# 162100271164
Unscheduled inspection
Start date: 2021-06-07, end date: —, duration: —
Authority: Sredne-Volzhskoe Mezhregionalnoe upravlenie gosudarstvennogo avtodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: The purpose of the audit:
to determine the possibility of the license applicant/licensee fulfilling the licensing requirements, to assess the compliance of the information in the application of the license applicant/ licensee dated 06/03/2021 registration No. 63.01.188-persons and in the documents attached to it with the provisions of parts 1 and 3 of Article 13 (for the license application)/Article 18 (for the application for renewal of the license) Federal Law No. 99-FZ dated 05/04/11 "On Licensing of Certain Types of Activities", as well as information about the license applicant/licensee contained in the unified State Register of Individual Entrepreneurs, in the unified State Register of Legal Entities "
Verification Tasks:
Identification and suppression of violations of regulatory legal acts, regulatory technical acts, standards and norms regulating the activities of the motor transport complex
Subject of verification:
compliance of the information contained in the application and documents of a legal entity or individual entrepreneur for granting a special permit (license), issuing a permit (approval), with mandatory requirements
# 632005196954
Unscheduled inspection
Start date: 2020-10-23, end date: 2020-11-20, duration: —
Authority: Gosudarstvennaya inspekciya truda v Samarskoi oblasti
Purpose of inspection: This audit is conducted in order to carry out federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms The objectives of this audit are to ensure compliance with labor legislation and protection of labor rights The subject of this audit is compliance with the requirements of labor legislation and other regulatory legal acts containing labor law norms
# 161904321842
Unscheduled inspection
Start date: 2019-10-02, end date: 2019-10-29, duration: —
Authority: Upravlenie Federalnoi sluzhby po veterinarnomu i fitosanitarnomu nadzoru po Respublike Tatarstan
Purpose of inspection: Carrying out control and supervision measures to comply with the previously issued instruction on the elimination of the detected violation
# 161904317926
Unscheduled inspection
Start date: 2019-07-01, end date: —, duration: —
Authority: Upravlenie Federalnoi sluzhby po veterinarnomu i fitosanitarnomu nadzoru po Respublike Tatarstan
Purpose of inspection:
# 161902801155
Unscheduled inspection
Start date: 2019-05-20, end date: 2019-06-17, duration: —
Authority: Upravlenie Federalnoi sluzhby po veterinarnomu i fitosanitarnomu nadzoru po Respublike Tatarstan
Purpose of inspection: Carrying out control and supervision measures to comply with the previously issued instruction on the elimination of the detected violation
# 161903646404
Unscheduled inspection
Start date: 2019-01-09, end date: 2019-02-05, duration: —
Authority: Upravlenie Federalnoi sluzhby po veterinarnomu i fitosanitarnomu nadzoru po Respublike Tatarstan
Purpose of inspection: Carrying out control and supervision measures based on the results of a planned inspection in connection with the revealed violation of mandatory requirements of the land legislation of the Russian Federation
# 631801088417
Unscheduled inspection
Start date: 2018-09-13, end date: 2018-09-14, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 161801120414
Unscheduled inspection
Start date: 2018-09-14, end date: 2018-09-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of a capital construction facility with the construction materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. Verification of the construction permit and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 10042018 case 151120180014 prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of the compliance of works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts
# 161801123524
Unscheduled inspection
Start date: 2018-09-14, end date: 2018-09-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of a capital construction facility with the construction materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. Verification of the construction permit and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 10042018 case 151120180015 prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts
# 631800896072
Unscheduled inspection
Start date: 2018-09-06, end date: 2018-09-07, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 161800532400
Unscheduled inspection
Start date: 2018-07-13, end date: 2018-07-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of a capital construction facility with the construction materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. Verification of the construction permit and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 10042018 case 151120180014 prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of the compliance of works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts
# 161800532291
Unscheduled inspection
Start date: 2018-07-13, end date: 2018-07-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of a capital construction facility with the construction materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. Verification of the construction permit and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 10042018 case 151120180015 prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts
# 161800299408
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-05-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of a capital construction facility with the construction materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. Verification of the construction permit and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 10042018 case 151120180014 prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of the compliance of works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts
# 161800297938
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-05-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of a capital construction facility with the construction materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. Verification of the construction permit and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 10042018 case 151120180015 prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts
# 161801120332
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-05-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of a capital construction facility with the construction materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. Verification of the construction permit and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 10042018 case 151120180014 prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of the compliance of works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts