# 002004370380
Unscheduled inspection
Start date: 2020-03-18, end date: 2020-03-31, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used for construction, compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004224867
Unscheduled inspection
Start date: 2020-01-27, end date: —, duration: —
Authority: Federalnaya sluzhba po akkreditacii
Purpose of inspection:
# 002004141025
Unscheduled inspection
Start date: 2020-01-10, end date: —, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001902948569
Unscheduled inspection
Start date: 2019-08-12, end date: —, duration: —
Authority: Federalnaya sluzhba po akkreditacii
Purpose of inspection:
# 001902556055
Unscheduled inspection
Start date: 2019-03-04, end date: 2019-04-01, duration: —
Authority: Federalnaya sluzhba po akkreditacii
Purpose of inspection: proverka svedenii soderzhaschihsya v uvedomlenii ob ustranenii nesootvetstvii kriteriyam akkreditacii predstavlennoe pismom FGUP «VNIIFTRI» ustanovlenie fakta ustraneniya akkreditovannym licom nesootvetstvii ego deyatelnosti trebovaniyam zakonodatelstva Rossiiskoi Federacii k deyatelnosti akkreditovannyh lic ukazannyh v Uvedomlenii o napravlenii perechnya nesootvetstvii kriteriyam akkreditacii po rezultatam okazaniya gosudarstvennoi uslugi po podtverzhdeniyu kompetentnosti soblyudenie obyazatelnyh trebovanii ili trebovanii ustanovlennyh municipalnymi pravovymi aktami
# 00170802754123
Unscheduled inspection
Start date: 2017-10-13, end date: 2017-10-27, duration: —
Authority: Federalnaya sluzhba po akkreditacii
Purpose of inspection: proverka provoditsya s celyu proverki ustraneniya akkreditovannym licom nesootvetstvii ego deyatelnosti trebovaniyam zakonodatelstva Rossiiskoi Federacii k deyatelnosti akkreditovannyh lic otrazhennyh v perechne nesootvetstvii napravlennyh Uvedomleniem o napravlenii perechnya nesootvetstvii ot 11082017 2181604TZHZadachami nastoyaschei proverki yavlyayutsya ustanovlenie fakta ustraneniya akkreditovannym licom nesootvetstvii ego deyatelnosti trebovaniyam zakonodatelstva Rossiiskoi Federacii k deyatelnosti akkreditovannyh lic ukazannyh v Uvedomlenii o napravlenii perechnya nesootvetstvii kriteriyam akkreditacii po rezultatam okazaniya gosudarstvennoi uslugi po podtverzhdeniyu kompetentnosti ot 11082017 2181604TZHPredmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii ili trebovanii ustanovlennyh municipalnymi pravovymi aktami
# 772100313385
Unscheduled inspection
Start date: 2021-06-29, end date: —, duration: 2
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya FGUP «VNIIFTRI» ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii ot 01.10.2019 № 5.2-2446vn-P/0094-2019 (dalee – Predpisanie).
Zadachei nastoyaschei proverki yavlyaetsya ustanovlenie faktov vypolneniya (nevypolneniya) FGUP «VNIIFTRI» Predpisaniya.
7. Predmetom nastoyaschei proverki yavlyaetsya vypolnenie FGUP «VNIIFTRI» Predpisaniya.
# 542100138863
Unscheduled inspection
Start date: 2021-04-15, end date: 2021-05-14, duration: 20
Authority: Glavnoe upravlenie MCHS Rossii po Novosibirskoi oblasti
Purpose of inspection: Kontrol ispolneniya predpisaniya Glavnogo upravleniya MCHS Rossii po Novosibirskoi oblasti ot 01.08.2019 № 59
# 542100138930
Unscheduled inspection
Start date: 2021-04-15, end date: 2021-05-14, duration: 20
Authority: Glavnoe upravlenie MCHS Rossii po Novosibirskoi oblasti
Purpose of inspection: Kontrol ispolneniya predpisaniya Glavnogo upravleniya MCHS Rossii po Novosibirskoi oblasti ot 03.09.2019 № 63
# 772100159265
Unscheduled inspection
Start date: 2021-04-29, end date: 2021-05-14, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the performed works with the mandatory requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility; the task of this check is to prevent, identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on on the basis of an agreement with a developer or technical customer, violations of legislation on urban development, including design documentation, requirements for energy conservation and energy efficiency improvement;
The subject of this review is:compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the design documentation in accordance with Parts 3.8 and 3.9 of Article 49 of the Urban Planning Code Of the Russian Federation) and (or) an information model, including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices for used energy resources;
availability of a building permit;
compliance with the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 502100140879
Unscheduled inspection
Start date: 2021-04-05, end date: 2021-04-23, duration: —
Authority: Glavnoe upravlenie Moskovskoi oblasti «Gosudarstvennaya zhilischnaya inspekciya Moskovskoi oblasti»
Purpose of inspection: Compliance with mandatory requirements or requirements established by municipal legal acts; Verification of facts stated in the application of other persons; Verification of completeness, reliability, relevance of information posted by management organizations in the GIS housing and communal services system
# 772100028145
Unscheduled inspection
Start date: 2021-03-11, end date: 2021-03-12, duration: 2
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ot 17.09.2020 № 5.3-2320vn-P/0339-2020, srok dlya ispolneniya kotorogo istek
# 002005223781
Unscheduled inspection
Start date: 2020-11-19, end date: 2020-12-02, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipment of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made in the design documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of the article 52 of the Urban Planning Code of the Russian Federation
# 002004448354
Unscheduled inspection
Start date: 2020-07-15, end date: 2020-07-28, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made in the design documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of the article 52 of the Urban Planning Code of the Russian Federation
# 002004370380
Unscheduled inspection
Start date: 2020-03-18, end date: 2020-03-31, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used for construction, compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 502004268792
Unscheduled inspection
Start date: 2020-02-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002004224867
Unscheduled inspection
Start date: 2020-01-27, end date: 2020-02-21, duration: —
Authority: Federalnaya sluzhba po akkreditacii
Purpose of inspection: proverka provoditsya s celyu proverki ustraneniya narushenii ukazannyh v Uvedomlenii o napravlenii perechnya nesootvetstvii kriteriyam akkreditacii po rezultatam okazaniya gosudarstvennoi uslugi po podtverzhdeniyu kompetentnosti ot 06112019 2605104AVZadachami nastoyaschei proverki yavlyayutsya ustanovlenie fakta ustraneniya akkreditovannym licom nesootvetstvii ego deyatelnosti trebovaniyam zakonodatelstva Rossiiskoi Federacii k deyatelnosti akkreditovannyh lic ukazannyh v Uvedomlenii o napravlenii perechnya nesootvetstvii kriteriyam akkreditacii po rezultatam okazaniya gosudarstvennoi uslugi po podtverzhdeniyu kompetentnosti ot 06112019 2605104AVPredmetom nastoyaschei proverki yavlyaetsyasoblyudenie obyazatelnyh trebovanii ili trebovanii ustanovlennyh municipalnymi pravovymi aktami
# 002004141025
Unscheduled inspection
Start date: 2020-01-10, end date: 2020-01-16, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya FGUP «VNIIFTRI» ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii ot 01102019 522446vnP00942019 dalee Predpisanie Zadachei nastoyaschei proverki yavlyaetsya ustanovlenie faktov vypolneniya nevypolneniya FGUP «VNIIFTRI» Predpisaniya Predmetom nastoyaschei proverki yavlyaetsya vypolnenie FGUP «VNIIFTRI» Predpisaniya
# 001903250906
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-10-01, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya FGUP «VNIIFTRI» ranee vydannogo predpisaniya ob ustranenii vyyavlennyh narushenii ot 07062019 521055plP00472019 dalee Predpisanie Zadachei nastoyaschei proverki yavlyaetsya ustanovlenie faktov vypolneniya nevypolneniya FGUP «VNIIFTRI» Predpisaniya Predmetom nastoyaschei proverki yavlyaetsya vypolnenie FGUP «VNIIFTRI» Predpisaniya
# 001902948569
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-09-06, duration: —
Authority: Federalnaya sluzhba po akkreditacii
Purpose of inspection: the purpose of checking the information contained in the report on the elimination of inconsistencies with the accreditation criteria is to establish the fact that an accredited person eliminates inconsistencies in his activities with the requirements of the legislation of the Russian Federation for the activities of accredited persons specified in the Notification of sending a list of inconsistencies with the accreditation criteria based on the results of the provision of public services to confirm competence the subject is compliance with mandatory requirements or requirements established by municipal legal acts
# 501902876237
Unscheduled inspection
Start date: 2019-07-15, end date: 2019-08-09, duration: —
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection: protection of the rights and interests of employees
# 501902793306
Unscheduled inspection
Start date: 2019-06-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 381902700291
Unscheduled inspection
Start date: 2019-05-06, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya truda v Irkutskoi oblasti
Purpose of inspection:
# 381902587623
Unscheduled inspection
Start date: 2019-03-18, end date: 2019-04-12, duration: —
Authority: Gosudarstvennaya inspekciya truda v Irkutskoi oblasti
Purpose of inspection: Ensuring the observance and protection of the labor rights and freedoms of citizens, including the right to safe working conditions
# 001902556055
Unscheduled inspection
Start date: 2019-03-04, end date: 2019-04-01, duration: —
Authority: Federalnaya sluzhba po akkreditacii
Purpose of inspection: proverka svedenii soderzhaschihsya v uvedomlenii ob ustranenii nesootvetstvii kriteriyam akkreditacii predstavlennoe pismom FGUP «VNIIFTRI» ustanovlenie fakta ustraneniya akkreditovannym licom nesootvetstvii ego deyatelnosti trebovaniyam zakonodatelstva Rossiiskoi Federacii k deyatelnosti akkreditovannyh lic ukazannyh v Uvedomlenii o napravlenii perechnya nesootvetstvii kriteriyam akkreditacii po rezultatam okazaniya gosudarstvennoi uslugi po podtverzhdeniyu kompetentnosti soblyudenie obyazatelnyh trebovanii ili trebovanii ustanovlennyh municipalnymi pravovymi aktami
# 501800431820
Unscheduled inspection
Start date: 2018-06-04, end date: 2018-06-20, duration: —
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection: compliance with the requirements of labor legislation protection of the rights and interests of employees in connection with the receipt of appeals supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms
# 501800399510
Unscheduled inspection
Start date: 2018-05-21, end date: 2018-06-18, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Moskovskoi oblasti
Purpose of inspection: realizaciya Prikaza Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka ot 14052018 goda 351 «O provedenii vneplanovyh proverok za soblyudeniem pravil priostanovleniya deyatelnosti opasnyh proizvodstv i organizacii» zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie narushenii trebovanii zakonodatelstva Rossiiskoi Federacii v oblasti obespecheniya sanitarno epidemiologicheskogo blagopoluchiya naseleniya
# 00170802754123
Unscheduled inspection
Start date: 2017-10-13, end date: 2017-10-27, duration: —
Authority: Federalnaya sluzhba po akkreditacii
Purpose of inspection: proverka provoditsya s celyu proverki ustraneniya akkreditovannym licom nesootvetstvii ego deyatelnosti trebovaniyam zakonodatelstva Rossiiskoi Federacii k deyatelnosti akkreditovannyh lic otrazhennyh v perechne nesootvetstvii napravlennyh Uvedomleniem o napravlenii perechnya nesootvetstvii ot 11082017 2181604TZHZadachami nastoyaschei proverki yavlyayutsya ustanovlenie fakta ustraneniya akkreditovannym licom nesootvetstvii ego deyatelnosti trebovaniyam zakonodatelstva Rossiiskoi Federacii k deyatelnosti akkreditovannyh lic ukazannyh v Uvedomlenii o napravlenii perechnya nesootvetstvii kriteriyam akkreditacii po rezultatam okazaniya gosudarstvennoi uslugi po podtverzhdeniyu kompetentnosti ot 11082017 2181604TZHPredmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii ili trebovanii ustanovlennyh municipalnymi pravovymi aktami
# 50170701490831
Unscheduled inspection
Start date: 2017-04-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 38160601644586
Unscheduled inspection
Start date: 2016-06-14, end date: —, duration: —
Authority: —
Purpose of inspection: