Found 40 inspections:

# 742201503871
Unscheduled inspection
Start date: 2022-01-11, end date: —, duration:
Authority:
Purpose of inspection:


# 742101409217
Unscheduled inspection
Start date: 2021-12-13, end date: 2021-12-17, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Sootvetstvie vypolneniya rabot po montazhu metallokarkasa zdaniya, stenovyh, krovelnyh sendvich-panelei, ognezaschite metallokonstrukcii, montazhu zh/b plit perekrytiya na otm.+3.00, +6.000, ustroistvu monolitnyh uchastkov 2 etazha, ustroistvu cementno-peschanoi styazhki pola 2 etazha, ustroistvu lestnic, montazhu naruzhnyh setei teplosnabzheniya, montazhu naruzhnyh dverei i vitrazhei, (posle fakticheskogo okonchaniya rabot), montazhu vnutrennih setei otopleniya (v processe vypolneniya rabot) i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov. 2. Nalichie razresheniya na stroitelstvo. 3. Vypolnenie trebovanii ch.ch. 2,3 i 3.1 st.52 Gradostroitelnogo kodeksa RF.


# 742101370689
Unscheduled inspection
Start date: 2021-11-24, end date: 2021-11-30, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Sootvetstvie vypolneniya rabot po montazhu stenovyh, krovelnyh sendvich-panelei, ognezaschite metallokonstrukcii, montazhu naruzhnyh dverei i vitrazhei, montazhu naruzhnyh setei teplosnabzheniya, elektrosnabzheniya, vnutrennih setei vodoprovoda, kanalizacii, otopleniya, elektrosnabzheniya, montazhu sistem ventilyacii i kondicionirovaniya, ustanovke vnutrennih dverei (posle fakticheskogo okonchaniya rabot). Otdelochnye raboty, blagoustroistvo territorii, ustanovka sportivnogo oborudovaniya i inventarya (v processe proizvodstva rabot). i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov. 2. Nalichie razresheniya na stroitelstvo. 3. Vypolnenie trebovanii ch.ch. 2,3 i 3.1 st.52 Gradostroitelnogo kodeksa RF.


# 742101229848
Unscheduled inspection
Start date: 2021-10-26, end date: —, duration:
Authority:
Purpose of inspection:


# 742100500962
Unscheduled inspection
Start date: 2021-08-26, end date: 2021-09-08, duration: 10
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Sootvetstvie vypolneniya rabot po Betonirovaniyu baz kolonn (posle fakticheskogo okonchaniya rabot). Kirpichnoi kladke sten i peregorodok, montazhu metallokarkasa zdaniya, ognezaschite metallokonstrukcii, montazhu stenovyh, krovelnyh sendvich-panelei, montazhu zh/b plit perekrytiya na otm.+3.00, ustroistvu monolitnyh uchastkov 2 etazha, ustroistvu cementno-peschanoi styazhki pola 2 etazha, montazhu naruzhnyh setei vodoprovoda i kanalizacii, teplosnabzheniya, elektrosnabzheniya, montazhu vnutrennih setei elektrosnabzheniya, blagoustroistvu territorii (v processe vypolneniya rabot). i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov. 2. Nalichie razresheniya na stroitelstvo. 3. Vypolnenie trebovanii ch.ch. 2,3 i 3.1 st.52 Gradostroitelnogo kodeksa RF.


# 742100383209
Unscheduled inspection
Start date: 2021-07-29, end date: 2021-08-11, duration: 10
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Sootvetstvie vypolneniya rabot po betonirovaniyu baz kolonn (posle fakticheskogo okonchaniya rabot), kirpichnoi kladke sten i peregorodok, montazhu metallokarkasa zdaniya, ognezaschite metallokonstrukcii, montazhu stenovyh, krovelnyh sendvich-panelei, montazhu zh/b plit perekrytiya na otm.+3.00, ustroistvu monolitnyh uchastkov 2 etazha, ustroistvu cementno-peschanoi styazhki pola 2 etazha, montazhu naruzhnyh setei vodoprovoda i kanalizacii, teplosnabzheniya, elektrosnabzheniya, montazhu vnutrennih setei elektrosnabzheniya, blagoustroistvu territorii i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov. 2. Nalichie razresheniya na stroitelstvo. 3. Vypolnenie trebovanii ch.ch. 2,3 i 3.1 st.52 Gradostroitelnogo kodeksa RF.


# 742100294292
Unscheduled inspection
Start date: 2021-06-22, end date: —, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:


# 742100137076
Unscheduled inspection
Start date: 2021-04-13, end date: 2021-04-19, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Sootvetstvie vypolneniya rabot po ustroistvu metallokarkasa, lestnic, kirpichnaya kladka sten i peregorodok, montazh zh/b plit perekrytiya na otm.+3.00, (posle fakticheskogo zaversheniya rabot), montazh stenovyh, krovelnyh sendvich-panelei, vitrazhei, naruzhnyh dverei, okon (v processe vypolneniya rabot) i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov. 2. Nalichie razresheniya na stroitelstvo. 3. Vypolnenie trebovanii ch.ch. 2,3 i 3.1 st.52 Gradostroitelnogo kodeksa RF.


# 742105354442
Unscheduled inspection
Start date: 2021-02-19, end date: 2021-02-26, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Sootvetstvie vypolneniya rabot po Montazh zh/b plit perekrytiya na otm. -0.360 (posle fakticheskogo okonchaniya rabot), ustroistvo metallokarkasa, lestnic, kirpichnaya kladka sten i peregorodok, montazh zh/b plit perekrytiya na otm.+3.00, montazh stenovyh, krovelnyh sendvich-panelei (v processe vypolneniya rabot) i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov. 2. Nalichie razresheniya na stroitelstvo. 3. Vypolnenie trebovanii ch.ch. 2,3 i 3.1 st.52 Gradostroitelnogo kodeksa RF.


# 742005268180
Unscheduled inspection
Start date: 2020-12-21, end date: 2020-12-25, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot po montazhu zhb plit perekrytiya na otm 0360 v processe vypolneniya rabot ustroistvo metallokarkasa lestnic kirpichnaya kladka cokolnoi chasti montazh zhb plit perekrytiya na otm+300 montazh naruzhnyh sten iz trehsloinyh panelei v processe vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 nastoyaschego Kodeksa i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 742005225734
Unscheduled inspection
Start date: 2020-11-19, end date: 2020-11-25, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot po montazh zhb plit perekrytiya na otm 0360 posle fakticheskogo okonchaniya rabot ustroistvo metallokarkasa lestnic kirpichnaya kladka cokolnoi chasti sten i peregorodok 1 etazha montazh zhb plit perekrytiya 1 etazha v processe vypolneniya rabot montazh naruzhnyh setei vodoprovoda i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 nastoyaschego Kodeksa i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 742005189411
Unscheduled inspection
Start date: 2020-10-22, end date: —, duration:
Authority:
Purpose of inspection:


# 742004485156
Unscheduled inspection
Start date: 2020-08-17, end date: 2020-08-21, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot po Zemlyanye raboty planirovka territorii razrabotka kotlovana ustroistvo naruzhnogo vodoprovoda v processe vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 nastoyaschego Kodeksa i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov 2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 741903668928
Unscheduled inspection
Start date: 2019-10-02, end date: —, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:


# 741802153066
Unscheduled inspection
Start date: 2018-11-30, end date: 2018-12-06, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot montazh polietilenovyh trub montazh PGB 1sht obratnaya zasypka transhei ispytanie gazoprovoda i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 741801993609
Unscheduled inspection
Start date: 2018-10-23, end date: 2018-10-29, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot po ustroistvu gazoprovoda i podvodov k domam vrezke gazoprovoda rekultivacii vypolnenie pozharnyh sanitarnoepidemiologicheskih i prirodoohrannyh meropriyatii posle vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 741801936818
Unscheduled inspection
Start date: 2018-10-23, end date: 2018-10-29, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on testing the gas pipeline and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 The availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 ct52 of the Urban Planning Code of the Russian Federation


# 741801635726
Unscheduled inspection
Start date: 2018-10-04, end date: 2018-10-10, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the development of the trench and the laying of the pipe from the GRPSh 4 and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 The availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741801998981
Unscheduled inspection
Start date: 2018-10-30, end date: 2018-11-06, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot podgotovitelnye raboty ustroistvo transhei osnovaniya montazh polietilenovyh trub ukladka signalnoi lenty i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 741801460463
Unscheduled inspection
Start date: 2018-09-24, end date: —, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:


# 741800620323
Unscheduled inspection
Start date: 2018-08-17, end date: 2018-08-23, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 The compliance of the work on the breakdown of the route, the development of trenches, the installation of beds, the laying of pipes along the streets of Nagornaya Stepnaya Zelenaya Sovetskaya Lugovaya during the production process and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 The availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code Russian Federation


# 741800616789
Unscheduled inspection
Start date: 2018-08-17, end date: 2018-08-23, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the development of the trench and the laying of the pipe from the GRPSh 3 and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 The availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741800536350
Unscheduled inspection
Start date: 2018-07-16, end date: 2018-07-20, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1Sootvetstvie vypolneniya rabot ustroistvo krovli lestnichnyh kletok LK1 LK2 okon dverei vnutrennyaya otdelka pomeschenii montazh vnutrennih inzhenernyh setei vodoprovoda kanalizacii otopleniya elektroosvescheniya ustroistvo krylec KR1 KR2 otmostki blagoustroistva pokrytie «Elastur» dorozhki i sektora iskusstvennyi gazon futbolnogo polya posle fakticheskogo okonchaniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 741800487665
Unscheduled inspection
Start date: 2018-06-26, end date: 2018-07-02, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot ustroistvo fundamentov sten perekrytii zdaniya ABK ograzhdenie territorii stadiona ograzhdenie legkoatleticheskoi dorozhki pokrytie legkoatleticheskoi dorozhki i sektorov asfaltobetonnym pokrytiem ustroistvo podstilayuschih sloev pod pokrytie gazona futbolnogo polya posle fakticheskogo okonchaniya rabot ustroistvo krovli lestnichnyh kletok LK1 LK2 okon dverei vnutrennyaya otdelka pomeschenii montazh vnutrennih inzhenernyh setei vodoprovoda kanalizacii otopleniya elektroosvescheniya ustroistvo krylec KR1 KR2 otmostki pokrytie «Elastur» dorozhki i sektora iskusstvennyi gazon futbolnogo polya v processe vypolneniya raboti primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 741800351049
Unscheduled inspection
Start date: 2018-05-15, end date: 2018-05-21, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot ustroistvo fundamentov sten perekrytii zdaniya ABK ograzhdenie territorii stadiona ograzhdenie legkoatleticheskoi dorozhki pokrytie legkoatleticheskoi dorozhki i sektorov asfaltobetonnym pokrytiem ustroistvo podstilayuschih sloev pod pokrytie gazona futbolnogo polya v processe vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 741800213329
Unscheduled inspection
Start date: 2018-03-21, end date: —, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:


# 74180803041515
Unscheduled inspection
Start date: 2018-01-10, end date: —, duration:
Authority:
Purpose of inspection:


# 74170802927769
Unscheduled inspection
Start date: 2017-12-06, end date: 2017-12-12, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot ustroistvo podstilayuschih sloev i asfaltobetonnogo pokrytiya pod sektora i begovye dorozhki podstilayuschih sloev pod iskusstvennoe pokrytie futbolnogo polya ustanovka bortovyh kamnei montazh livnevoi kanalizacii smotrovyh kolodcev vygreba drenazhnyh kanalov ograzhdeniya legkoatleticheskoi dorozhki i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 74170802927474
Unscheduled inspection
Start date: 2017-12-06, end date: 2017-12-12, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot montazh polietilenovyh trub montazh PGB 1sht GRPSH 1 sht obratnaya zasypka transhei puskonaladochnye raboty i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 74170802965140
Unscheduled inspection
Start date: 2017-12-11, end date: —, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:


# 74170802802110
Unscheduled inspection
Start date: 2017-11-08, end date: 2017-11-14, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot podgotovitelnye raboty ustroistvo transhei peschanogo osnovaniya montazh polietilenovyh trub podzemnogo gazoprovoda montazh stalnyh trub nadzemnogo gazoprovoda i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 74170802783676
Unscheduled inspection
Start date: 2017-11-03, end date: 2017-11-10, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the earthworks for the installation of the gas pipeline and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2 The availability of a construction permit3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 74170802675860
Unscheduled inspection
Start date: 2017-10-09, end date: 2017-10-13, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot podgotovitelnye raboty ustroistvo transhei peschanogo osnovaniya montazh polietilenovyh trub i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 74170802642978
Unscheduled inspection
Start date: 2017-10-09, end date: —, duration:
Authority:
Purpose of inspection:


# 74170802582798
Unscheduled inspection
Start date: 2017-10-04, end date: 2017-10-10, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the installation of PGB 1 GRPSh 3 4 5, the testing of the gas pipeline, the commissioning and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2the need for a construction permit3compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 74170701854007
Unscheduled inspection
Start date: 2017-08-08, end date: 2017-08-14, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the trench development, pipe laying, and construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 74160701243285
Unscheduled inspection
Start date: 2016-12-26, end date: 2016-12-30, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot montazh nadzemnogo gazoprovoda iz stalnyh trub ustanovka GRPSH i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii2 Nalichie razresheniya na stroitelstvo3 Soblyudenie trebovanii ch 23 st 52 Gradostroitelnogo kodeksa RF


# 74160701051746
Unscheduled inspection
Start date: 2016-10-31, end date: —, duration:
Authority:
Purpose of inspection:


# 74160700915966
Unscheduled inspection
Start date: 2016-10-04, end date: 2016-10-07, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work Preparatory work breakdown of the gas pipeline route digging holes for the gas pipeline supports installation and concreting of the gas pipeline support pillars and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the technical regulations of the project documentation2 Availability of a construction permit3 Compliance with the requirements of h 23 Art 52 of the Urban Planning Code of the Russian Federation


# 74160601531657
Unscheduled inspection
Start date: 2016-03-04, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.