No. 1/35-19-os-2 dated 12.07.2021), inspection program No. 1/35-19-PP5 dated 14.05.2021. Tasks: prevention, as well as detection and suppression of violations of urban planning legislation. Subject: compliance with mandatory requirements and or requirements established by municipal legal acts: compliance of the work performed and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices for used energy resources, the availability of permits for construction, the requirements established by parts 2 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation, the requirements for the procedure for carrying out construction control established by the Urban Planning Code of the Russian Federation.
# 702100252970
Unscheduled inspection
Start date: 2021-06-07, end date: 2021-06-11, duration: 5
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: Objectives: prevention, as well as detection and suppression of violations of urban planning legislation during an unscheduled on-site inspection based on the expiration of the deadline for the execution of Regulation No. 1/35-19-PR3 dated 01/13/2021. Tasks: prevention, as well as detection and suppression of violations of urban planning legislation. Subject: compliance with the regulations of state control (supervision) bodies, municipal control bodies.
# 702005256656
Unscheduled inspection
Start date: 2020-12-09, end date: 2021-01-13, duration: 20
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: Purpose of the prevention, as well as the identification and suppression of violations of urban planning legislation during an unscheduled on-site inspection based on the notice of completion of construction 1 dated 20112020 BX 35 19oc1 dated 26112020 inspection program 3519PP4 dated 21052020the prevention task, as well as the identification and suppression of violations of urban planning legislation, is the observance of mandatory requirements and or requirements established by municipal legal acts of compliance with the performance of works and applied building materials in the process of construction and reconstruction of a capital construction facility as well as the results of such work to the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of this Code and or the information model, if the formation and maintenance of the information model are mandatory in accordance with the requirements of this Code, including the requirements of energy efficiency for With the exception of capital construction facilities, energy efficiency requirements do not apply to the requirements for equipping the capital construction facility with metering devices for used energy resources, the availability of a construction permit, and compliance with the requirements of Parts 2, 3, and 31 of Article 52 of the Urban Planning Code of the Russian Federation.
# 702004448011
Unscheduled inspection
Start date: 2020-07-08, end date: 2020-08-04, duration: 20
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: The purpose of the prevention, as well as the identification and suppression of violations of urban planning legislation during an unscheduled documentary check based on the expiration of the deadline for the elimination of violations 3519PR2 dated 27112019, the failure to comply with which poses a threat of harm to life and healththe task of the prevention, as well as the identification and suppression of violations of urban planning legislation, is to comply with the instructions of state control bodies, supervision bodies, municipal control order 3519PR2 dated 27112019
# 701903911229
Unscheduled inspection
Start date: 2019-11-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 701903905572
Unscheduled inspection
Start date: 2019-10-30, end date: 2019-11-27, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: the purpose of prevention, as well as the identification and suppression of violations of urban planning legislation during an unscheduled on-site documentary check on the implementation of the Regulation on the elimination of violations 3519PR1 dated 30082019 with a period of elimination until 28102019the task is prevention, as well as the identification and suppression of violations of urban planning legislation, the subject is compliance with the regulations of state control bodies supervision of municipal control bodies regulation 3519PR1 dated 30082019
# 701902917313
Unscheduled inspection
Start date: 2019-08-05, end date: 2019-08-30, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: purpose prevention and detection and suppression of violations of urban planning legislation during an unscheduled on-site inspection based on the notice of the start of construction reg 3519NS1 dated 22072019 task prevention and detection and suppression of violations of urban planning legislation subject to compliance with mandatory requirements and or requirements established by municipal legal acts of compliance with the performance of works and applied building materials during the construction reconstruction of a capital construction facility as well as the results of such work, the requirements of the project documentation for the availability of a construction permit, compliance with the requirements of parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 701902586756
Unscheduled inspection
Start date: 2019-03-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 701800623923
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-09-14, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: The purpose is to prevent, as well as identify and suppress violations of urban planning legislation during an unscheduled on-site inspection at the request of the director of LLC PPK Tsarskoye Beer, Zheleznyakov, and the memo from the head of the Department of the State Tax Service of the Tomsk Region, Marchenko AP dated 02082018, on the modification of the above-mentioned object containing signs of unauthorized reconstruction, which poses a threat of harm to human life and health. The task is to prevent and identification and suppression of violations of urban planning legislation Subject to compliance with mandatory requirements or requirements established by municipal legal acts of compliance of work performed and construction materials used during the construction of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, project documentation, permits for reconstruction, compliance with the requirements of parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation