Found 100 inspections:

# 002004306213
Unscheduled inspection
Start date: 2020-02-27, end date: 2020-03-26, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to verify the completed construction of an object of capital construction on the basis of the notice of completion 17680E92 dated 13022020 in order to control the compliance of completed works with the mandatory requirements of technical regulations other regulatory legal acts of project documentation requirements for energy conservation and energy efficiency improvement during the construction of an object of capital construction the objectives of this inspection are to prevent identify and suppress violations of mandatory regulatory requirements The subject of this audit is to note the necessary compliance of the work and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements established by parts 2 3 and 3_1 of Article 52 of this Code


# 002004267535
Unscheduled inspection
Start date: 2020-02-10, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 002004247694
Unscheduled inspection
Start date: 2020-02-10, end date: 2020-03-10, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to control the fulfillment by a legal entity, an individual entrepreneur, of the previously issued by the state construction supervision authority of the points of the instruction on the elimination of identified violations of mandatory requirements 570907819R dated August 16, 2019. The tasks of this audit are to verify the elimination by a legal entity of the identified violations specified in the paragraphs of the instruction 570907819R dated August 16, 2019. The subject of this audit is the fulfillment of the instructions of the state control bodies supervision bodies municipal control


# 002004191982
Unscheduled inspection
Start date: 2020-01-13, end date: 2020-02-03, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the implementation of the previously issued instruction dated October 19, 2018 586563P2 Prevention detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts Compliance with the instructions of state control bodies supervision of municipal control bodies


# 001903935329
Unscheduled inspection
Start date: 2019-11-05, end date: 2019-11-28, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the completed construction of the capital construction facility Arrangement of the well cluster 13 of the Sorovsky field of the Vostochnovuyemsky license area Correction code K17613 3rd stage Oil and gas collecting pipeline Bush 13 node 2 Measuring installation IU Control and management unit BKU Drainage tank UNIT Well arrangement position 1 with engineering support networks Site for installation of a borehole reagent dosing unit SUDR in order to control compliance of completed works with mandatory requirements of technical regulations and other normative legal acts of project documentation requirements for energy saving and energy efficiency improvement during the construction of a capital construction facility The objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts The subject of the audit is the compliance of the work and the construction materials used during the construction reconstruction of a capital construction facility as well as the results of such work with the requirements technical regulations of the project documentation, including requirements for energy efficiency and requirements for equipping the capital construction facility with metering devices for energy resources used, availability of a construction permit, compliance with the requirements established by Parts 2 3 and 3_1 of Article 52 of this Code


# 001902951686
Unscheduled inspection
Start date: 2019-08-06, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001902815141
Unscheduled inspection
Start date: 2019-07-01, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001902833388
Unscheduled inspection
Start date: 2019-07-22, end date: —, duration:
Authority:
Purpose of inspection:


# 001902764823
Unscheduled inspection
Start date: 2019-07-22, end date: 2019-08-30, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is conducted in order to verify the fulfillment of previously issued regulations dated October 19, 2018 586563P1 dated October 19, 2018 586564P1THE objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts The subject of this audit is to comply with the regulations of state control bodies supervision of municipal control bodies


# 001902779773
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-17, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the execution of the order dated February 19, 2019 P5701399000820191 issued by the North Ural Department of Rostechnadzor


# 001902476292
Unscheduled inspection
Start date: 2019-02-15, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001902454824
Unscheduled inspection
Start date: 2019-01-14, end date: 2019-02-08, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Inspection of the completed capital construction facility "Reconstruction of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Construction stage 3 in order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of the capital construction facility, the objectives of this inspection are to prevent identify and suppress violations of mandatory regulatory requirements documents and legislative acts The subject of verification is the compliance of the work performed and the construction materials used in the construction process of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements established by parts 2 3 and 3_1 Article 52 of this Code


# 001902454823
Unscheduled inspection
Start date: 2019-01-14, end date: 2019-02-08, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Inspection of the completed capital construction facility "Reconstruction of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Construction stage 2 in order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of the capital construction facility, the objectives of this inspection are to prevent identify and suppress violations of mandatory regulatory requirements documents and legislative acts The subject of verification is the compliance of the work performed and the construction materials used in the construction process of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements established by parts 2 3 and 3_1 Article 52 of this Code


# 001902454803
Unscheduled inspection
Start date: 2019-01-14, end date: 2019-02-08, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Inspection of the completed capital construction facility "Reconstruction of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Construction stage 2 in order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of the capital construction facility, the objectives of this inspection are to prevent identify and suppress violations of mandatory regulatory requirements documents and legislative acts The subject of verification is the compliance of the work performed and the construction materials used in the construction process of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements established by parts 2 3 and 3_1 Article 52 of this Code


# 001902454800
Unscheduled inspection
Start date: 2019-01-14, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001800834112
Unscheduled inspection
Start date: 2018-09-17, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001800834078
Unscheduled inspection
Start date: 2018-09-17, end date: —, duration:
Authority:
Purpose of inspection:


# 001800834077
Unscheduled inspection
Start date: 2018-09-17, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001800834074
Unscheduled inspection
Start date: 2018-09-17, end date: 2018-10-12, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the completed construction of the capital construction facility Arrangement of the well cluster 3 of the Sorovsky field of the Vostochnovuyemsky license area Correction code K17608P Stage 13 1 Arrangement of the injection well position 11 with engineering support networks in order to control the compliance of the completed works with the mandatory requirements of technical regulations other regulatory legal acts of project documentation requirements for energy saving and energy efficiency improvement during the construction of the capital construction facility with the objectives of this inspections are aimed at preventing, identifying and suppressing violations of mandatory requirements of regulatory documents and legislative acts. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources. building permits to comply with the requirements established by Parts 2 3 and 3_1 of Article 52 of this Code


# 001800834073
Unscheduled inspection
Start date: 2018-09-17, end date: 2018-10-12, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Inspection of the completed capital construction facility Arrangement of the well cluster 3 of the Sorovsky field of the Vostochnovuyemsky license area Correction cipher K17608P Stage 12 1 Arrangement of the producing well position 10 with engineering support networks 2 Site for the installation of dosing of SUDR reagents in order to control the compliance of the completed works with the mandatory requirements of technical regulations other regulatory legal acts project documentation requirements for energy conservation and energy efficiency during the construction of a capital construction facility, the objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility construction of metering devices for energy resources used, availability of a construction permit, compliance with the requirements established by Parts 2 3 and 3_1 of Article 52 of this Code


# 001800834072
Unscheduled inspection
Start date: 2018-09-17, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001802044932
Unscheduled inspection
Start date: 2018-09-05, end date: 2018-10-16, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the fulfillment of the previously issued prescription from 20022018 5813890P


# 001800833855
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-09-14, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the completed construction of the capital construction facility Arrangement of the well cluster 6 of the Sorovsky field of the Vostochnovuyemsky license area cipher 17609P Stage 9 construction of all main technological facilities of the oil reservoir flooding system providing the supply of prepared reservoir water to the bush 6 working agent through the projected water duct VD distribution regulation and measurement of the injection volume through 4 injection wells 6 including the high-pressure water conduit Node 30V Bush 6 injection comb unit Transfer to injection of well 1342 in order to control the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy saving and energy efficiency improvement during the construction of a capital construction facility the objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts The subject of this audit is compliance with the implementation of works and construction materials used in the process of construction reconstruction of a capital construction facility as well as the results of such work to the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used, availability of a construction permit, compliance with the requirements established by parts 2 3 and 3_1 of Article 52 of this Code


# 001800833854
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-09-14, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the completed construction of the capital construction facility Arrangement of the well cluster 6 of the Sorovsky field of the Vostochnovuyemsky license area cipher 17609P Stage 3 in order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of the capital construction facility, the objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents The subject of this audit is the compliance of the work and the construction materials used in the process of construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements established by parts 2 3 and 3_1 Article 52 of this Code


# 001800833853
Unscheduled inspection
Start date: 2018-08-27, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001800833522
Unscheduled inspection
Start date: 2018-08-27, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001800833377
Unscheduled inspection
Start date: 2018-08-27, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001800811047
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-09-14, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the completed construction of the capital construction facility "Arrangement of the well cluster 1 of the well 51R of the Sorovsky field of the Vostochnovuyemsky license area" cipher 17611P Stage 3 in order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of the capital construction facility, the objectives of this audit are to prevent identify and suppress violations mandatory requirements of regulatory documents and legislative acts The subject of this audit is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements established by parts 2 3 and 3_1 of Article 52 of this Code


# 001800811021
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-09-07, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the completed construction of the capital construction facility "Arrangement of the well cluster 1 of the well 51R of the Sorovsky field of the Vostochnovuyemsky license area" cipher 17611P Stage 1 in order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of the capital construction facility, the objectives of this audit are to prevent identify and suppress violations mandatory requirements of regulatory documents and legislative acts The subject of this audit is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements established by the parts 2 3 and 3_1 of Article 52 of this Code


# 001800811176
Unscheduled inspection
Start date: 2018-08-27, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001800811020
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-09-14, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the completed construction of the capital construction facility "Arrangement of the well cluster 1 of the well 51R of the Sorovsky field of the Vostochnovuyemsky license area" cipher 17611P Stage 2 in order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of the capital construction facility, the objectives of this audit are to prevent identify and suppress violations mandatory requirements of regulatory documents and legislative acts The subject of this audit is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements established by the parts 2 3 and 3_1 of Article 52 of this Code


# 00170802925665
Unscheduled inspection
Start date: 2017-12-05, end date: 2018-01-09, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to verify the completed construction of a capital construction facility on the basis of the notice of completion 02SIKN 16 dated November 20, 2017 in order to control the compliance of completed works with the mandatory requirements of technical regulations other regulatory legal acts of project documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility the tasks of this inspection are the prevention detection and suppression of violations of mandatory according to the requirements of regulatory documents and legislative acts for the facility "Expansion of the CIC oil acceptance point of Sorovskneft LLC to 16 million tons per year", the subject of this audit is to note the necessary compliance of the work and the construction materials used during the construction of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including the requirements energy efficiency and requirements for equipping a capital construction facility with metering devices for energy resources used, availability of a construction permit, compliance with the requirements established by Parts 2 3 and 3_1 of Article 52 of this Code


# 00170802883495
Unscheduled inspection
Start date: 2017-11-01, end date: 2017-11-29, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: inspection of the completed capital construction facility Prospecting well 6P at the SeveroItyakhsky 3 license area on the basis of the notice of completion of the capital construction facility dated September 28, 2017 61 prevention detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170802883492
Unscheduled inspection
Start date: 2017-11-01, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00170802911351
Unscheduled inspection
Start date: 2017-11-30, end date: 2017-12-22, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Inspection of the completed construction of the capital construction facility "Low pressure water pipeline from the well cluster 14 to the CPS of the Sorovsky field of the Vostochnovuyemsky license area" on the basis of the completion notice 100204034191 dated October 26, 2017 in order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation with the requirements for energy saving and energy efficiency improvement during the construction of the capital construction facility prevention detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts compliance of work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used availability of a construction permit compliance with the requirements established parts 2 3 and 3_1 of Article 52 of this Code


# 00170802911349
Unscheduled inspection
Start date: 2017-11-30, end date: 2017-12-22, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the completed construction of the capital construction facility "Arrangement of the exploration well 59P of the Sorovsky field of the Vostochnovuyemsky license area" stage 2 on the basis of the completion notice 0259P dated November 7, 2017 in order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation requirements for energy conservation and energy efficiency improvement during the construction of the capital construction facility prevention detection and the suppression of violations of mandatory requirements of regulatory documents and legislative acts compliance of the work and construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources availability of a construction permit compliance with the requirements established by parts 2 3 and 3_1 of Article 52 of this Code


# 00170802788033
Unscheduled inspection
Start date: 2017-10-05, end date: 2017-10-25, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the fulfillment of the previously issued prescription pp 4 6 7 9 of 03052017 252715P


# 00170802654929
Unscheduled inspection
Start date: 2017-09-18, end date: —, duration:
Authority:
Purpose of inspection:


# 00170802798113
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-26, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: inspection of the completed construction of the capital construction facility "Central Oil Collection Point of the Sorovsky field of Vostochnovuyemsky LU" stage 3 Block cluster pumping station BKNS on the basis of the notice of completion of the construction of the capital construction facility from 12092017 03CPS BKNS prevention detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170802798110
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-25, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the completed construction of the capital construction facility "Arrangement of the well cluster 16 of the Sorovsky field of the Vostochnovuyemsky license area" cipher 17610P Stage 16 Arrangement of well 1377 with engineering support networks a site for installing a mobile SDR after working off for oil transfer of well 1377 to the injection fund based on the notice of completion of the capital construction facility from 12092017 Bush 1616 warning detection and suppression violations of mandatory requirements of regulatory documents and legislative acts compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170802797858
Unscheduled inspection
Start date: 2017-09-29, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00170802797857
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-25, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the completed construction of the capital construction facility "Arrangement of the well cluster 16 of the Sorovsky field of the Vostochnovuyemsky license area" cipher 17610P Stage 6 Arrangement of well 1442 with engineering support networks a site for installing a mobile ship after oil refining transfer of well 1442 to the injection fund on the basis of a notice of completion of the capital construction facility from 12092017 Bush 166 prevention detection and suppression violations of mandatory requirements of regulatory documents and legislative acts compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170802797856
Unscheduled inspection
Start date: 2017-09-29, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00170802797855
Unscheduled inspection
Start date: 2017-09-29, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00170802798109
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-25, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the completed construction of the capital construction facility "Arrangement of the well cluster 16 of the Sorovsky field of the Vostochnovuyemsky license area" cipher 17610P Stage 15 Arrangement of well 1372 with engineering support networks a site for installing a mobile ship after working off for oil transfer of well 1372 to the injection fund based on the notice of completion of the capital construction facility from 12092017 Bush 1615 warning detection and suppression violations of mandatory requirements of regulatory documents and legislative acts compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170802798030
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-25, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the completed construction of the capital construction facility "Arrangement of the well cluster 16 of the Sorovsky field of the Vostochnovuyemsky license area" cipher 17610P Stage 10 Arrangement of well 1355 with engineering support networks a site for installing a mobile ship after working off for oil transfer of well 1355 to the injection fund based on the notice of completion of the capital construction facility from 12092017 Bush 1610 warning detection and suppression violations of mandatory requirements of regulatory documents and legislative acts compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170802797854
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-25, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the completed construction of the capital construction facility "Arrangement of the well cluster 16 of the Sorovsky field of the Vostochnovuyemsky license area" cipher 17610P Stage 9 Arrangement of well 1361 with engineering support networks a site for installing a mobile ship after working off for oil transfer of well 1442 to the injection fund based on the notice of completion of the capital construction facility from 12092017 Bush 169 prevention detection and suppression violations of mandatory requirements of regulatory documents and legislative acts compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170802798029
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-25, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the completed construction of the capital construction facility "Arrangement of the well cluster 16 of the Sorovsky field of the Vostochnovuyemsky license area" cipher 17610P Stage 11 Arrangement of well 1369 with engineering support networks a site for installing a mobile ship after working off for oil transfer of well 1369 to the injection fund based on the notice of completion of the capital construction facility from 12092017 Bush 1611 warning detection and suppression violations of mandatory requirements of regulatory documents and legislative acts compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170802798028
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-25, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the completed construction of the capital construction facility "Arrangement of the well cluster 16 of the Sorovsky field of the Vostochnovuyemsky license area" cipher 17610P Stage 12 Arrangement of well 1307 with engineering support networks a site for installing a mobile ship after working off for oil transfer of well 1307 to the injection fund based on the notice of completion of the capital construction facility from 12092017 Bush 1612 warning detection and suppression violations of mandatory requirements of regulatory documents and legislative acts compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170802798027
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-25, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the completed construction of the capital construction facility "Arrangement of the well cluster 16 of the Sorovsky field of the Vostochnovuyemsky license area" cipher 17610P Stage 14 Arrangement of well 1354 with engineering support networks site for the installation of a mobile ship based on the notice of completion of the capital construction facility from 12092017 Bush 1614 prevention detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts compliance with mandatory requirements requirements and or requirements established by municipal legal acts


# 00170701787539
Unscheduled inspection
Start date: 2017-06-13, end date: 2017-07-03, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: inspection of the completed capital construction facility "Prospecting well 61P within the VostochnOvuyemsky license area" on the basis of the notice of completion of the capital construction facility dated 24042017 61 prevention detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170701787697
Unscheduled inspection
Start date: 2017-06-13, end date: 2017-07-03, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: inspection of the completed construction of the capital construction facility "Prospecting well 6P at the SeveroItyakhsky 3 license area" on the basis of the notice of completion of the construction of the capital construction facility dated 27042017 6 prevention detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170701771023
Unscheduled inspection
Start date: 2017-06-13, end date: 2017-06-22, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: inspection of the completed construction of the capital construction facility "Prospecting well 63P within the VostochnOvuyemsky license area" on the basis of the notice of completion of the construction of the capital construction facility 631 dated 18052017 prevention detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170701606081
Unscheduled inspection
Start date: 2017-05-29, end date: 2017-06-26, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to verify the completed construction of the capital construction facility on the basis of the completion notice dated 27042017 03NGS1215 for the capital construction facility "Oil collection pipeline from the CPS "Sorovsky" to the intersection with the corridor of communications bushes 1215"the objectives of this inspection are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts The subject of this inspection is to note the necessary compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170701778740
Unscheduled inspection
Start date: 2017-05-26, end date: 2017-06-16, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the completed construction of a capital construction facility on the basis of a notice of completion of the construction of a capital construction facility Central Oil Collection Point of the Sorovskoye field of the Vostochnovuyemsky LU cipher 1149P stage 5 Heater site oil heater P4 POZ65 The objectives of this inspection are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts The subject of this inspection is compliance with mandatory requirements and or the requirements established by municipal legal acts


# 00170701778691
Unscheduled inspection
Start date: 2017-05-26, end date: 2017-06-16, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the completed construction of a capital construction facility on the basis of a notice of completion of the construction of a capital construction facility Reconstruction of the Sorovsky CPS with the expansion of the tank farm cipher 1287P Stage 2 Technological tank V=3000m3 RVS5 Technological tank V=3000m3 RVS6 transition bridge technological pipelinesproblems of this inspection are the prevention detection and suppression of violations of mandatory requirements of regulatory documents and The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170701778624
Unscheduled inspection
Start date: 2017-05-26, end date: 2017-06-16, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the completed construction of an object of capital construction on the basis of a notice of completion of the construction of an object of capital construction The Center for Heat supply of the CPS Sorovskneft Installation of heating of the Working agent stage 1 installation of heating of the working agent a heating gas separator a control unit with TP a heating unit The tasks of this inspection are the prevention detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170701631758
Unscheduled inspection
Start date: 2017-04-19, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00160701269459
Unscheduled inspection
Start date: 2016-11-07, end date: 2016-12-01, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials as well as the results of such work with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used in the construction of reconstruction of the capital construction facility "Arrangement of the well cluster 16 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 5 availability of a construction permit compliance with the requirements of Parts 2 and 3 of Article 52 of Federal Law No. 191 FZ of December 29, 2004


# 00160701269438
Unscheduled inspection
Start date: 2016-11-07, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00160701269426
Unscheduled inspection
Start date: 2016-11-07, end date: 2016-12-01, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials as well as the results of such work with the requirements of technical regulations norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with metering devices for energy resources used in the construction of reconstruction of the capital construction facility "Arrangement of a well bush 19 wells 53R 55P Sorovskoye field Vostochnovuyemsky licensed the site" Stage 12 of the availability of a construction permit to meet the requirements of Parts 2 and 3 of Article 52 of the Federal Law No. 191 FZ of December 29, 2004


# 00160701269377
Unscheduled inspection
Start date: 2016-11-07, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00160701112852
Unscheduled inspection
Start date: 2016-09-14, end date: 2016-09-28, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used in the construction of reconstruction of the capital construction facility "Arrangement of the well cluster 16 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 2 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law No. 191 FZ of December 29, 2004


# 00160601709714
Unscheduled inspection
Start date: 2016-06-14, end date: 2016-07-05, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 8 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601709713
Unscheduled inspection
Start date: 2016-06-14, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00160601709712
Unscheduled inspection
Start date: 2016-06-14, end date: 2016-07-05, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 6 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601709679
Unscheduled inspection
Start date: 2016-06-14, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00160601709678
Unscheduled inspection
Start date: 2016-06-14, end date: 2016-07-06, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 4 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601709734
Unscheduled inspection
Start date: 2016-06-14, end date: 2016-07-05, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 9 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601709733
Unscheduled inspection
Start date: 2016-06-14, end date: 2016-07-05, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 11 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601601182
Unscheduled inspection
Start date: 2016-04-28, end date: 2016-05-20, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 10 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601601157
Unscheduled inspection
Start date: 2016-04-28, end date: 2016-05-20, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 9 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601601156
Unscheduled inspection
Start date: 2016-04-28, end date: 2016-05-20, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 8 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601601155
Unscheduled inspection
Start date: 2016-04-28, end date: 2016-05-20, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 7 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601601153
Unscheduled inspection
Start date: 2016-04-28, end date: 2016-05-20, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 6 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601601200
Unscheduled inspection
Start date: 2016-04-28, end date: 2016-05-20, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 11 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601601152
Unscheduled inspection
Start date: 2016-04-28, end date: 2016-05-20, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 4 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601601150
Unscheduled inspection
Start date: 2016-04-28, end date: 2016-05-20, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 19 of the Sorovsky field of the Vostochnovuyemsky license area" Stage 3 availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601601116
Unscheduled inspection
Start date: 2016-04-18, end date: 2016-05-18, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of completed works and applied building materials, as well as the results of such work, with the requirements of technical regulations, norms and rules of other regulatory legal acts of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with metering devices for energy resources used in the construction of the capital construction facility "Arrangement of the well cluster 15 of the Sorovsky field of the Vostochnovuyemsky license area Stages 215" availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law of December 29, 2004 191 FZ


# 00160601595568
Unscheduled inspection
Start date: 2016-03-10, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00150601358918
Unscheduled inspection
Start date: 2015-11-23, end date: 2015-12-18, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po HantyMansiiskomu avtonomnomu okrugu YUgre
Purpose of inspection: In order to verify the fulfillment by a legal entity Limited Liability Company "Sorovskneft" of the requirements of the previously issued regulation on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements 155OK25 dated 23042015, the task of this audit is to monitor the execution of the previously issued regulation on the elimination of identified violations of legislation in the field of environmental protection and violations of environmental requirements 155OK25 dated 23042015


# 00150601358960
Unscheduled inspection
Start date: 2015-11-23, end date: 2015-12-18, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po HantyMansiiskomu avtonomnomu okrugu YUgre
Purpose of inspection: In order to verify the fulfillment by a legal entity Limited Liability Company "Sorovskneft" of the requirements of the previously issued regulation on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements 149OK25 dated 23042015, the task of this audit is to monitor the execution of the previously issued regulation on the elimination of identified violations of legislation in the field of environmental protection and violations of environmental requirements 149OK25 dated 23042015


# 00150601358913
Unscheduled inspection
Start date: 2015-11-23, end date: 2015-12-18, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po HantyMansiiskomu avtonomnomu okrugu YUgre
Purpose of inspection: In order to verify the fulfillment by a legal entity Limited Liability Company "Sorovskneft" of the requirements of the previously issued regulation on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements 154OK25 of 23042015, the task of this audit is to monitor the execution of the previously issued regulation on the elimination of identified violations of legislation in the field of environmental protection and violations of environmental requirements 154OK25 of 23042015


# 00150601358897
Unscheduled inspection
Start date: 2015-11-23, end date: 2015-12-18, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po HantyMansiiskomu avtonomnomu okrugu YUgre
Purpose of inspection: In order to verify the fulfillment by a legal entity Limited Liability Company "Sorovskneft" of the requirements of the previously issued regulation on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements 153OK25 dated 23042015, the task of this audit is to monitor the execution of the previously issued regulation on the elimination of identified violations of legislation in the field of environmental protection and violations of environmental requirements 153OK25 dated 23042015


# 00150601358888
Unscheduled inspection
Start date: 2015-11-23, end date: 2015-12-18, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po HantyMansiiskomu avtonomnomu okrugu YUgre
Purpose of inspection: In order to verify the fulfillment by a legal entity Limited Liability Company "Sorovskneft" of the requirements of the previously issued regulation on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements 151OK25 dated 23042015, the task of this audit is to monitor the implementation of the previously issued regulation on the elimination of identified violations of legislation in the field of environmental protection and violations of environmental requirements 151OK25 dated 23042015


# 00150601358926
Unscheduled inspection
Start date: 2015-11-23, end date: 2015-12-18, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po HantyMansiiskomu avtonomnomu okrugu YUgre
Purpose of inspection: In order to verify the fulfillment by a legal entity Limited Liability Company "Sorovskneft" of the requirements of the previously issued regulation on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements 156OK25 dated 23042015, the task of this audit is to monitor the implementation of the previously issued regulation on the elimination of identified violations of legislation in the field of environmental protection and violations of environmental requirements 156OK25 dated 23042015


# 00150601358975
Unscheduled inspection
Start date: 2015-11-27, end date: 2015-12-24, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po HantyMansiiskomu avtonomnomu okrugu YUgre
Purpose of inspection: In order to verify the fulfillment by a legal entity Limited Liability Company "Sorovskneft" of the requirements of the previously issued regulation on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements 150OK25 dated 23042015, the task of this audit is to monitor the implementation of the previously issued regulation on the elimination of identified violations of legislation in the field of environmental protection and violations of environmental requirements 150OK25 dated 23042015


# 722100190899
Unscheduled inspection
Start date: 2021-04-28, end date: —, duration: 20
Authority: Severo-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the completed construction of the capital construction facility "Arrangement of the well cluster No. 9, well 65SOR of the Sorovskoye field of the Vostochno-Vuemsky license area" cipher 17658P. Stage 6 on the basis of a notice of completion in order to control the compliance of completed works with the mandatory requirements of technical regulations, other regulatory legal acts, project documentation, requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility. The objectives of this audit are: prevention, detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts. The subject of this review is: compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used; availability of a construction permit; compliance with the requirements established by parts 2, 3 and 3_1 of Article 52 of this Code.


# 722100190873
Unscheduled inspection
Start date: 2021-04-28, end date: —, duration: 20
Authority: Severo-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the completed construction of the capital construction facility "Pressure oil pipeline from the CPS "Sorovsky" to the switching node (2nd line)" cipher 17688. 1 Stage on the basis of a notice of completion in order to control the compliance of the completed works with the mandatory requirements of technical regulations, other regulatory legal acts, project documentation, requirements for energy saving and energy efficiency improvement during the construction of a capital construction facility. The objectives of this audit are: prevention, detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts. The subject of this review is: compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used; availability of a construction permit; compliance with the requirements established by parts 2, 3 and 3_1 of Article 52 of this Code.


# 722100039814
Unscheduled inspection
Start date: 2021-03-04, end date: 2021-03-18, duration: 10
Authority: Severo-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the completed construction of the capital construction facility "Arrangement of the bush of well No. 11, well 61P of the Sorovskoye field of the Vostochno-Vuemsky license area. Adjustment". Stage 3 of construction (project code K.17665) on the basis of a notice of completion in order to control the compliance of completed works with the mandatory requirements of technical regulations, other regulatory legal acts, project documentation, requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility. The objectives of this audit are: prevention, detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts. The subject of this review is: compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used; availability of a construction permit; compliance with the requirements established by parts 2, 3 and 3_1 of Article 52 of this Code.


# 722100039813
Unscheduled inspection
Start date: 2021-03-04, end date: 2021-03-15, duration: 7
Authority: Severo-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of the audit: to verify the fulfillment by a legal entity of an order previously issued by the state construction supervision authority on the elimination of identified violations of mandatory requirements No. RP-322-42- o-P dated February 4, 2021 on the basis of the notice of elimination of violations No. K17665-E3 dated February 18, 2021. Verification tasks: verification of the elimination by a legal entity of the identified violation specified in paragraphs of regulation No. RP-322-42- o-P dated February 4, 2021 The subject of the audit: compliance with the instructions of state control (supervision) bodies, municipal control bodies.


# 002105312621
Unscheduled inspection
Start date: 2021-01-20, end date: 2021-02-04, duration: 12
Authority: Severo-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the completed construction of the capital construction facility "Arrangement of the well cluster No. 11, well 61P of the Sorovskoye field of the Vostochno-Vuemsky license area. Correction" cipher K.17665. Stage 3 - Oil and gas collecting pipeline from the site of the well cluster No. 11 to node 43 of the oil and gas collecting pipeline "Bush 9 - Node 41". Measuring unit (IU) with a control and control unit (BKU). Drainage capacity (UNIT1). Well construction (position 1) with engineering and technical support networks. Well construction (position 2) with engineering and technological support networks. Well construction (position 3) with engineering and technological support networks ..." on the basis of a notice of completion in order to control the compliance of completed works with the mandatory requirements of technical regulations, other regulatory legal acts, project documentation, requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility. The objectives of this audit are: prevention, detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts. The subject of this review is: compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used; availability of a construction permit; compliance with the requirements established by parts 2, 3 and 3_1 of Article 52 of this Code.


# 002004306213
Unscheduled inspection
Start date: 2020-02-27, end date: 2020-03-26, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to verify the completed construction of an object of capital construction on the basis of the notice of completion 17680E92 dated 13022020 in order to control the compliance of completed works with the mandatory requirements of technical regulations other regulatory legal acts of project documentation requirements for energy conservation and energy efficiency improvement during the construction of an object of capital construction the objectives of this inspection are to prevent identify and suppress violations of mandatory regulatory requirements The subject of this audit is to note the necessary compliance of the work and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements established by parts 2 3 and 3_1 of Article 52 of this Code


# 002004267535
Unscheduled inspection
Start date: 2020-02-10, end date: 2020-03-10, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to implement the inspection program approved by 573752 dated May 31, 2019 in order to control the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility the objectives of this inspection are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts by the subject of this The purpose of the inspection is to note the necessary compliance of the work and the construction materials used in the construction process of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements established by parts 2 3 and 3_1 of Article 52 of this code The Code


# 002004247694
Unscheduled inspection
Start date: 2020-02-10, end date: 2020-03-10, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to control the fulfillment by a legal entity, an individual entrepreneur, of the previously issued by the state construction supervision authority of the points of the instruction on the elimination of identified violations of mandatory requirements 570907819R dated August 16, 2019. The tasks of this audit are to verify the elimination by a legal entity of the identified violations specified in the paragraphs of the instruction 570907819R dated August 16, 2019. The subject of this audit is the fulfillment of the instructions of the state control bodies supervision bodies municipal control


# 002004191982
Unscheduled inspection
Start date: 2020-01-13, end date: 2020-02-03, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the implementation of the previously issued instruction dated October 19, 2018 586563P2 Prevention detection and suppression of violations of mandatory requirements of regulatory documents and legislative acts Compliance with the instructions of state control bodies supervision of municipal control bodies


# 001904069791
Unscheduled inspection
Start date: 2019-12-04, end date: 2019-12-06, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the execution of the order dated June 17, 2019 573838P issued by the North Ural Department of Rostechnadzor


# 001903935329
Unscheduled inspection
Start date: 2019-11-05, end date: 2019-11-28, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the completed construction of the capital construction facility Arrangement of the well cluster 13 of the Sorovsky field of the Vostochnovuyemsky license area Correction code K17613 3rd stage Oil and gas collecting pipeline Bush 13 node 2 Measuring installation IU Control and management unit BKU Drainage tank UNIT Well arrangement position 1 with engineering support networks Site for installation of a borehole reagent dosing unit SUDR in order to control compliance of completed works with mandatory requirements of technical regulations and other normative legal acts of project documentation requirements for energy saving and energy efficiency improvement during the construction of a capital construction facility The objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts The subject of the audit is the compliance of the work and the construction materials used during the construction reconstruction of a capital construction facility as well as the results of such work with the requirements technical regulations of the project documentation, including requirements for energy efficiency and requirements for equipping the capital construction facility with metering devices for energy resources used, availability of a construction permit, compliance with the requirements established by Parts 2 3 and 3_1 of Article 52 of this Code


# 001902951686
Unscheduled inspection
Start date: 2019-08-06, end date: 2019-09-16, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the fulfillment of the previously issued instruction dated October 16, 2018 586640P The objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts The subject of this audit is the fulfillment of the instructions of state control bodies supervision of municipal control bodies


# 001902910300
Unscheduled inspection
Start date: 2019-07-23, end date: 2019-08-19, duration:
Authority: Uralskoe mezhregionalnoe territorialnoe upravlenie Federalnogo agentstva po tehnicheskomu regulirovaniyu i metrologii
Purpose of inspection: This audit is conducted in order to assess the compliance of the activities carried out with the requirements of Federal Law No. 102FZ dated 26062008 "On Ensuring the Uniformity of Measurements" to assess the compliance of the activities carried out with the mandatory requirements of Federal Law No. 184FZ dated December 27, 2002 "On Technical Regulation" the objectives of this audit are to assess the conformity of products or related design processes including surveys of production construction installation commissioning operation storage transportation sale and disposal of mandatory requirements of technical regulations standards verification of compliance with mandatory requirements in the field of state regulation to ensure the uniformity of measurements to measurements units measurement methods measuring instruments when used in the territory of the Russian Federation The purpose of this audit is to note the necessary compliance with mandatory requirements established by municipal legal acts


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.