# 582100321824
Unscheduled inspection
Start date: 2021-06-22, end date: —, duration: 3
Authority: Upravlenie gosudarstvennoi inspekcii v zhilischnoi, stroitelnoi sferah i po nadzoru za tehnicheskim sostoyaniem samohodnyh mashin i drugih vidov tehniki Penzenskoi oblasti
Purpose of inspection: The purpose of the verification with the details of the foundation documents
Verification of the fulfillment of paragraph 1 of Regulation No. PN-475-P1 dated 05/26/2021.
The tasks of the audit
are the implementation of: the Housing Code of the Russian Federation; the Rules for the Maintenance of Common Property in an Apartment Building, approved by Decree of the Government of the Russian Federation No. 491 dated 08/13/06; Decree of the Government of the Russian Federation No. 290 dated 04/03/2013 "On the minimum list of services and works necessary to ensure the proper maintenance of common property in an apartment building, and the procedure for their provision and implementation"; Rules and Regulations for the technical operation of housing Stock, approved by Resolution No. 170 of the State Construction Committee of the Russian Federation dated 09/27/03; Resolution No. 1110 of the Government of the Russian Federation dated 10/28/2014 "On Licensing business activities for the Management of apartment buildings
Subject of verification
The measures taken by the licensee to comply with the regulations on the elimination of identified violations of licensing requirements
# 581801655426
Unscheduled inspection
Start date: 2018-09-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 581800673170
Unscheduled inspection
Start date: 2018-08-28, end date: 2018-08-31, duration: —
Authority: Upravlenie gosudarstvennoi inspekcii v zhilischnoi stroitelnoi sferah i po nadzoru za tehnicheskim sostoyaniem samohodnyh mashin i drugih vidov tehniki Penzenskoi oblasti
Purpose of inspection: Implementation of item 5 of the inspection program from 09062017 case number 7D1136 Compliance with urban planning legislation Compliance of work performed and construction materials used during the construction of a capital construction facility An apartment building above 5 floors at the address Penza region Penza Pervomaisky district Fourth passage Ternovskiy d 2 as well as the results of such work with the requirements of technical regulations other regulations and project documentation
# 581800388949
Unscheduled inspection
Start date: 2018-05-31, end date: 2018-06-06, duration: —
Authority: Upravlenie gosudarstvennoi inspekcii v zhilischnoi stroitelnoi sferah i po nadzoru za tehnicheskim sostoyaniem samohodnyh mashin i drugih vidov tehniki Penzenskoi oblasti
Purpose of inspection: To carry out a visual inspection of the capital construction object and an analysis of the documents specified in paragraph 13 of the regulations on the implementation of state construction supervision in the Russian Federation approved by the decree of the Government of the Russian Federation dated February 1, 2006 54
# 581800222912
Unscheduled inspection
Start date: 2018-03-19, end date: —, duration: —
Authority: Upravlenie gosudarstvennoi inspekcii v zhilischnoi stroitelnoi sferah i po nadzoru za tehnicheskim sostoyaniem samohodnyh mashin i drugih vidov tehniki Penzenskoi oblasti
Purpose of inspection:
# 581800091897
Unscheduled inspection
Start date: 2018-02-14, end date: 2018-02-15, duration: —
Authority: Upravlenie gosudarstvennoi inspekcii v zhilischnoi stroitelnoi sferah i po nadzoru za tehnicheskim sostoyaniem samohodnyh mashin i drugih vidov tehniki Penzenskoi oblasti
Purpose of inspection: Compliance with the requirements of current legislation on the basis of a reasoned submission dated 09022018 25 Compliance with the requirements of Federal Law No. 30122004 214 FZ On Participation in the Shared Construction of Apartment Buildings and Other Real Estate Objects and on Amendments to Certain Legislative Acts of the Russian Federation Compliance with mandatory requirements or requirements established by municipal legal acts
# 58170802999729
Unscheduled inspection
Start date: 2017-12-29, end date: 2018-01-10, duration: —
Authority: Upravlenie gosudarstvennoi inspekcii v zhilischnoi stroitelnoi sferah i po nadzoru za tehnicheskim sostoyaniem samohodnyh mashin i drugih vidov tehniki Penzenskoi oblasti
Purpose of inspection: Implementation of item 3 of the inspection program from 09062017 Case number 7D1136Compliance with urban planning legislation and compliance with the work performed and the building materials used during the construction of a capital construction facility an apartment building above 5 floors, as well as the results of such work, with the requirements of technical regulations, other regulations and project documentation
# 58170802310811
Unscheduled inspection
Start date: 2017-09-13, end date: 2017-09-15, duration: —
Authority: Upravlenie gosudarstvennoi inspekcii v zhilischnoi stroitelnoi sferah i po nadzoru za tehnicheskim sostoyaniem samohodnyh mashin i drugih vidov tehniki Penzenskoi oblasti
Purpose of inspection: implementation of item 2 of the inspection program from 09062017 case number 7D1136Compliance with urban planning legislation and compliance with the work and construction materials used during the construction of a capital construction facility An apartment building above 5 floors at the address Penza region Penza Pervomaisky district Fourth passage Ternovskiy d2 as well as the results of such work requirements of technical regulations other regulations and project documentation
# 58170701729619
Unscheduled inspection
Start date: 2017-06-23, end date: —, duration: —
Authority: Upravlenie gosudarstvennoi inspekcii v zhilischnoi stroitelnoi sferah i po nadzoru za tehnicheskim sostoyaniem samohodnyh mashin i drugih vidov tehniki Penzenskoi oblasti
Purpose of inspection:
# 58170701592655
Unscheduled inspection
Start date: 2017-05-10, end date: 2017-05-11, duration: —
Authority: Upravlenie gosudarstvennoi inspekcii v zhilischnoi stroitelnoi sferah i po nadzoru za tehnicheskim sostoyaniem samohodnyh mashin i drugih vidov tehniki Penzenskoi oblasti
Purpose of inspection: Verification of the construction of the 6th floor on the basis of a notice on the completion dates of works subject to verification during the construction of the reconstruction of the capital construction facility bn dated 20042017Compliance with urban planning legislation on the conformity of work performed and building materials used during the construction of the capital construction facility An apartment building above 5 floors at the address Penza region Penza Pervomaisky district Fourth Passage Ternovsky d 2 as well as the results of such work requirements of technical regulations, other regulations and project documentation