Found 56 inspections:

# 422101277180
Unscheduled inspection
Start date: 2021-11-08, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the conformity of the work performed and the construction materials and products used during the construction of the capital construction facility "Multi-apartment residential building at the address: Kemerovo, Leninsky district, microdistrict No. 72, Stroiteley Boulevard, 60, building 4/1", located at Kemerovo, Boulevard. Builders, 60, as well as the results of such work (installation of a basement, bricklaying of walls and partitions; installation of external engineering systems: heat supply, water supply, sanitation) to the requirements of the design documentation (including taking into account the changes made to the working documentation and which, in accordance with part 1.3 of Article 52 of the Urban Planning Code of the Russian Federation, are part of such design documentation documentation); The purpose of the audit is to comply with the requirements of the legislation of the Russian Federation on urban development; The subject of this audit is to comply with the mandatory requirements of the legislation of the Russian Federation on urban development


# 422101278429
Unscheduled inspection
Start date: 2021-11-08, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:


# 422101278399
Unscheduled inspection
Start date: 2021-11-08, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the conformity of the work performed and the construction materials and products used during the construction of the capital construction facility "Multi-apartment residential building at the address: Kemerovo, Leninsky district, microdistrict No. 72, Stroiteley Boulevard, 60, building 4/1", located at Kemerovo, Boulevard. Builders, 60, as well as the results of such work (installation of a basement, bricklaying of walls and partitions; installation of external engineering systems: heat supply, water supply, sanitation) to the requirements of the design documentation (including taking into account the changes made to the working documentation and which, in accordance with part 1.3 of Article 52 of the Urban Planning Code of the Russian Federation, are part of such design documentation documentation); The purpose of the audit is to comply with the requirements of the legislation of the Russian Federation on urban development; The subject of this audit is to comply with the mandatory requirements of the legislation of the Russian Federation on urban development


# 422101430249
Unscheduled inspection
Start date: 2021-11-22, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: the purpose is to verify the compliance of the work performed and the construction materials and products used during the construction of the facility (glazing of loggias, facade design, installation of doors, installation of ventilation, OPS systems, electrical, plumbing and finishing works), as well as the results of such work with the requirements of the project documentation (including taking into account the changes made to the working documentation and which, in accordance with Part 1.3 of Article 52 of the Urban Planning Code of the Russian Federation, are part of such project documentation); The purpose of the audit is to comply with the legislation of the Russian Federation on urban development activities during construction; The subject of the audit is compliance with the legislation of the Russian Federation on urban development activities


# 422101277045
Unscheduled inspection
Start date: 2021-11-22, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: the purpose is to verify the compliance of the work performed and the construction materials and products used during the construction of the facility (glazing of loggias, facade design, installation of doors, installation of ventilation, OPS systems, electrical, plumbing and finishing works), as well as the results of such work with the requirements of the project documentation (including taking into account the changes made to the working documentation and which, in accordance with Part 1.3 of Article 52 of the Urban Planning Code of the Russian Federation, are part of such project documentation); The purpose of the audit is to comply with the legislation of the Russian Federation on urban development activities during construction; The subject of the audit is compliance with the legislation of the Russian Federation on urban development activities


# 422100642043
Unscheduled inspection
Start date: 2021-09-14, end date: —, duration:
Authority:
Purpose of inspection:


# 422100591176
Unscheduled inspection
Start date: 2021-09-03, end date: —, duration:
Authority:
Purpose of inspection:


# 422100591030
Unscheduled inspection
Start date: 2021-09-03, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the conformity of the work performed and the construction materials and products used during the construction of the capital construction facility "Multi-apartment residential building at the address: Kemerovo, Leninsky district, microdistrict No. 72, Stroiteley Boulevard, 60, building 4/2", located at Kemerovo, Boulevard. Builders, 60, as well as the results of such work (excavation, pile field construction) to the requirements of the design documentation and verification of compliance with the requirements of parts 2 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; The purpose of the verification is to comply with the requirements of the legislation of the Russian Federation on urban development; The subject of this audit is compliance with the mandatory requirements of the legislation of the Russian Federation on urban development


# 422100348965
Unscheduled inspection
Start date: 2021-07-19, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the conformity of the work performed and the building materials used during the construction of the facility (bricklaying of walls and partitions, installation of window blocks, glazing of loggias, roofing, facade, floors, installation of doors, ventilation, electrical, plumbing and finishing works, installation of heating units, elevators, OPS systems), as well as the results of such works are required by the design documentation, verification of compliance with the requirements of Parts 2, 3, 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; the task and subject of this audit is compliance with the legislation of the Russian Federation on urban planning activities during construction


# 422100268828
Unscheduled inspection
Start date: 2021-06-09, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose and subject of the inspection is to verify the fulfillment of inspection instruction No. 01-14-20-02 dated 04/28/2021 (due on 05/31/2021) during the construction of a capital construction facility: "An apartment building at 16A Tereshkova St. in microdistrict No. 15A of the Central District of Kemerovo. Stage 1", located at Kemerovo, Central district, microdistrict No. 15A, Tereshkova str., 16A. The purpose of this inspection is to verify the elimination of violations committed during the construction of the facility.


# 422100260652
Unscheduled inspection
Start date: 2021-06-08, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the conformity of the work performed and the building materials used during the construction of the capital construction facility "Multi-apartment residential building at the address: Kemerovo, Leninsky district, microdistrict No. 72, Stroiteley Boulevard, 60, building 4/1", located at Kemerovo, Boulevard. Builders, 60, as well as the results of such work (pile foundation, grillings, installation of load-bearing structures (plinth), installation of enclosing structures, installation of internal walls and partitions) to the requirements of the design documentation and verification of compliance with the requirements of parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; The task of verification is compliance with the requirements of the legislation of the Russian Federation on urban development activities; The subject of this audit is compliance with the mandatory requirements of the legislation of the Russian Federation on urban development activities


# 422100233906
Unscheduled inspection
Start date: 2021-06-02, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:


# 422100112399
Unscheduled inspection
Start date: 2021-04-12, end date: 2021-04-14, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of the facility (bricklaying of walls and partitions, installation of window blocks, roofing, facade, floors, installation of doors, electrical, plumbing and finishing works), as well as the results of such work with the requirements of the project documentation, verification of compliance with the requirements of parts 2, 3, 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; the objective and subject of this audit is compliance with the legislation of the Russian Federation on urban planning activities during construction


# 422100112497
Unscheduled inspection
Start date: 2021-04-12, end date: 2021-04-14, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of the facility (installation of window blocks, roofing, facades, installation of doors, electrical work, installation of elevators), as well as the results of such work with the requirements of the design documentation, verification of compliance with the requirements of parts 2, 3, 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; task and the subject of this audit is compliance with the legislation of the Russian Federation on urban planning activities during construction.


# 422100059853
Unscheduled inspection
Start date: 2021-03-26, end date: 2021-03-31, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: the purpose of verifying the conformity of the work performed and the building materials used during the construction of the capital construction facility "Multi-apartment residential building at the address: Kemerovo, Leninsky district, microdistrict No. 72, Stroiteley Boulevard, 60, building 4/1", located at Kemerovo, Boulevard. Builders, 60, as well as the results of such work (excavation, excavation fencing, pile field, grillings) to the requirements of the project documentation and verification of compliance with the requirements of parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; The purpose of verification is compliance with the requirements of the legislation of the Russian Federation on urban development; The subject of verification is compliance with mandatory legal requirements Of the Russian Federation on urban development activities


# 422105344222
Unscheduled inspection
Start date: 2021-02-04, end date: —, duration:
Authority:
Purpose of inspection:


# 422005187811
Unscheduled inspection
Start date: 2020-10-07, end date: —, duration:
Authority:
Purpose of inspection:


# 422004484953
Unscheduled inspection
Start date: 2020-08-11, end date: —, duration:
Authority:
Purpose of inspection:


# 422004482995
Unscheduled inspection
Start date: 2020-07-17, end date: 2020-07-21, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of the facility, the installation of elevator window blocks, OPS glazing of loggias, facade installation, including on balconies, installation of entrance doors, installation of a ventilation system, a heating unit and a metering unit, a water measuring unit, the installation of partitions, floors, finishing electrical and plumbing work, landscaping, as well as the results of such work, with the requirements of the design documentation. to comply with the requirements of Parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is to comply with the legislation of the Russian Federation on urban planning activities during construction


# 422004411330
Unscheduled inspection
Start date: 2020-05-19, end date: 2020-05-21, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of the facility, the installation of a frame above 000 16th floor technical floor parapet masonry partitions, as well as the results of such work, with the requirements of the design documentation and verification of compliance with the requirements of parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with the legislation of the Russian Federation on urban planning activities when construction implementation


# 422004407663
Unscheduled inspection
Start date: 2020-05-19, end date: 2020-05-21, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of the facility, the facade of the floors of the heating unit of the metering unit of the water measuring unit, the installation of doors, electrical plumbing and finishing works, the installation of ventilation systems, elevators, OPS systems, commissioning, as well as the results of such work, with the requirements of the design documentation, the verification of compliance with the requirements of parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and the subject of this audit is compliance with the legislation of the Russian Federation on urban planning activities during construction.


# 422004326384
Unscheduled inspection
Start date: 2020-03-10, end date: 2020-03-12, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of the facility, the installation of the roof, facade, floors, heating unit, metering unit, installation of doors, electrical plumbing, finishing works, as well as the results of such work, with the requirements of the design documentation and verification of compliance with the requirements of parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with the legislation of the Russian Federation on urban planning activities during construction


# 422004260114
Unscheduled inspection
Start date: 2020-02-05, end date: 2020-02-07, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of the facility, the installation of the roof, facade, floors, installation of doors, installation of ventilation systems, electrical plumbing and finishing work, installation of elevators, as well as the results of such work, with the requirements of the design documentation, verification of compliance with the requirements of parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with legislation of the Russian Federation on urban planning activities during construction


# 422004277828
Unscheduled inspection
Start date: 2020-02-11, end date: 2020-03-11, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Kemerovskoi oblasti
Purpose of inspection: in order to verify compliance with the instructions of the territorial Department of the Federal Service for Supervision of Consumer Rights Protection and Human Welfare in the Kemerovo region in Kemerovo dated 08062019 321


# 421903977048
Unscheduled inspection
Start date: 2019-11-25, end date: 2019-11-28, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421903833069
Unscheduled inspection
Start date: 2019-10-14, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:


# 421903449747
Unscheduled inspection
Start date: 2019-09-13, end date: 2019-09-17, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421902924932
Unscheduled inspection
Start date: 2019-08-07, end date: 2019-08-09, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421902925017
Unscheduled inspection
Start date: 2019-08-07, end date: 2019-08-09, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421902795462
Unscheduled inspection
Start date: 2019-06-17, end date: 2019-06-19, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421902739851
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-06-26, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421902739773
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-06-26, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421902617795
Unscheduled inspection
Start date: 2019-04-10, end date: 2019-04-12, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421902564442
Unscheduled inspection
Start date: 2019-03-13, end date: 2019-03-15, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421902564581
Unscheduled inspection
Start date: 2019-03-18, end date: —, duration:
Authority:
Purpose of inspection:


# 421902432783
Unscheduled inspection
Start date: 2019-02-04, end date: —, duration:
Authority:
Purpose of inspection:


# 421802331655
Unscheduled inspection
Start date: 2018-12-07, end date: 2018-12-11, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421802336300
Unscheduled inspection
Start date: 2018-12-17, end date: 2018-12-19, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421801060246
Unscheduled inspection
Start date: 2018-09-12, end date: 2018-09-14, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421800596652
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-08, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421800562099
Unscheduled inspection
Start date: 2018-07-25, end date: 2018-07-27, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421800562073
Unscheduled inspection
Start date: 2018-07-25, end date: —, duration:
Authority:
Purpose of inspection:


# 421800338021
Unscheduled inspection
Start date: 2018-05-10, end date: 2018-05-14, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421800337999
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-05-10, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421800337958
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-05-10, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421800264508
Unscheduled inspection
Start date: 2018-04-10, end date: 2018-04-12, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421800102096
Unscheduled inspection
Start date: 2018-02-07, end date: 2018-02-09, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421800102169
Unscheduled inspection
Start date: 2018-02-07, end date: 2018-02-09, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 42170802919534
Unscheduled inspection
Start date: 2017-12-04, end date: 2017-12-06, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the work performed and the construction materials used in the course of work Tasks compliance with the requirements of the legislation of the Russian Federation on urban planning activities during the construction of the object Subject compliance with the mandatory requirements of the legislation of the Russian Federation on urban planning activities


# 42170802919525
Unscheduled inspection
Start date: 2017-12-04, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:


# 42170802762206
Unscheduled inspection
Start date: 2017-10-26, end date: 2017-10-30, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the work performed and the construction materials used during the construction of the facility as well as the results of such work with the requirements of technical regulations, other regulations and project documentation Tasks Compliance with the requirements of the legislation of the Russian Federation in the field of urban development during the construction of a capital construction facility Subject Compliance with the requirements of the legislation of the Russian Federation in the field of urban development


# 42170802024909
Unscheduled inspection
Start date: 2017-09-07, end date: 2017-09-08, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the work performed and the construction materials used in the course of work Tasks compliance with the requirements of the legislation of the Russian Federation on urban planning activities during the construction of the object Subject compliance with the mandatory requirements of the legislation of the Russian Federation on urban planning activities


# 42170802023913
Unscheduled inspection
Start date: 2017-09-07, end date: 2017-09-11, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the work performed and the construction materials used in the course of work Tasks compliance with the requirements of the legislation of the Russian Federation on urban planning activities during the construction of the object Subject compliance with the mandatory requirements of the legislation of the Russian Federation on urban planning activities


# 42170802563245
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-27, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the work performed and the construction materials used during the construction of the facility as well as the results of such work with the requirements of technical regulations, other regulations and project documentation Tasks Compliance with the requirements of the legislation of the Russian Federation in the field of urban development during the construction of a capital construction facility Subject Compliance with the requirements of the legislation of the Russian Federation in the field of urban development


# 42170801917293
Unscheduled inspection
Start date: 2017-08-24, end date: 2017-08-28, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the work performed and the building materials used during the construction of the facility as well as the results of such work with the requirements of technical regulations, other regulations and project documentation Tasks compliance with the legislation of the Russian Federation on urban development activities during construction Subject compliance with the legislation of the Russian Federation on urban development activities


# 42160601781150
Unscheduled inspection
Start date: 2016-08-29, end date: 2016-08-31, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose verification of the execution of regulation 01741502 dated 11052016 deadline 11062016 extended by letter to 15082016 Task verification of the elimination of violations committed during the construction of the facility Subject of the execution of regulation 01741502 dated 11052016 deadline 15082016


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.