Found 101 inspection:

# 001902857102
Unscheduled inspection
Start date: 2019-07-09, end date: 2019-07-25, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to implement the inspection programs dated 24092018 for the implementation of state planning supervision of the construction and reconstruction of capital construction facilities of the Northeast Department of Rostechnadzor in 2019. The purpose of this inspection is to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation during the construction of the facility, committed by the developer, the technical customer, as well as by persons engaged in construction on the basis of an agreement with the Developer or the technical customer capital construction "Tailings and turnaround water supply "Dam of stage II tailings protected in search of sorption" in accordance with the project documentation "Mining and processing enterprise based on the Pavlik gold deposit" Magadan region Tenkinsky district Correction of design solutions for tailings facilities design characteristics are indicated in the list of capital construction facilities"owned by the joint-stock company Zolotorudnaya CompanyavlikThe subject of this audit is 1 the conformity of the work performed and the construction materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping the capital construction facility with metering devices for energy resources used.2 The availability of a construction permit.3 the fulfillment of the requirements established by Parts 2 3 and 31 of the article 52


# 001902435957
Unscheduled inspection
Start date: 2019-01-14, end date: —, duration:
Authority:
Purpose of inspection:


# 001902497543
Unscheduled inspection
Start date: 2019-01-09, end date: 2019-02-01, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to comply with the previously issued instruction dated 21092018 056192018C The task is to prevent the identification and intersection of violations of urban planning legislation committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of a capital construction facility Waste rock dumps Adjustments performed according to working documentation Mining and processing enterprises on on the basis of the PAVLIK gold deposit, Magadan region, Tenkinsky district, Adjustment of design solutions for tailings facilities, Waste rock dumps, Adjustment of the PAVLIK Gold Mining Company owned by Joint Stock Company, subject to compliance with the instructions of state control bodies, supervision bodies, municipal control bodies


# 001902439146
Unscheduled inspection
Start date: 2019-01-09, end date: 2019-02-01, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to verify the fulfillment of the previously issued regulation dated 21092018 056192018C The task is to ensure the compliance of the work and the construction materials used during the construction of the facility eliminate violations committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer of violations of legislation on urban development, including technical regulations in the design documentation during the construction of the capital construction facility. Mining and processing enterprise based on the PAVLIK gold deposit, Magadan Region, Tenkinsky district, Adjustment of design solutions for tailings facilities, Waste rock dumps, Adjustment of PAVLIK Gold Mining Company Items 1. compliance of work performed and construction materials used during construction, reconstruction of the capital construction facility, reconstruction of the capital construction facility, as well as the results of such work requirements of the project documentation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 23 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 001902435618
Unscheduled inspection
Start date: 2019-01-09, end date: 2019-02-01, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to verify the fulfillment of the previously issued regulation dated 21092018 056192018C The task is to prevent identify and intersect violations of urban planning legislation committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of a capital construction facility Waste rock dumps Adjustments performed according to working documentation Mining and processing the enterprise based on the PAVLIK gold deposit Magadan region Tenkinsky district Adjustment of design solutions for tailings facilities Waste rock dumps Adjustment of the PAVLIK Gold Ore Company owned by Joint Stock company Items 1 compliance of work performed and construction materials used during construction reconstruction of the capital construction facility reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation including energy efficiency requirements with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 23 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 001800833399
Unscheduled inspection
Start date: 2018-01-29, end date: 2018-02-16, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This unscheduled on-site inspection is carried out in order to monitor the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility on the basis of the notice of completion of construction dated 24.012018 3 The purpose of this inspection is to prevent identify and suppress violations committed by the developer, the technical customer, as well as by persons carrying out construction on based on an agreement with the developer or a technical customer for violations of legislation on urban development, including technical regulations and design documentation during the construction of the capital construction facility "Tier 3 Collapse Dam" in accordance with the design documentation "Mining and processing enterprise based on the Pavlik gold deposit" Magadan region Tenkinsky district Adjustment of design solutions for tailings facilities". The purpose of this check is to ensure that the work performed and the building materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used


# 00170802752014
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-05, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The present final inspection is carried out in order to ensure that the constructed capital construction facility meets the requirements of technical regulations of other regulatory legal acts and project documentation based on the completion notice dated 22092017 2The task is to assess the compliance of the work performed with the requirements of technical regulations of other regulatory legal acts and project documentation to identify violations deficiencies in relation to the work performed during the construction of the capital construction facility Tailings dump Flotation dam Tier 2 provides for verification of compliance with mandatory requirements or requirements established by municipal legal acts


# 492100313936
Unscheduled inspection
Start date: 2021-06-29, end date: —, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to implement the inspection program dated 02/03/2021 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. The purpose of this audit is to prevent, identify and suppress violations of urban planning legislation committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of the capital construction facility "Highway for dump trucks to RMM" code 009-0606.1 in accordance with the project documentation "Mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". The subject of this review is: - compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.


# 492100313873
Unscheduled inspection
Start date: 2021-06-29, end date: —, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to implement the inspection program dated 02/03/2021 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. The purpose of this audit is to prevent, identify and suppress violations of the legislation on urban development activities, including technical regulations and design documentation during the construction of the capital construction facility "Highway to Sushch", committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer. crushed ore warehouse" code 009-0606.2 in accordance with the project documentation "Mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". The subject of this review is: - compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.


# 492100313918
Unscheduled inspection
Start date: 2021-06-29, end date: —, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to implement the inspection program dated 02/03/2021 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. The purpose of this audit is to prevent, identify and suppress violations of urban planning legislation committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of the capital construction facility "Ore Supply Gallery No. 2" code 009-0301.4 in accordance with the project documentation "Mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". The subject of this review is: - compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.


# 492100313865
Unscheduled inspection
Start date: 2021-06-29, end date: —, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to implement the inspection program dated 02/03/2021 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. The purpose of this audit is to prevent, identify and suppress violations of urban planning legislation committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of the capital construction facility "Ore Supply Gallery No. 1" code 009-0301.2 in accordance with the project documentation "Mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". The subject of this review is: - compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.


# 492100245648
Unscheduled inspection
Start date: 2021-06-02, end date: —, duration: 20
Authority: Severo-Vostochnoe mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya
Purpose of inspection: in order to assess the completeness and timeliness of the execution of the issued Instruction on the elimination of violations of legislation in the field of nature management and environmental protection


# 492100231675
Unscheduled inspection
Start date: 2021-05-12, end date: —, duration: 5
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to monitor the implementation of paragraphs 1,2,3,4,5,6,7,8,9,10,11,12, previously issued by the North–Eastern Directorate of Rostechnadzor regulation dated March 05, 2021 No. 04/08-2021 E (L, D). The objectives of this audit are: to control the completeness and quality of the implementation of the points 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, previously issued by the North-Eastern Department of Rostechnadzor Regulation No. 04/08-2021 E (L, D) dated March 05, 2021.


# 492100325547
Unscheduled inspection
Start date: 2021-05-26, end date: —, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms (49/7-27-19- About from 17.01.2019 by request ) Ensuring the observance and protection of citizens' labor rights and freedoms, including the right to safe working conditions; compliance with mandatory requirements and (or) requirements established by municipal legal acts; compliance with mandatory requirements and (or) requirements established by municipal legal acts; compliance with mandatory requirements and/or requirements established by municipal legal acts;


# 492100107883
Unscheduled inspection
Start date: 2021-04-19, end date: —, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms. Ensuring the observance and protection of citizens' labor rights and freedoms, including the right to safe working conditions; ensuring that employers comply with labor laws and other regulatory legal acts containing labor law norms. Compliance with mandatory requirements and/or requirements established by municipal legal acts.


# 492100154343
Unscheduled inspection
Start date: 2021-04-14, end date: 2021-05-13, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Magadanskoi oblasti
Purpose of inspection: execution of the order of the Head of the Federal Service for Supervision of Consumer Rights Protection and Human Welfare, A.Y. Popova, dated 04/02/2021, No. 131 "On conducting inspections of working conditions of foreign citizens involved in the implementation of major investment inspections", issued pursuant to the instruction of the President of the Russian Federation dated 03/05/2021, No. Pr-356


# 492100150372
Unscheduled inspection
Start date: 2021-04-14, end date: 2021-05-13, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms; Rostrud Order No. 73 dated 04/02/2021; Rostrud Letter No.49/2-77-21- PV dated 04/12/2021; Subparagraph 5.2 of paragraph 5 of the Protocol of the operational meeting of the Security Council of the Russian Federation dated 23 February 2021, approved by the President of the Russian Federation V.V. Putin on March 5, 2021, No. Pr-356.


# 492100118886
Unscheduled inspection
Start date: 2021-04-06, end date: 2021-05-04, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Execution of the inspection program dated 10.13.2021 for the implementation of state construction supervision over the construction of the capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, detection and suppression of violations of urban planning legislation committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of the capital construction facility "Waste Rock Dump West" code 009-0203 in accordance with the design documentation "A mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100114725
Unscheduled inspection
Start date: 2021-04-06, end date: 2021-05-04, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Execution of the inspection program dated 03/10/2021 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, detection and suppression of violations of urban planning legislation committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of the capital construction facility "On-site engineering networks" code 009-300 in accordance with the design documentation "Mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100115004
Unscheduled inspection
Start date: 2021-04-06, end date: 2021-05-04, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Execution of the inspection program dated 12/15/2020 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, detection and suppression of violations of urban planning legislation, including technical regulations and design documentation, committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, during the construction of the capital construction facility "Overpass No. 1 on-site engineering networks" code 009-0307.1 in accordance with the project documentation "Mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100114807
Unscheduled inspection
Start date: 2021-04-06, end date: 2021-05-04, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Execution of the inspection program dated 03/10/2021 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, detection and suppression of violations of the legislation on urban planning activities committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of the Pavlik Waste Rock Dump facility code 009-0201 in accordance with the design documentation "A mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100114592
Unscheduled inspection
Start date: 2021-04-06, end date: 2021-05-04, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Execution of the inspection program dated 02/03/2021 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, detection and suppression of violations of the legislation on urban planning activities committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of the capital construction facility "Repair and Mechanical Workshop" code 009-0302 in accordance with the design documentation "A mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100118888
Unscheduled inspection
Start date: 2021-04-06, end date: 2021-05-04, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Execution of the inspection program dated 12/15/2020 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, detection and suppression of violations of the legislation on urban planning activities committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of the capital construction facility "Large crushing Building" code 009-0301.1 in accordance with the design documentation "Mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100114539
Unscheduled inspection
Start date: 2021-04-06, end date: 2021-05-04, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Execution of the inspection program dated 12/15/2020 for the implementation of state construction supervision over the construction of the capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation during the construction of the capital construction facility "Thickener with PNS-1.1" code 009-0301.6 committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, in accordance with with project documentation "Mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100114747
Unscheduled inspection
Start date: 2021-04-06, end date: 2021-05-04, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Execution of the inspection program dated 03/10/2021 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, detection and suppression of violations of the legislation on urban planning activities committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of the capital construction facility "Severny Waste Dump" code 009-0204 in accordance with the design documentation "A mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100114691
Unscheduled inspection
Start date: 2021-04-06, end date: 2021-05-04, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Execution of the inspection program dated 12/15/2020 for the implementation of state construction supervision over the construction of the capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, detection and suppression of violations of urban planning legislation committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of the capital construction facility "Main Building ZIF" code 009-0301.5 in accordance with the design documentation "Mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100114712
Unscheduled inspection
Start date: 2021-04-06, end date: 2021-05-04, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Execution of the inspection program dated 12/15/2020 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, detection and suppression of violations of the legislation on urban planning activities committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of the capital construction facility "Surface warehouse of crushed ore" code 009-0301.3 in accordance with project documentation "Mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100114555
Unscheduled inspection
Start date: 2021-04-06, end date: 2021-05-04, duration: 20
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Execution of the inspection program dated 12/15/2020 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, detection and suppression of violations of urban planning legislation, including technical regulations and design documentation, committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, during the construction of the capital construction facility "Overpass No. 3 on-site engineering networks" code 009-0307.3 in accordance with the project documentation "Mining and processing enterprise based on the Pavlik gold deposit (Magadan region, Tenkinsky district). Expansion to 10 million tons of ore per year. Magadan region". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100064569
Unscheduled inspection
Start date: 2021-02-15, end date: 2021-03-05, duration: 14
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: compliance with mandatory requirements and/or requirements established by municipal legal acts The subject of this audit is a real audit conducted for the purpose of executing an order: Federal Service for Environmental, Technological and Nuclear Supervision No. 545 dated December 17, 2020 "On Conducting Inspections of Compliance with Mandatory Requirements by Electric Power Industry Entities, Heat Supply Organizations, Heating Grid Organizations and Consumers of Electric Energy in 2021", issued pursuant to the instruction of the Government of the Russian Federation dated December 11, 2020 No. AN-P9-16299. The objectives of this review are: -prevention, detection and suppression of violations of mandatory requirements established by federal laws and other regulatory acts of the Russian Federation.


# 492105302742
Unscheduled inspection
Start date: 2021-01-15, end date: —, duration: 20
Authority: Glavnoe upravlenie MCHS Rossii po Magadanskoi oblasti
Purpose of inspection: Monitoring the implementation by a legal entity (Joint Stock Company Pavlik Gold Mining Company) of the previously issued Regulation No. 39/1/1 dated 09/19/19 on the elimination of identified violations of mandatory requirements and (or) requirements established by regulatory legal acts on fire safety, the objectives of this audit are compliance with fire safety requirements by organizations and citizens at protection facilities used (operated) they are in the process of carrying out their activities and taking measures based on the results of the audit.


# 492005176190
Unscheduled inspection
Start date: 2020-10-19, end date: 2020-11-16, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with mandatory requirements of labor legislation and other regulatory legal acts containing norms of labor law Ensuring compliance and protection of labor rights and freedoms of citizens including the right to safe working conditions compliance with mandatory requirements and or requirements established by municipal legal acts


# 492005150207
Unscheduled inspection
Start date: 2020-10-12, end date: 2020-11-09, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with mandatory requirements of labor legislation and other regulatory legal acts containing norms of labor law Ensuring compliance and protection of labor rights and freedoms of citizens including the right to safe working conditions compliance with mandatory requirements and or requirements established by municipal legal acts


# 492004468603
Unscheduled inspection
Start date: 2020-08-06, end date: 2020-09-02, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms Appeal 49749420 of 17072020 Gerasimenko OA Ensuring compliance with and protection of labor rights and freedoms of citizens including the right to safe working conditions ensuring compliance by employers with labor legislation and other regulatory legal acts containing labor law norms compliance with mandatory requirements and or requirements established by municipal legal acts


# 492004489087
Unscheduled inspection
Start date: 2020-08-13, end date: 2020-08-20, duration: 6
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility based on the completion notice dated 07082020 1 Prevention identification and suppression of violations of urban planning legislation committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer activities, including technical regulations and design documentation during the construction of the capital construction facility "Tailings dump of flotation tails "Collapse dam of tier 8" in accordance with the design documentation "Mining and processing enterprise based on the PAVLIK gold deposit" Magadan region Tenkinsky district Adjustment of design solutions for tailings facilities" owned by the joint-stock company "PAVLIK Gold Mining Company" Compliance the performance of works and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work to the requirements of project documentation including energy efficiency requirements with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used2 the availability of a construction permit 3 the fulfillment of the requirements set out in Parts 2 to 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 492004540589
Unscheduled inspection
Start date: 2020-07-27, end date: —, duration:
Authority:
Purpose of inspection:


# 492004446025
Unscheduled inspection
Start date: 2020-07-06, end date: —, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 492004426384
Unscheduled inspection
Start date: 2020-06-08, end date: 2020-07-06, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms Appeal 49738220 of 01062020


# 492004425303
Unscheduled inspection
Start date: 2020-05-08, end date: 2020-06-05, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms 4972719OB dated 17012019 on the application Ensuring compliance with and protection of labor rights and freedoms of citizens including the right to safe working conditions compliance with mandatory requirements and or requirements established by municipal legal acts Compliance with mandatory requirements and or requirements established by compliance with mandatory requirements and or requirements established by municipal legal acts


# 492004354044
Unscheduled inspection
Start date: 2020-03-17, end date: 2020-03-26, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the execution of the instruction issued by the Northeast Department of Rostechnadzor dated December 02, 2019 03235R2019THE objectives of this audit are to assess the completeness of the quality and timeliness of the execution of the previously issued instruction dated December 02, 2019 03235R2019 on the elimination of violations identified during the scheduled on-site inspection of PAVLIK JSC


# 492004292087
Unscheduled inspection
Start date: 2020-02-19, end date: —, duration:
Authority:
Purpose of inspection:


# 492004207270
Unscheduled inspection
Start date: 2020-01-16, end date: 2020-01-21, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of the possibility for the licensee of Pavlik JSC to fulfill the licensing requirements and conditions when carrying out the licensed type of activity "Production of surveying works" according to the criteria assigned to the licensed types of activities


# 491904152318
Unscheduled inspection
Start date: 2019-12-23, end date: 2019-12-27, duration:
Authority: Ohotskoe territorialnoe upravlenie Federalnogo agentstva po rybolovstvu
Purpose of inspection: Control of the execution of the order dated July 16, 2019 on the elimination of violations of the requirements of legislation in the field of fisheries and conservation of aquatic biological resources and habitat 32019


# 491904288860
Unscheduled inspection
Start date: 2019-12-30, end date: 2020-02-03, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms appeal by Yuzeeva EO 49774019 dated 16122019 Ensuring compliance with and protection of labor rights and freedoms of citizens including the right to safe working conditions Compliance with mandatory requirements and or requirements established by municipal legal acts


# 491904151225
Unscheduled inspection
Start date: 2019-11-27, end date: 2019-12-06, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms 4972719OB dated 17012019 on the application Ensuring compliance with and protection of labor rights and freedoms of citizens including the right to safe working conditions compliance with mandatory requirements and or requirements established by municipal legal acts Compliance with mandatory requirements and or requirements established by compliance with mandatory requirements and or requirements established by municipal legal acts


# 491903985129
Unscheduled inspection
Start date: 2019-11-05, end date: 2019-11-13, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out with the aim of monitoring the implementation of the previously issued instruction dated May 28, 2019 055032019 1111 on the elimination of violations of the mandatory industrial safety requirements issued by PAVLIK Joint Stock Company following the results of the measures to monitor compliance with the mandatory industrial safety requirements during operation of the facility "Basic Reagent Inventory" of hazard class 1 reg A76005370003 in the mode of permanent supervision.


# 491903917327
Unscheduled inspection
Start date: 2019-11-05, end date: 2019-11-13, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out with the aim of monitoring the implementation of the previously issued order dated May 28, 2019 055032019 GSH on the elimination of violations of the mandatory industrial safety requirements issued by PAVLIK Joint Stock Company following the results of the measures to monitor compliance with the mandatory industrial safety requirements for the operation of the facility "Basic Reagent Inventory" of hazard class 1 per A76005370003 in the mode of permanent supervision. Compliance with the information contained in the application and documents of a legal person or individual when granting the legal status of a special permit to a licensee, the right to carry out certain types of activities or to authorize other legally significant actions if an appropriate unscheduled audit of the individual entrepreneur's legal person is provided for in the rules for granting the legal status of a special permit to a licensee and granting approval to mandatory requirements, as well as information about these legal entities and individual entrepreneurs contained in the unified State Register of Legal Entities, the unified State Register of individual entrepreneurs and other federal information systems resourcescompliance with the regulations of state control bodies and municipal control bodies


# 491904059052
Unscheduled inspection
Start date: 2019-10-29, end date: 2019-11-26, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms 4972719OB dated 17012019 on the application Ensuring compliance with and protection of labor rights and freedoms of citizens including the right to safe working conditions compliance with mandatory requirements and or requirements established by municipal legal acts Compliance with mandatory requirements and or requirements established by compliance with mandatory requirements and or requirements established by municipal legal acts


# 491903594802
Unscheduled inspection
Start date: 2019-09-19, end date: —, duration:
Authority:
Purpose of inspection:


# 491903910901
Unscheduled inspection
Start date: 2019-09-24, end date: 2019-10-21, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Ensuring compliance with and protection of labor rights and freedoms of citizens, including the right to safe working conditions, ensuring compliance by employers with labor legislation and other regulatory legal acts containing labor law norms


# 491902986084
Unscheduled inspection
Start date: 2019-09-02, end date: 2019-09-09, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of the completeness of the quality and timeliness of the execution of the previously issued instruction dated November 12, 2018 03156rP2018 on the elimination of violations identified during the scheduled on-site inspection of Pavlik JSC


# 491902985627
Unscheduled inspection
Start date: 2019-07-26, end date: 2019-08-02, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms 4972719OB dated 17012019 on the application Ensuring compliance with and protection of labor rights and freedoms of citizens including the right to safe working conditions compliance with mandatory requirements and or requirements established by municipal legal acts Compliance with mandatory requirements and or requirements established by compliance with mandatory requirements and or requirements established by municipal legal acts


# 001902857102
Unscheduled inspection
Start date: 2019-07-09, end date: 2019-07-25, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to implement the inspection programs dated 24092018 for the implementation of state planning supervision of the construction and reconstruction of capital construction facilities of the Northeast Department of Rostechnadzor in 2019. The purpose of this inspection is to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation during the construction of the facility, committed by the developer, the technical customer, as well as by persons engaged in construction on the basis of an agreement with the Developer or the technical customer capital construction "Tailings and turnaround water supply "Dam of stage II tailings protected in search of sorption" in accordance with the project documentation "Mining and processing enterprise based on the Pavlik gold deposit" Magadan region Tenkinsky district Correction of design solutions for tailings facilities design characteristics are indicated in the list of capital construction facilities"owned by the joint-stock company Zolotorudnaya CompanyavlikThe subject of this audit is 1 the conformity of the work performed and the construction materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping the capital construction facility with metering devices for energy resources used.2 The availability of a construction permit.3 the fulfillment of the requirements established by Parts 2 3 and 31 of the article 52


# 001902846341
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-07-29, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of this final verification of the compliance of the constructed capital construction facility with the requirements of the technical regulations of the design documentation of the working documentation of the Urban Planning Code of the Russian Federation and other regulatory legal acts is carried out by YAG on the basis of the notice of completion of construction"a dated 17062019 4Present 1 compliance of the work and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency, with the exception of capital construction projects that are not subject to energy efficiency requirements and the requirements for equipping a capital construction facility with metering devices for energy resources used 2 the availability of a construction permit 3 the fulfillment of the requirements established by Parts 2 3 and 31 of Article 52 of the Urban Code of the Russian Federation


# 491902690415
Unscheduled inspection
Start date: 2019-05-06, end date: 2019-05-08, duration:
Authority: Upravlenie arhitektury i gradostroitelstva Magadanskoi oblasti
Purpose of inspection: The purpose of the inspection is the fulfillment by Pavlik JSC of regulation 04181 dated 21122018 issued by the Department of Architecture and Urban Planning of the Magadan region based on the results of an inspection of the construction of the capital construction facility "Fuel Depot" in accordance with the project documentation "Mining and Processing Enterprise based on the Pavlik gold deposit"Magadan Region Tenkinsky District" located at Magadan region Tenkinsky district Pavlik ruch tract Vanin ruch Tenkinskoe forestry Tenkinskoe district forestry quarter 29 specified in paragraph 1 of the inspection program case 0418 in connection with the receipt from Pavlik JSC of notice 1 dated 22042019 on the elimination of violations during the construction of the reconstruction of the capital construction facility Verification tasks verification of the actual fulfillment by Pavlik JSC of instruction 04181 dated 21122018 Subject verification of the execution of an instruction issued by the state control supervision body and or the municipal control body


# 491902696987
Unscheduled inspection
Start date: 2019-04-19, end date: 2019-04-30, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Ensuring compliance with and protection of labor rights and freedoms of citizens, including the right to safe working conditions, ensuring compliance by employers with labor legislation and other regulatory legal acts containing labor law norms


# 001902636946
Unscheduled inspection
Start date: 2019-04-08, end date: 2019-04-22, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to verify the compliance of the constructed capital construction facility with the requirements of technical regulations design documentation working documentation of the Urban Planning Code of the Russian Federation and other regulatory legal acts based on the notice of completion of construction dated 04042019 1 The task is to prevent identify and suppress violations of legislation on urban development committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including among the technical regulations and design documentation for the construction of the capital construction facility "Tailings dump of flotation tailings "Tier 5 collapse dam" in accordance with the design documentation "Mining and processing enterprises based on the Pavlik gold deposit" Magadan region Tenkinsky district Adjustment of design solutions for tailings facilities" owned by Joint Stock Company PAVLIK Gold Mining Company Subject 1 compliance performance of works and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work to the requirements of project documentation including energy efficiency requirements except for capital construction facilities to which energy efficiency requirements do not apply and to the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 Articles 52 of the Urban Planning Code of the Russian Federation


# 001902636939
Unscheduled inspection
Start date: 2019-04-08, end date: 2019-04-22, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to verify the fulfillment of the previously issued regulation dated 01022019 1 on the basis of notification 1 on the elimination of violations dated 03042019 The task is to prevent identify and suppress violations of urban planning legislation committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of the capital construction facility "Tailing dump tailings of the flotation "Tier 5 collapse dam" in accordance with the project documentation "Mining and processing enterprises based on the Pavlik gold deposit" Magadan region Tenkinsky district Adjustment of design solutions for tailings facilities" owned by Joint Stock Company PAVLIK Gold Mining Company Subject to compliance with the instructions of state control bodies and municipal control bodies


# 491902621339
Unscheduled inspection
Start date: 2019-03-13, end date: 2019-03-29, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Ensuring compliance with and protection of labor rights and freedoms of citizens, including the right to safe working conditions, ensuring compliance by employers with labor legislation and other regulatory legal acts containing labor law norms


# 491902577271
Unscheduled inspection
Start date: 2019-03-18, end date: 2019-03-26, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: carrying out licensing activities attributed by the legislation and regulatory legal acts of the Russian Federation to the competence of Rostechnadzor on the basis of an application for renewal of the license for the type of activity "Production of surveying works" from the licensee JSC Pavlik dated 26022019 g vx 76749


# 491902651442
Unscheduled inspection
Start date: 2019-01-14, end date: 2019-02-08, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Federal State supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms 10001244260 Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms Ensuring compliance and protection of labor rights and freedoms of citizens including the right to safe working conditions ensuring compliance by employers with labor law legislation and other regulatory legal acts containing labor law norms


# 001902435957
Unscheduled inspection
Start date: 2019-01-14, end date: 2019-02-04, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to implement the inspection program dated 24092018 for the implementation of state construction supervision over the construction and reconstruction of capital construction facilities of the Northeastern Department of Rostechnadzor for 2018-2019. The task is to prevent identify and intersect violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer during the construction of the capital construction facility, Tailings facilities and circulating water supply Dam 2 stages of the sorption tailings dam in accordance with the design documentation Mining and processing enterprises based on the Pavlik gold deposit Magadan region Tenkinsky district Adjustment of design solutions for tailings facilities owned by joint stock company PAVLIK Gold Mining Company Items 1 compliance of work and construction materials used during the construction reconstruction of the capital construction reconstruction of the capital construction facility as well as the results of such work requirements of project documentation including energy efficiency requirements with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 23 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 491902651439
Unscheduled inspection
Start date: 2019-01-22, end date: 2019-02-18, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Federal State supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms 10001244260 Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms Ensuring compliance and protection of labor rights and freedoms of citizens including the right to safe working conditions ensuring compliance by employers with labor law legislation and other regulatory legal acts containing norms of labor law


# 001902497543
Unscheduled inspection
Start date: 2019-01-09, end date: 2019-02-01, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to comply with the previously issued instruction dated 21092018 056192018C The task is to prevent the identification and intersection of violations of urban planning legislation committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of a capital construction facility Waste rock dumps Adjustments performed according to working documentation Mining and processing enterprises on on the basis of the PAVLIK gold deposit, Magadan region, Tenkinsky district, Adjustment of design solutions for tailings facilities, Waste rock dumps, Adjustment of the PAVLIK Gold Mining Company owned by Joint Stock Company, subject to compliance with the instructions of state control bodies, supervision bodies, municipal control bodies


# 001902439146
Unscheduled inspection
Start date: 2019-01-09, end date: 2019-02-01, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to verify the fulfillment of the previously issued regulation dated 21092018 056192018C The task is to ensure the compliance of the work and the construction materials used during the construction of the facility eliminate violations committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer of violations of legislation on urban development, including technical regulations in the design documentation during the construction of the capital construction facility. Mining and processing enterprise based on the PAVLIK gold deposit, Magadan Region, Tenkinsky district, Adjustment of design solutions for tailings facilities, Waste rock dumps, Adjustment of PAVLIK Gold Mining Company Items 1. compliance of work performed and construction materials used during construction, reconstruction of the capital construction facility, reconstruction of the capital construction facility, as well as the results of such work requirements of the project documentation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 23 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 001902439112
Unscheduled inspection
Start date: 2019-01-09, end date: 2019-02-01, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to implement the inspection program dated 15/12/2018 for the implementation of state construction supervision over the construction and reconstruction of capital construction facilities of the Rostechnadzor Northeast Directorate for 2018-2019. The task is to prevent identify and intersect violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer during the construction of the capital construction facility, the tailings tailings dam and the collapse dam of tier 5, in accordance with the design documentation, Mining and processing enterprises based on the Pavlik gold deposit, Magadan Region, Tenkinsky district, Adjustment of design solutions for tailings facilities owned by the joint-stock company PAVLIK Gold Mining Company, Items 1 compliance of work and construction materials used during the construction of the reconstruction of the capital construction facility reconstruction of the capital construction facility construction as well as the results of such work to the requirements of project documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and to the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 23 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 001902435618
Unscheduled inspection
Start date: 2019-01-09, end date: 2019-02-01, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to verify the fulfillment of the previously issued regulation dated 21092018 056192018C The task is to prevent identify and intersect violations of urban planning legislation committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation during the construction of a capital construction facility Waste rock dumps Adjustments performed according to working documentation Mining and processing the enterprise based on the PAVLIK gold deposit Magadan region Tenkinsky district Adjustment of design solutions for tailings facilities Waste rock dumps Adjustment of the PAVLIK Gold Ore Company owned by Joint Stock company Items 1 compliance of work performed and construction materials used during construction reconstruction of the capital construction facility reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation including energy efficiency requirements with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 23 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 491801946418
Unscheduled inspection
Start date: 2018-09-10, end date: —, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection:


# 491801946695
Unscheduled inspection
Start date: 2018-08-20, end date: —, duration:
Authority:
Purpose of inspection:


# 491800494854
Unscheduled inspection
Start date: 2018-07-04, end date: 2018-06-18, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to verify the fulfillment of the previously issued prescription from 25052018 056172018C


# 491800490644
Unscheduled inspection
Start date: 2018-07-04, end date: 2018-07-19, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Magadanskoi oblasti
Purpose of inspection: verification of compliance with the instructions of the official authorized to carry out federal state sanitary and epidemiological supervision and federal state supervision in the field of consumer rights protection and human well-being 36 dated 06102017


# 491802002185
Unscheduled inspection
Start date: 2018-06-05, end date: 2018-06-29, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Ensuring compliance with and protection of labor rights and freedoms of citizens, including the right to safe working conditions, ensuring compliance by employers with labor legislation and other regulatory legal acts containing labor law norms


# 491800582028
Unscheduled inspection
Start date: 2018-06-26, end date: 2018-07-23, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: To establish that this audit is conducted in order to exercise federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms in connection with the appeal 49717818OB on violation of the labor rights of employees the objectives of this audit are to ensure compliance with and protection of labor rights and freedoms of citizens including the right to safe working conditions 7 The subject of this audit is to note the necessary compliance with mandatory requirements and or requirements established by municipal legal acts


# 491800582037
Unscheduled inspection
Start date: 2018-05-14, end date: 2018-06-08, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Ensuring compliance with and protection of labor rights and freedoms of citizens, including the right to safe working conditions, ensuring compliance by employers with labor legislation and other regulatory legal acts containing labor law norms


# 491800318886
Unscheduled inspection
Start date: 2018-05-08, end date: 2018-06-05, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: 6 To establish that this audit is conducted in order to exercise federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms in connection with the appeal 49719418OB on violation of Chekmenev's labor rights. The objectives of this audit are to ensure compliance with and protection of labor rights and freedoms of citizens, including the right to safe working conditions 7 The subject of this audit is to note the necessary compliance with mandatory requirements and or requirements established by municipal legal acts


# 001801264496
Unscheduled inspection
Start date: 2018-04-26, end date: 2018-05-25, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to implement the program of inspections for the implementation of state construction supervision over the construction and reconstruction of capital construction facilities of Rostechnadzor Northeast Directorate for 2018. The task is to prevent identify and suppress violations of legislation on urban development, including technical regulations, committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer. project documentation for the construction of the capital construction facility "Tailings dump of flotation tailings "Tier 4 collapse dam" in accordance with the project documentation "Mining and processing enterprises based on the Pavlik gold deposit" Magadan region Tenkinsky district Adjustment of design solutions for tailings facilities" The subject of this audit is the compliance of the work and the construction materials used during the construction of the reconstruction facility capital construction as well as the results of such work, the requirements of technical regulations and project documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used


# 001801264429
Unscheduled inspection
Start date: 2018-04-26, end date: 2018-05-25, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to implement the inspection program from 17042018 for the implementation of state construction supervision over the construction of a capital construction facility of the Rostechnadzor Northeast Directorate for 2018. prevention detection and suppression of violations of urban planning legislation committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and design documentation documentation during the construction of the capital construction facility "Waste rock dumps Adjustment" performed according to the working documentation "Mining and processing enterprise based on the PAVLIK gold deposit" Magadan region Tenkinsky district Adjustment of design solutions for tailings facilities " Waste rock dumps Adjustment" The subject of this audit is the compliance of the work and the construction materials used during the construction of the reconstruction of the capital construction as well as the results of such work to the requirements of technical regulations and project documentation, including energy efficiency requirements, requirements for equipping a capital construction facility with metering devices for used energy resources


# 491802007831
Unscheduled inspection
Start date: 2018-02-26, end date: 2018-03-27, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Ensuring compliance with and protection of labor rights and freedoms of citizens, including the right to safe working conditions, ensuring compliance by employers with labor legislation and other regulatory legal acts containing labor law norms


# 491802007861
Unscheduled inspection
Start date: 2018-01-15, end date: 2018-02-08, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: Ensuring compliance with and protection of labor rights and freedoms of citizens, including the right to safe working conditions, ensuring compliance by employers with labor legislation and other regulatory legal acts containing labor law norms


# 001800833399
Unscheduled inspection
Start date: 2018-01-29, end date: 2018-02-16, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This unscheduled on-site inspection is carried out in order to monitor the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility on the basis of the notice of completion of construction dated 24.012018 3 The purpose of this inspection is to prevent identify and suppress violations committed by the developer, the technical customer, as well as by persons carrying out construction on based on an agreement with the developer or a technical customer for violations of legislation on urban development, including technical regulations and design documentation during the construction of the capital construction facility "Tier 3 Collapse Dam" in accordance with the design documentation "Mining and processing enterprise based on the Pavlik gold deposit" Magadan region Tenkinsky district Adjustment of design solutions for tailings facilities". The purpose of this check is to ensure that the work performed and the building materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used


# 49170802966086
Unscheduled inspection
Start date: 2017-12-12, end date: 2018-01-16, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: This audit is conducted with the aim of implementing federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms in connection with the consideration of the appeal dated 28112017 768717 on violation of Matveenko's labor rights. The objectives of this audit are to ensure compliance with and protection of labor rights and freedoms of citizens, including the right to safe working conditions, ensuring compliance by employers with labor legislation and other regulatory legal acts containing norms of labor law7 The subject of this audit is to note the necessary compliance with mandatory requirements or requirements established by municipal legal acts


# 49170802880421
Unscheduled inspection
Start date: 2017-11-23, end date: 2017-12-08, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: as part of the performance of the state function of state construction supervision during the construction of capital construction facilities specified in p 51 st6 of the Urban Planning Code of the Russian Federation, with the exception of those facilities in respect of which state construction supervision is entrusted by decrees of the President of the Russian Federation to other federal executive authorities registration number of the function 10001515438 Verification is carried out in order to implement a program of inspections for the implementation of state construction supervision over the construction and reconstruction of capital construction facilities of Rostechnadzor Northeast Directorate for 2017


# 00170802752014
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-05, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The present final inspection is carried out in order to ensure that the constructed capital construction facility meets the requirements of technical regulations of other regulatory legal acts and project documentation based on the completion notice dated 22092017 2The task is to assess the compliance of the work performed with the requirements of technical regulations of other regulatory legal acts and project documentation to identify violations deficiencies in relation to the work performed during the construction of the capital construction facility Tailings dump Flotation dam Tier 2 provides for verification of compliance with mandatory requirements or requirements established by municipal legal acts


# 49170701658574
Unscheduled inspection
Start date: 2017-06-05, end date: 2017-06-09, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: an unscheduled on-site inspection is carried out as part of the performance of the state function of state construction supervision during the construction of capital construction facilities specified in p 51 st6 of the Urban Planning Code of the Russian Federation, with the exception of those facilities for which the implementation of state construction supervision by decrees of the President of the Russian Federation is entrusted to other federal executive authorities registration number of the function 10001515438the current final verification of the conformity of the constructed capital construction facility construction according to the requirements of technical regulations, other regulatory legal acts and project documentation is carried out on the basis of the notice of completion of construction dated 07052017 1


# 49170701467246
Unscheduled inspection
Start date: 2017-03-20, end date: 2017-03-24, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of the Regulation on the regime of permanent supervision at Hazardous Production Facilities


# 49160701358725
Unscheduled inspection
Start date: 2016-12-14, end date: —, duration:
Authority:
Purpose of inspection:


# 49160701213927
Unscheduled inspection
Start date: 2016-11-28, end date: —, duration:
Authority:
Purpose of inspection:


# 49160701198512
Unscheduled inspection
Start date: 2016-10-24, end date: 2016-11-21, duration:
Authority: Gosudarstvennaya inspekciya truda v Magadanskoi oblasti
Purpose of inspection: protection of the rights and interests of employees in terms of ensuring the safe performance of work in connection with accidents that have occurred with employees of Pavlik JSC supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms compliance with mandatory requirements or requirements established by municipal legal acts prevention of harm to the life health of citizens harm to animals plants and the environment


# 49160701019284
Unscheduled inspection
Start date: 2016-09-15, end date: 2016-09-19, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: federal state supervision in the field of industrial safety compliance with mandatory requirements


# 49160700044548
Unscheduled inspection
Start date: 2016-07-04, end date: 2016-07-12, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of the compliance of the completed works with the requirements of the technical regulations of the Urban Planning Code of the Russian Federation


# 49160700044540
Unscheduled inspection
Start date: 2016-07-04, end date: 2016-07-12, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of the compliance of the completed works with the requirements of the technical regulations of the Urban Planning Code of the Russian Federation


# 49160700044477
Unscheduled inspection
Start date: 2016-07-04, end date: 2016-07-12, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of compliance of the performed works with the requirements of technical regulations and the Civil Code of the Russian Federation


# 49160700044527
Unscheduled inspection
Start date: 2016-07-04, end date: 2016-07-12, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of the compliance of the completed works with the requirements of the technical regulations of the Urban Planning Code of the Russian Federation


# 49160700044464
Unscheduled inspection
Start date: 2016-07-04, end date: 2016-07-12, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of compliance of the performed works with the requirements of technical regulations and the Civil Code of the Russian Federation


# 49160700044512
Unscheduled inspection
Start date: 2016-07-04, end date: 2016-07-12, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of the compliance of the completed works with the requirements of the technical regulations of the Urban Planning Code of the Russian Federation


# 49160700044449
Unscheduled inspection
Start date: 2016-07-04, end date: 2016-07-12, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of compliance of works with the requirements of those regulations


# 49160700044438
Unscheduled inspection
Start date: 2016-07-04, end date: —, duration:
Authority:
Purpose of inspection:


# 49160700044345
Unscheduled inspection
Start date: 2016-07-04, end date: 2016-07-12, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of the conformity of completed works


# 49160700044500
Unscheduled inspection
Start date: 2016-07-04, end date: 2016-07-12, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of the compliance of the completed works with the requirements of the technical regulations of the Urban Planning Code of the Russian Federation


# 49160700044430
Unscheduled inspection
Start date: 2016-07-04, end date: 2016-07-12, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of compliance of works with the requirements of those regulations


# 49160601793791
Unscheduled inspection
Start date: 2016-07-07, end date: 2016-07-25, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of compliance of the performed works with the requirements of technical regulations, other regulatory legal acts and project documentation elimination of violations and deficiencies in relation to the performed works identified during construction control during the construction of the facility


# 49160601793788
Unscheduled inspection
Start date: 2016-07-07, end date: 2016-07-25, duration:
Authority: SeveroVostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of compliance of the performed works with the requirements of technical regulations, other regulatory legal acts and project documentation elimination of violations and deficiencies in relation to the performed works identified during construction control during the construction of the facility


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.