Found 19 inspections:

# 002004626159
Unscheduled inspection
Start date: 2020-08-24, end date: 2020-08-28, duration: 5
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to comply with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 08072020 267 "On monitoring the progress of preparation of electric power and Heat supply facilities for operation in the autumn winter period of 20202021" and the order of the Caucasian Directorate of Rostechnadzor dated 10072020 PR410217o "On monitoring the progress of preparation of electric Power and Heat supply facilities for operation in the autumn winter period of 20202021"The purpose of this audit is to establish the fact of fulfillment of non-fulfillment of legal requirements in the established field of activity.


# 00170802866692
Unscheduled inspection
Start date: 2017-11-16, end date: —, duration:
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 262100199578
Unscheduled inspection
Start date: 2021-05-17, end date: —, duration: 20
Authority: Otdel nadzornoi deyatelnosti i profilakticheskoi raboty upravleniya nadzornoi deyatelnosti i profilakticheskoi raboty Glavnogo upravleniya MCHS Rossii po Stavropolskomu krayu (po Izobilnenskomu gorodskomu okrugu i Trunovskomu municipalnomu okrugu)
Purpose of inspection: control of the execution of regulation No. 3/1/3 dated 02/20/2020


# 262005255469
Unscheduled inspection
Start date: 2020-12-04, end date: —, duration:
Authority:
Purpose of inspection:


# 002004626159
Unscheduled inspection
Start date: 2020-08-24, end date: 2020-08-28, duration: 5
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to comply with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 08072020 267 "On monitoring the progress of preparation of electric power and Heat supply facilities for operation in the autumn winter period of 20202021" and the order of the Caucasian Directorate of Rostechnadzor dated 10072020 PR410217o "On monitoring the progress of preparation of electric Power and Heat supply facilities for operation in the autumn winter period of 20202021"The purpose of this audit is to establish the fact of fulfillment of non-fulfillment of legal requirements in the established field of activity.


# 262004457949
Unscheduled inspection
Start date: 2020-07-13, end date: —, duration:
Authority:
Purpose of inspection:


# 262004328620
Unscheduled inspection
Start date: 2020-02-17, end date: 2020-03-06, duration:
Authority: Gosudarstvennaya inspekciya truda v Stavropolskom krae
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms Written request from citizen 26730820OB dated 06022020


# 261904022003
Unscheduled inspection
Start date: 2019-11-27, end date: —, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection:


# 261904022070
Unscheduled inspection
Start date: 2019-11-27, end date: 2019-12-24, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: Purpose notification of completion of construction inspection program dated 18012018 23022018 final inspection The objectives of this inspection are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, technical customer, and person carrying out construction. The subject of this inspection is compliance with the procedure for conducting construction control, maintaining general and or special work logs, executive documentation, and drafting acts inspections of structures of sections of engineering and technical support networks compliance with other requirements when performing work established by the design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for used energy resources compliance with mandatory requirements and or requirements established by municipal legal acts


# 261902826163
Unscheduled inspection
Start date: 2019-06-28, end date: —, duration:
Authority:
Purpose of inspection:


# 261902446404
Unscheduled inspection
Start date: 2019-01-11, end date: 2019-01-25, duration:
Authority: Gosudarstvennaya inspekciya truda v Stavropolskom krae
Purpose of inspection: Protection of the rights and interests of the employee in connection with the consideration of the appeal dated 26122018 267410018OB on violation of labor rights


# 261902470349
Unscheduled inspection
Start date: 2019-01-21, end date: 2019-01-31, duration:
Authority: Gosudarstvennaya inspekciya truda v Stavropolskom krae
Purpose of inspection: Protection of the rights and interests of the employee in connection with the consideration of the appeal dated 17012019 26715919OB on violation of labor rights


# 261800444589
Unscheduled inspection
Start date: 2018-01-24, end date: 2018-02-20, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: notice of the start of construction dated 12.012018 The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, hereinafter referred to as the contractor. The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts


# 261800009404
Unscheduled inspection
Start date: 2018-01-24, end date: 2018-02-20, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: notice of the start of construction dated 12.012018 The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, hereinafter referred to as the contractor. The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts


# 261800009403
Unscheduled inspection
Start date: 2018-01-24, end date: 2018-02-20, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: notice of the start of construction dated 12.012018 The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, hereinafter referred to as the contractor. The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts


# 00170802866692
Unscheduled inspection
Start date: 2017-11-16, end date: 2017-11-20, duration:
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to monitor the fulfillment by Solnechny Dar LLC of the previously issued instruction from 04092017 4565rPL18 on the elimination of violations during the construction of the capital construction facility "External power supply of the greenhouse complex for the production of fruit and vegetable products in an enclosed area of 5722 hectares near Solnechnodolsk, Izobilnensky district, Stavropol Territory, Stage 1". The objectives of this inspection are to monitor the acceptedSunny gift" by measures to comply with the regulation dated 04092017 4565rPL18 and comply with the mandatory requirements of regulatory acts in the field of construction during the construction of the reconstruction of the capital construction facility "External power supply of the greenhouse complex for the production of fruit and vegetable products in an enclosed area of 5722 hectares near Solnechnodolsk, Izobilnensky district of the Stavropol Territory stage 1"measures to identify violations of mandatory requirements and to attract to bring to responsibility persons who have committed violations of the requirements of Federal laws and other regulatory legal acts


# 00170701909869
Unscheduled inspection
Start date: 2017-08-28, end date: 2017-09-04, duration:
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to control the fulfillment by Solnechny Dar LLC of the previously issued instruction from 25052017 g 2445rVP18 on the elimination of violations during the construction of the reconstruction of the capital construction facility "External power supply of the greenhouse complex for the production of fruit and vegetable products in an enclosed area of 5722 hectares near Solnechnodolsk of the Izobilnensky district of the Stavropol Territory Stage 1" the objectives of this inspection are to monitor the accepted LLC Solnechny Dar measures to comply with the regulation of 25052017 g 2445rVP18 compliance with mandatory requirements of regulatory acts in the field of construction and taking measures to identify violations of mandatory requirements and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts


# 26170701400274
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-03-21, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: 1 this inspection is carried out for the purpose of notification of the start of construction dated 15022017 2 The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation3 committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, hereinafter referred to as the contractor. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts


# 26170701400178
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-03-21, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: 1 this inspection is carried out for the purpose of notification of the start of construction dated 15022017 2 The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation3 committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, hereinafter referred to as the contractor. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.