# 002005298248
Unscheduled inspection
Start date: 2020-11-02, end date: 2020-11-27, duration: 19
Authority: SeveroKavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to verify the completed construction of a capital construction facility on the basis of a notice dated 16092020 and 012100 on the completion of the construction of a capital construction facility, the objectives of this audit are the Federal State Construction Supervision. The purpose of this audit is to comply with mandatory requirements or requirements established by municipal legal acts for the compliance of work performed and construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with technical requirements regulations of the project documentation for obtaining a construction permit to comply with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code
# 002004270917
Unscheduled inspection
Start date: 2020-02-27, end date: 2020-03-26, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is celosamente Federal state construction supervision within the competence of Rostekhnadzor in the construction, reconstruction of all the objects referred to in paragraph 51 of article 6 of the town planning code of the Russian Federation on the basis of the audit programme what not less than three business days prior to its implementation to notify the legal entity in any way allows you to control receiving notification adrenalised of this review is to prevent detection and suppression approved developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer hereinafter called the contractor violations of the legislation on town-planning activities including technical regulations and project documentlibraries present validation of yavlyaetsyasredstvom perform work and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of this Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices used energy resourcevalue permissions stroitelstvoimoti the requirements set forth in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 001902665886
Unscheduled inspection
Start date: 2019-04-22, end date: 2019-05-15, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: control of previously issued regulations on the elimination of violations of fire safety requirements from 26062018 31211
# 00170802720377
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-10-27, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the implementation of previously issued regulations from 23062017 5041282059PR in connection with the expiration of deadlines
# 00170701775255
Unscheduled inspection
Start date: 2017-08-07, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00170701441723
Unscheduled inspection
Start date: 2017-03-13, end date: 2017-03-17, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution of a previously issued prescription
# 232100136023
Unscheduled inspection
Start date: 2021-03-29, end date: 2021-04-02, duration: 5
Authority: Severo-Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation of paragraph 2 of Regulation No. 980-148-25-18 dated 10/22/2019.
The task is to verify the implementation of paragraph 2 of the regulation dated 10/22/2019 No. 980-148-25-18.
The subject is the fulfillment of the instructions of state control (supervision) bodies and municipal control bodies.
# 232100135919
Unscheduled inspection
Start date: 2021-03-29, end date: 2021-04-02, duration: 5
Authority: Severo-Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation of paragraphs 2, 3 of Regulation No. 981-148-25-18 dated 10/22/2019.
The task is to check paragraphs 2, 3 of the regulation dated 22.10.2019 No. 981-148-25-18.
Subject - - compliance with the regulations of state control (supervision) bodies, municipal control bodies
# 232100135827
Unscheduled inspection
Start date: 2021-03-29, end date: 2021-04-02, duration: 5
Authority: Severo-Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The goal is to control the fulfillment of points 1, 2, 5, 7, 8, 10, 11, 13, 14 Regulations dated 22.10.2019 No. 982-148-25-18.
The task is to check the fulfillment of the points 1, 2, 5, 7, 8, 10, 11, 13, 14 Regulations dated 22.10.2019 No. 982-148-25-18.
The subject is the fulfillment of the regulations of state control (supervision) bodies and municipal control bodies.
# 232100135754
Unscheduled inspection
Start date: 2021-03-29, end date: 2021-04-02, duration: 5
Authority: Severo-Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation of paragraphs 1-48 of Regulation No. 469-119-25-18 dated 05/31/2019.
The task is to check paragraphs 1-48 of the regulation dated 05/31/2019 No. 469-119-25-18.
The subject is the fulfillment of the instructions of the state control (supervision) bodies, municipal control bodies
# 002005298248
Unscheduled inspection
Start date: 2020-11-02, end date: 2020-11-27, duration: 19
Authority: SeveroKavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to verify the completed construction of a capital construction facility on the basis of a notice dated 16092020 and 012100 on the completion of the construction of a capital construction facility, the objectives of this audit are the Federal State Construction Supervision. The purpose of this audit is to comply with mandatory requirements or requirements established by municipal legal acts for the compliance of work performed and construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with technical requirements regulations of the project documentation for obtaining a construction permit to comply with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code
# 002004270917
Unscheduled inspection
Start date: 2020-02-27, end date: 2020-03-26, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is celosamente Federal state construction supervision within the competence of Rostekhnadzor in the construction, reconstruction of all the objects referred to in paragraph 51 of article 6 of the town planning code of the Russian Federation on the basis of the audit programme what not less than three business days prior to its implementation to notify the legal entity in any way allows you to control receiving notification adrenalised of this review is to prevent detection and suppression approved developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer hereinafter called the contractor violations of the legislation on town-planning activities including technical regulations and project documentlibraries present validation of yavlyaetsyasredstvom perform work and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of this Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices used energy resourcevalue permissions stroitelstvoimoti the requirements set forth in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 001902665886
Unscheduled inspection
Start date: 2019-04-22, end date: 2019-05-15, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: control of previously issued regulations on the elimination of violations of fire safety requirements from 26062018 31211
# 00170802720377
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-10-27, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the implementation of previously issued regulations from 23062017 5041282059PR in connection with the expiration of deadlines
# 00170701775284
Unscheduled inspection
Start date: 2017-08-07, end date: 2017-08-31, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of checking the implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of the verification program is to prevent identify and suppress violations of legislation on urban development activities committed by the developer, technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or technical customer, hereinafter referred to as the contractor. including technical regulations and project documentationthe subject of verification is a the conformity of the work performed and the building materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, b the availability of a construction permit and the fulfillment of the requirements of Parts 2 and 3 Article 52 of the Urban Planning Code of the Russian Federation
# 00170701775255
Unscheduled inspection
Start date: 2017-08-07, end date: 2017-08-31, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of checking the implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of the verification program is to prevent identify and suppress violations of legislation on urban development activities committed by the developer, technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or technical customer, hereinafter referred to as the contractor. including technical regulations and project documentationthe subject of verification is a the conformity of the work performed and the building materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, b the availability of a construction permit and the fulfillment of the requirements of Parts 2 and 3 Article 52 of the Urban Planning Code of the Russian Federation
# 00170701441723
Unscheduled inspection
Start date: 2017-03-13, end date: 2017-03-17, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution of a previously issued prescription
# 00160601528506
Unscheduled inspection
Start date: 2016-03-01, end date: —, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: compliance with the requirements of the construction legislation