Found 34 inspections:

# 772101444250
Unscheduled inspection
Start date: 2021-12-10, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772101521871
Unscheduled inspection
Start date: 2021-12-28, end date: 2021-12-30, duration: 3
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 772101322602
Unscheduled inspection
Start date: 2021-11-10, end date: —, duration:
Authority:
Purpose of inspection:


# 772101322603
Unscheduled inspection
Start date: 2021-11-10, end date: —, duration:
Authority:
Purpose of inspection:


# 772101275915
Unscheduled inspection
Start date: 2021-11-08, end date: —, duration:
Authority:
Purpose of inspection:


# 772101374355
Unscheduled inspection
Start date: 2021-11-25, end date: 2021-12-22, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision


# 772101158198
Unscheduled inspection
Start date: 2021-10-05, end date: —, duration:
Authority:
Purpose of inspection:


# 772101099180
Unscheduled inspection
Start date: 2021-10-01, end date: —, duration:
Authority:
Purpose of inspection:


# 772101246182
Unscheduled inspection
Start date: 2021-10-21, end date: 2021-11-12, duration: 15
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision


# 772101227317
Unscheduled inspection
Start date: 2021-10-18, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772100680336
Unscheduled inspection
Start date: 2021-09-10, end date: —, duration:
Authority:
Purpose of inspection:


# 772101052155
Unscheduled inspection
Start date: 2021-09-24, end date: —, duration:
Authority:
Purpose of inspection:


# 772100364744
Unscheduled inspection
Start date: 2021-07-16, end date: —, duration:
Authority:
Purpose of inspection:


# 772100353141
Unscheduled inspection
Start date: 2021-07-13, end date: —, duration:
Authority:
Purpose of inspection:


# 772100376626
Unscheduled inspection
Start date: 2021-07-23, end date: 2021-07-29, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 772100085218
Unscheduled inspection
Start date: 2021-03-23, end date: —, duration:
Authority:
Purpose of inspection:


# 772100034264
Unscheduled inspection
Start date: 2021-02-25, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772005256440
Unscheduled inspection
Start date: 2020-12-03, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772005204909
Unscheduled inspection
Start date: 2020-10-28, end date: —, duration:
Authority:
Purpose of inspection:


# 772004482870
Unscheduled inspection
Start date: 2020-08-12, end date: —, duration:
Authority:
Purpose of inspection:


# 772004433303
Unscheduled inspection
Start date: 2020-06-17, end date: —, duration:
Authority:
Purpose of inspection:


# 772004335120
Unscheduled inspection
Start date: 2020-03-03, end date: —, duration:
Authority:
Purpose of inspection:


# 772004257695
Unscheduled inspection
Start date: 2020-02-05, end date: 2020-02-11, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the compliance of the work and construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility construction of metering devices for energy resources used


# 772004257689
Unscheduled inspection
Start date: 2020-02-05, end date: —, duration:
Authority:
Purpose of inspection:


# 772004189232
Unscheduled inspection
Start date: 2020-01-09, end date: —, duration:
Authority:
Purpose of inspection:


# 772004215887
Unscheduled inspection
Start date: 2020-01-23, end date: —, duration:
Authority:
Purpose of inspection:


# 771903845040
Unscheduled inspection
Start date: 2019-10-14, end date: —, duration:
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection:


# 771902782884
Unscheduled inspection
Start date: 2019-06-06, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803309240
Unscheduled inspection
Start date: 2018-12-26, end date: 2019-01-17, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803309238
Unscheduled inspection
Start date: 2018-12-26, end date: 2019-01-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803309243
Unscheduled inspection
Start date: 2018-12-26, end date: 2019-01-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 771802199346
Unscheduled inspection
Start date: 2018-12-04, end date: 2018-12-29, duration:
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: control over the implementation of the regulation GPN 1278111 of 17072018 on the elimination of violations of fire safety requirements on the implementation of measures to ensure fire safety at protection facilities and to prevent the threat of fire


# 771800519456
Unscheduled inspection
Start date: 2018-06-25, end date: 2018-07-20, duration:
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: to prevent the threat of harm to the life and health of citizens, harm to animals, plants, the environment, cultural heritage sites, historical and cultural monuments of the peoples of the Russian Federation, museum objects and museum collections included in the Museum Fund of the Russian Federation, especially valuable, including unique documents of the Archival Fund of the Russian Federation, documents of special historical, scientific and cultural significance included in the National Library Security Fund states, as well as threats of natural and man-made emergencies


# 77170802872495
Unscheduled inspection
Start date: 2017-11-21, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.