# 772100189161
Unscheduled inspection
Start date: 2021-05-11, end date: 2021-05-19, duration: 7
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772100132539
Unscheduled inspection
Start date: 2021-04-08, end date: 2021-04-21, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772100029527
Unscheduled inspection
Start date: 2021-02-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100029622
Unscheduled inspection
Start date: 2021-02-24, end date: 2021-03-24, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772100029633
Unscheduled inspection
Start date: 2021-02-24, end date: 2021-03-24, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772100029630
Unscheduled inspection
Start date: 2021-02-24, end date: 2021-03-24, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772100029522
Unscheduled inspection
Start date: 2021-02-24, end date: 2021-03-24, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772100029526
Unscheduled inspection
Start date: 2021-02-24, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100029524
Unscheduled inspection
Start date: 2021-02-24, end date: 2021-03-24, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772100029558
Unscheduled inspection
Start date: 2021-02-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005265074
Unscheduled inspection
Start date: 2020-12-08, end date: 2020-12-16, duration: 7
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person The subject of verification is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of project documentation identified during construction control and state construction supervision
# 772005266736
Unscheduled inspection
Start date: 2020-12-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005200692
Unscheduled inspection
Start date: 2020-11-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005222165
Unscheduled inspection
Start date: 2020-11-12, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772005170876
Unscheduled inspection
Start date: 2020-10-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004466841
Unscheduled inspection
Start date: 2020-07-27, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 002004667972
Unscheduled inspection
Start date: 2020-07-16, end date: 2020-09-12, duration: 20
Authority: Upravlenie gosudarstvennogo aviacionnogo nadzora i nadzora za obespecheniem transportnoi bezopasnosti po Centralnomu federalnomu okrugu
Purpose of inspection: state supervision over the observance and execution by a legal entity of the legislation of the Russian Federation in the field of civil aviation in connection with the requirement to conduct an audit of the Moscow Interregional Transport Prosecutor's Office dated 29052020 7452020compliance with LLC FIRST MOSCOW air legislation of the Russian Federation on civil aviation and international treaties of the Russian Federation in the field of civil aviation
# 77180803298069
Unscheduled inspection
Start date: 2018-12-14, end date: 2018-12-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used