# 772100139850
Unscheduled inspection
Start date: 2021-04-12, end date: 2021-04-30, duration: 15
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772004325687
Unscheduled inspection
Start date: 2020-03-03, end date: 2020-03-13, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer's task of verification, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check and verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 772004364396
Unscheduled inspection
Start date: 2020-03-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004232228
Unscheduled inspection
Start date: 2020-01-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771903884270
Unscheduled inspection
Start date: 2019-10-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803446653
Unscheduled inspection
Start date: 2019-07-05, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77190803379644
Unscheduled inspection
Start date: 2019-03-22, end date: 2019-04-04, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii trebovanii proektnoi dokumentacii zakonodatelstva o gradostroitelnoi deyatelnosti
# 77190803328754
Unscheduled inspection
Start date: 2019-02-07, end date: 2019-02-13, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803326494
Unscheduled inspection
Start date: 2019-02-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803257445
Unscheduled inspection
Start date: 2018-10-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803157977
Unscheduled inspection
Start date: 2018-06-06, end date: 2018-06-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803128157
Unscheduled inspection
Start date: 2018-04-19, end date: 2018-04-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170803005652
Unscheduled inspection
Start date: 2017-12-19, end date: 2017-12-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802908245
Unscheduled inspection
Start date: 2017-11-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802562757
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701864517
Unscheduled inspection
Start date: 2017-08-03, end date: 2017-08-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701721750
Unscheduled inspection
Start date: 2017-06-20, end date: 2017-06-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701632465
Unscheduled inspection
Start date: 2017-05-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701632485
Unscheduled inspection
Start date: 2017-05-29, end date: 2017-06-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701522728
Unscheduled inspection
Start date: 2017-04-06, end date: 2017-04-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701569413
Unscheduled inspection
Start date: 2017-04-25, end date: 2017-04-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701577603
Unscheduled inspection
Start date: 2017-04-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701446820
Unscheduled inspection
Start date: 2017-03-14, end date: 2017-03-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701429769
Unscheduled inspection
Start date: 2017-03-07, end date: 2017-03-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701402050
Unscheduled inspection
Start date: 2017-02-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701302586
Unscheduled inspection
Start date: 2017-01-11, end date: 2017-01-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77160701012915
Unscheduled inspection
Start date: 2016-10-12, end date: —, duration: —
Authority: —
Purpose of inspection: