# 772101433181
Unscheduled inspection
Start date: 2021-12-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101404095
Unscheduled inspection
Start date: 2021-12-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101248662
Unscheduled inspection
Start date: 2021-10-25, end date: 2021-10-29, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772101231715
Unscheduled inspection
Start date: 2021-10-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101237141
Unscheduled inspection
Start date: 2021-10-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100551758
Unscheduled inspection
Start date: 2021-08-27, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100403583
Unscheduled inspection
Start date: 2021-08-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100314247
Unscheduled inspection
Start date: 2021-06-25, end date: 2021-07-08, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772100310322
Unscheduled inspection
Start date: 2021-06-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100154453
Unscheduled inspection
Start date: 2021-04-19, end date: 2021-05-18, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772005265653
Unscheduled inspection
Start date: 2020-12-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005235926
Unscheduled inspection
Start date: 2020-11-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005235115
Unscheduled inspection
Start date: 2020-11-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005235114
Unscheduled inspection
Start date: 2020-11-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005206454
Unscheduled inspection
Start date: 2020-11-02, end date: 2020-11-30, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notice from the developer of the customer. The objectives of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development by the person being checked. The subject of the audit is the fulfillment by the person carrying out the construction of the requirements of part 3 of Article 52 of the Urban Planning Code. The conformity of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such the requirements of the project documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance with the requirements of the project documentation identified during construction control and state construction supervision
# 772005202929
Unscheduled inspection
Start date: 2020-11-02, end date: 2020-11-30, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development by the audited person The subject of the audit is the fulfillment by the developer of the requirements of part 31 of Article 52 of the Urban Planning Code compliance with the performance of works and applied building materials during the construction reconstruction of the capital construction facility as well as the results of such works the requirements of the project documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance with the completed works with the requirements of the project documentation identified during construction control and state construction supervision
# 772004513395
Unscheduled inspection
Start date: 2020-08-31, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004512651
Unscheduled inspection
Start date: 2020-08-31, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004512647
Unscheduled inspection
Start date: 2020-08-31, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004452472
Unscheduled inspection
Start date: 2020-07-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004338312
Unscheduled inspection
Start date: 2020-03-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004375595
Unscheduled inspection
Start date: 2020-03-30, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772004265818
Unscheduled inspection
Start date: 2020-02-10, end date: 2020-02-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor Compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including the requirements of energy efficiency efficiency and equipment requirements of the capital construction facility with metering devices for energy resources used
# 772004290563
Unscheduled inspection
Start date: 2020-02-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771903950444
Unscheduled inspection
Start date: 2019-11-07, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 771903925330
Unscheduled inspection
Start date: 2019-11-18, end date: 2019-11-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for energy resources used
# 771903619267
Unscheduled inspection
Start date: 2019-09-05, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 771903619110
Unscheduled inspection
Start date: 2019-09-05, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 771903634647
Unscheduled inspection
Start date: 2019-09-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771902918050
Unscheduled inspection
Start date: 2019-07-31, end date: 2019-08-27, duration: 20
Authority: Komitet goroda Moskvy po obespecheniyu realizacii investicionnyh proektov v stroitelstve i kontrolyu v oblasti dolevogo stroitelstva
Purpose of inspection: the purpose and objective of this audit is to verify compliance with the mandatory requirements of legislation on participation in the shared construction of apartment buildings and or other real estate objects. The subject of an unscheduled documentary audit is compliance with the requirements of legislation on participation in the shared construction of apartment buildings and or other real estate objects
# 77190803457736
Unscheduled inspection
Start date: 2019-07-12, end date: 2019-07-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803457735
Unscheduled inspection
Start date: 2019-07-12, end date: 2019-07-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803409589
Unscheduled inspection
Start date: 2019-05-13, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77190803413896
Unscheduled inspection
Start date: 2019-05-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803413767
Unscheduled inspection
Start date: 2019-05-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803354931
Unscheduled inspection
Start date: 2019-03-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803328588
Unscheduled inspection
Start date: 2019-02-11, end date: 2019-02-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803277051
Unscheduled inspection
Start date: 2018-11-26, end date: 2018-12-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803221132
Unscheduled inspection
Start date: 2018-09-07, end date: 2018-09-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803166432
Unscheduled inspection
Start date: 2018-06-25, end date: 2018-07-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used