Found 13 inspections:

# 77190803324420
Unscheduled inspection
Start date: 2019-02-04, end date: 2019-02-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803276142
Unscheduled inspection
Start date: 2018-11-15, end date: 2018-11-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803180103
Unscheduled inspection
Start date: 2018-07-12, end date: 2018-07-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803099279
Unscheduled inspection
Start date: 2018-03-12, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803055097
Unscheduled inspection
Start date: 2018-01-15, end date: 2018-01-19, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170802788863
Unscheduled inspection
Start date: 2017-10-27, end date: 2017-11-02, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170802577030
Unscheduled inspection
Start date: 2017-09-22, end date: 2017-10-05, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701832221
Unscheduled inspection
Start date: 2017-07-27, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701672077
Unscheduled inspection
Start date: 2017-06-02, end date: 2017-06-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701550507
Unscheduled inspection
Start date: 2017-04-17, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701401464
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-03-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701305939
Unscheduled inspection
Start date: 2017-01-18, end date: —, duration:
Authority:
Purpose of inspection:


# 77160701184221
Unscheduled inspection
Start date: 2016-11-29, end date: 2016-12-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.