# 002105331433
Unscheduled inspection
Start date: 2021-02-04, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002005250523
Unscheduled inspection
Start date: 2020-12-02, end date: 2020-12-04, duration: 3
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of monitoring the execution of the previously issued instruction of the Caucasian Department of Rostechnadzor dated 06112020 RP4102193o on the elimination of violations of JSC "CIUS UES" during the construction of the capital construction facility "Kochubeevskaya WPP Stage 5 of 330 kV Badgers with the construction of two 330 kV Nevinnomyssk Badgers I and II chain" located at Russia Stavropol Territory Kochubeevsky district Tasks of monitoring the accepted JSC "CIUS UES" measures to comply with the instruction of the Caucasian Department of Rostechnadzor dated 06112020 RP4102193o during the construction of the capital construction facility "Kochubeevskaya WPP Stage 5 of 330 kV Badgers with the construction of two 330 kV Nevinnomyssk Badgers I and II chain" located at Russia Stavropol Territory Kochubeevsky district Subject to compliance with the instructions of state control supervision bodies
# 002005285228
Unscheduled inspection
Start date: 2020-11-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002005205038
Unscheduled inspection
Start date: 2020-11-09, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002005265980
Unscheduled inspection
Start date: 2020-11-13, end date: 2020-12-03, duration: 15
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban development, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the 500 kV Nevinnomyssk substation with the expansion of 330 kV RU into two linear cells" on the basis of paragraphs 111 of the inspection program from 27102020the tasks of this inspection are as follows: and the suppression of violations of the legislation on urban planning activities committed by CIUS UES JSC, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the 500 kV Nevinnomyssk substation with the expansion of 330 kV RU into two linear cells"The subject of this audit is compliance with mandatory requirements
# 002005172992
Unscheduled inspection
Start date: 2020-10-07, end date: 2020-10-19, duration: 9
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to verify compliance with mandatory requirements in the field of urban development activities on the basis of the verification program. The objectives of this audit are to prevent identify and suppress violations in the implementation of measures to monitor compliance with the requirements of legislation on urban development
# 002005297643
Unscheduled inspection
Start date: 2020-08-06, end date: 2020-09-02, duration: 20
Authority: SeveroKavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: purpose control of the previously issued prescription from 22062020 2271212518 on the basis of the Petition of JSC "CIUS UES" from 28072020 C040997 letter of JSC "CIUS UES" from 04082020 C508253 Notification 1 on the elimination of violations during the construction of a capital construction facility sent by a cover letter from 29072020 C508250 Task verification of the elimination by a legal entity of the violations identified in paragraphs 137 of the prescription from 22062020 2271212518 subject to the fulfillment of the regulations bodies of state control supervision of municipal control bodies
# 002004474131
Unscheduled inspection
Start date: 2020-08-10, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002004455177
Unscheduled inspection
Start date: 2020-07-16, end date: —, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002004451497
Unscheduled inspection
Start date: 2020-06-19, end date: 2020-06-30, duration: 7
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban development, including technical regulations and design documentation during the reconstruction of the capital construction facility "Construction of 330 kV overhead line ArtemDerbent Adjustment" Stage IV on the basis of the notice of completion of the reconstruction of the capital construction facility from 29052020 M521999 vx 4109331 from 03062020the tasks of this inspection are and the prevention, detection and suppression of violations of the legislation on urban planning activities committed by CIUS UES JSC, including technical regulations and design documentation during the reconstruction of the capital construction facility "Construction of 330 kV overhead line ArtemDerbent Adjustment" IV This is the subject of this audit to note the necessary compliance with mandatory requirements
# 002004398815
Unscheduled inspection
Start date: 2020-04-01, end date: 2020-04-13, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to prevent violations of legislation on urban development activities, including design documentationthe objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to eliminate violations of mandatory requirements in case of their identification and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts
# 002004387125
Unscheduled inspection
Start date: 2020-04-20, end date: 2020-05-21, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to control the fulfillment by a legal entity, an individual entrepreneur, of the previously issued by the state construction supervision authority of the points of the instruction on the elimination of identified violations of mandatory requirements 570904318R dated December 10, 2018. The tasks of this audit are to verify the elimination by a legal entity of identified violations specified in the paragraphs of the instruction 570904318R dated December 10, 2018. The purpose of this audit is to comply with the instructions of the state control bodies supervision bodies municipal control
# 002004291245
Unscheduled inspection
Start date: 2020-02-27, end date: 2020-03-19, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of reconstruction of the capital construction facility the task of this audit is to prevent identify and suppress violations committed by the developer by the technical customer as well as by the person carrying out the reconstruction on the basis of an agreement with the developer or technical customer violations of legislation on urban planning activities, including technical regulations and design documentation requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements the requirements for equipping a capital construction facility with metering devices for energy resources used do not apply either. Compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004272520
Unscheduled inspection
Start date: 2020-01-22, end date: —, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001904066398
Unscheduled inspection
Start date: 2019-11-27, end date: 2019-12-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to prevent violations of legislation on urban development activities, including project documentation. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to eliminate violations of mandatory requirements in the event of their identification and prosecution of persons who have committed violations of the requirements of Federal laws and other regulatory legal acts7 The subject of this audit is the compliance of the work performed and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation project documentation taking into account the changes made to the design documentation in accordance with parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of the article 52 of the Urban Planning Code of the Russian Federation
# 001904030606
Unscheduled inspection
Start date: 2019-11-19, end date: 2019-11-20, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is conducted in order to monitor the implementation of the regulations dated July 17, 2019 469G3320J01 dated August 14, 2019 518G3320J01 The objectives of this audit are to monitor the measures taken by a legal entity to comply with the regulations and comply with mandatory requirements of legislation on urban development during the construction reconstruction of a capital construction facility, taking measures to eliminate violations of mandatory requirements if they are identified and to involve the responsibility of persons who have committed violations of the requirements of Federal laws and other regulatory legal acts7 The subject of verification is the fulfillment of the instructions of the state control supervision body
# 001903898983
Unscheduled inspection
Start date: 2019-11-19, end date: 2019-11-20, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is conducted in order to monitor the implementation of the regulations dated July 17, 2019 469G3320J01 dated August 14, 2019 518G3320J01 The objectives of this audit are to monitor the measures taken by a legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban development during the construction reconstruction of a capital construction facility, taking measures to eliminate violations of mandatory requirements if they are identified and to involve liability of persons who have committed violations of the requirements of Federal laws and other regulatory legal acts
# 001903899218
Unscheduled inspection
Start date: 2019-10-22, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001903148825
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-09-30, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to control the execution of JSC "CIUS UES" of the previously issued order dated 19072019 3088RVA18C on the elimination of violations during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation 500 kV ORU"The objectives of this audit are to monitor the measures taken by JSC "CIUS UES" to comply with the regulation dated 19072019 3088RVA18. The purpose of this audit is to comply with the instructions of state control bodies
# 001902961260
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-08-14, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of the regulation dated April 24, 2019 271G3320J02THE tasks of this audit are to monitor the measures taken by a legal entity to comply with the regulation and comply with the mandatory requirements of legislation on urban development during the construction reconstruction of a capital construction facility, to take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws laws and other regulatory legal acts7 The subject of verification is the fulfillment of the instruction of the state control body supervision
# 001903009116
Unscheduled inspection
Start date: 2019-08-27, end date: 2019-09-09, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with legislation on urban planning activities, including technical regulations and project documentation on the basis of paragraph 1 of the inspection program dated 17062019 agreed with JSC "CIUS UES"
# 001902900497
Unscheduled inspection
Start date: 2019-07-25, end date: 2019-07-31, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the completed construction of the capital construction facility Verification of compliance of the work and construction materials used in the process of construction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements of equipping the capital construction facility with metering devices for used energy resources availability of a permit for construction of compliance with the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation dated 29122004 190FZ
# 001902820296
Unscheduled inspection
Start date: 2019-07-04, end date: 2019-07-17, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to implement the audit program approved by the Deputy head of Rostechnadzor MTU AA Kulakov on February 11, 2019. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to elimination of violations of mandatory requirements in case of their detection and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts7 The subject of this audit is the compliance of the work performed and the construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation including energy efficiency requirements with the exception of capital construction facilities which the requirements of energy efficiency do not apply to and the requirements for equipping a capital construction facility with metering devices for used energy resources, the need for a construction permit to comply with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902669281
Unscheduled inspection
Start date: 2019-05-13, end date: 2019-05-21, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban planning activities verification of compliance of completed works and applied building materials during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used verification of compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law the Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 001902594728
Unscheduled inspection
Start date: 2019-04-23, end date: 2019-04-24, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is conducted in order to monitor the implementation of the regulations dated December 28, 2018 949G3320J01 dated January 21, 2019 18G3320J01 The objectives of this audit are to monitor the measures taken by a legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban development during the construction reconstruction of a capital construction facility taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts 7 The subject of verification is the fulfillment of the instructions of the state control supervision body
# 001902594750
Unscheduled inspection
Start date: 2019-04-23, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001902556807
Unscheduled inspection
Start date: 2019-03-11, end date: 2019-04-05, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the fulfillment of the instruction previously issued to the person being checked from 04122018 09721 on the elimination of previously identified violations, the deadline for which expires 040319 The task of the audit is to establish the fact of elimination of previously identified violations specified in the instruction from 04122018 09721 The subject of this audit is the fulfillment of the instruction of the state construction supervision authority from 04122018 09721
# 001902426377
Unscheduled inspection
Start date: 2019-01-16, end date: 2019-01-21, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 13092018 665G3320J01 Execution of the order of 13092018 666G3320J01 Execution of the order of 29102018 793G3320J01
# 001902426367
Unscheduled inspection
Start date: 2019-01-16, end date: 2019-01-21, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 13092018 685G3320J02 Execution of the order of 13092018 686G3320J02 Execution of the order of 31102018 803G3320J02
# 001802193309
Unscheduled inspection
Start date: 2018-11-21, end date: 2018-11-27, duration: —
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: it is carried out in order to monitor the implementation of pp 1 15 of the previously issued prescription from 27042018 10105C2018B1 during the construction of the capital construction facility "Construction of the 500 kV Beloberezhskaya substation with 500 kV Novobryanskaya Yeletskaya overhead line 220 kV Beloberezhskaya Cement overhead line 220 kV Beloberezhskaya Machine Plant and 220 kV Beloberezhskaya Bryanskaya overhead line" located at Bryansk region Karachevsky district Mylinskoye rural settlement The Berezovsky deadline for which expired on 27072018 and 27102018 the objectives of this audit are to verify the elimination by a legal entity of the violations identified in paragraphs 1 15 of the previously issued prescription from 27042018 10105C2018B1 The subject of this audit is to verify the fulfillment by a legal entity of paragraphs 115 of the previously issued prescription from 27042018 10105C2018B1
# 001802130122
Unscheduled inspection
Start date: 2018-11-28, end date: 2018-12-25, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development activities, including design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor. The subject of this audit is to control the compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements project documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for used energy resources availability of a construction permit compliance with the requirements established by parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation during the construction of a capital construction facility "PS 500 kV Sunrise with approaches 500 kV and 220 kV overhead lines" located at the address Omsk region Kormilovsky district Georgievskoye rural settlement
# 001801762185
Unscheduled inspection
Start date: 2018-10-25, end date: 2018-10-29, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 12072018 491G3327J01 Execution of the order of 24072018 555G3327J01
# 001801763102
Unscheduled inspection
Start date: 2018-10-30, end date: 2018-10-31, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 12072018 492G3327J02 Execution of the order of 24072018 556G3327J02
# 001801762392
Unscheduled inspection
Start date: 2018-10-30, end date: 2018-10-31, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 12072018 492G3327J02 Execution of the order of 24072018 556G3327J02
# 001800769860
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-09-13, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800769845
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-09-13, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800765826
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-09-13, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800673467
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-09-13, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the execution of the order dated May 24, 2018 363G3327J01
# 001800499065
Unscheduled inspection
Start date: 2018-07-16, end date: 2018-08-03, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the fulfillment of the instruction previously issued to the person being checked from 05032018 0983 on the elimination of violations identified earlier, the deadline for which has expired The task of the audit is to establish the fact of elimination of previously identified violations specified in the instruction from 05032018 0983 The subject of this audit is the fulfillment of the instruction of the state construction supervision authority from 05032018 0983
# 001800492524
Unscheduled inspection
Start date: 2018-07-16, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001800578692
Unscheduled inspection
Start date: 2018-07-30, end date: 2018-08-24, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of state construction supervision during the construction of the specified capital construction facility in connection with the onset of completion dates of works that are subject to verification in accordance with the approved program of inspections during the construction of the capital construction facility
# 001800496308
Unscheduled inspection
Start date: 2018-07-10, end date: 2018-07-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order from 09042018 g 225G3327J01 Execution of the order from 19042018 g 257G3327J01
# 001800492598
Unscheduled inspection
Start date: 2018-07-10, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001800524569
Unscheduled inspection
Start date: 2018-07-05, end date: 2018-07-13, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development activities, including technical regulations and project documentation, committed by the developer, the customer, as well as by persons carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor
# 001800528977
Unscheduled inspection
Start date: 2018-07-02, end date: 2018-07-03, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to control the execution of JSC "CIUS UES" previously issued instruction from 06042018 821RVPA18 on the elimination of violations during the reconstruction of the capital construction facility "Reconstruction and technical re-equipment of 330 kV Vladikavkaz2" the objectives of this inspection are to monitor the measures taken by JSC "CIUS UES" to comply with the instruction from 06042018 821RVPA18 and compliance with mandatory requirements regulatory acts in the field of construction during the construction of the reconstruction of the capital construction facility "Reconstruction and technical re-equipment of the 330 kV Vladikavkaz2 substation" b taking measures to identify violations of mandatory requirements and to bring to justice persons who committed violations of the requirements of federal laws and other regulatory legal acts
# 001800465843
Unscheduled inspection
Start date: 2018-07-02, end date: 2018-07-27, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the fulfillment of the instruction previously issued to the person being checked from 28122017 09864C on the elimination of previously identified violations, the deadline for which has expired The task of the audit is to establish the fact of elimination of previously identified violations specified in the instruction from 28122017 09864C The subject of this audit is the fulfillment of the instruction of the state construction supervision authority from 28122017 09864C
# 001800292406
Unscheduled inspection
Start date: 2018-03-20, end date: 2018-04-09, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban planning activities, including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation 500 kV ORU construction" on the basis of paragraphs 930 of the inspection program from 25082017 the objectives of this audit are: a prevention, detection and suppression of violations of the legislation on urban planning activities committed by CIUS UES JSC, including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation construction of 500 kV ORU" b taking measures to to identify violations of mandatory requirements and to bring to justice persons who have committed violations of the requirements of federal laws and other regulatory legal acts
# 001800167324
Unscheduled inspection
Start date: 2018-03-20, end date: —, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001800225008
Unscheduled inspection
Start date: 2018-03-22, end date: 2018-03-29, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation dated 25.012018 g 30G3327J03
# 001800103111
Unscheduled inspection
Start date: 2018-03-01, end date: 2018-03-30, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to control the fulfillment by a legal entity, an individual entrepreneur, previously issued by the state construction supervision authority of the points of the instruction on the elimination of identified violations of mandatory requirements 570910917R dated October 23, 2017. The objectives of this audit are to verify the elimination by a legal entity of the identified violation specified in the paragraphs of the instruction 570910917R dated October 23, 2017. The subject of this audit is the fulfillment of the instructions of state control bodies supervision of municipal control bodies for the Reconstruction of the 500 kV Tyumen substation
# 001800064016
Unscheduled inspection
Start date: 2018-02-12, end date: 2018-02-19, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban planning activities verification of compliance of completed works and applied building materials during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used verification of compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law the Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 001800104557
Unscheduled inspection
Start date: 2018-02-05, end date: 2018-02-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800051253
Unscheduled inspection
Start date: 2018-02-05, end date: 2018-02-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800172162
Unscheduled inspection
Start date: 2018-02-07, end date: 2018-02-19, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800051960
Unscheduled inspection
Start date: 2018-02-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001800170523
Unscheduled inspection
Start date: 2018-01-22, end date: 2018-01-25, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation of 14122017 g 748G3327Z09
# 001800170635
Unscheduled inspection
Start date: 2018-01-22, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00170802996796
Unscheduled inspection
Start date: 2017-12-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00170802907053
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-11-29, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170802866228
Unscheduled inspection
Start date: 2017-11-16, end date: 2017-11-27, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban development, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction and technical re-equipment of the 330 kV Vladikavkaz2 substation" on the basis of paragraph 1 of the inspection program from 30062017the tasks of this audit are prevention detection and suppression of admitted JSC "CIUS UES"violations of legislation on urban planning activities, including technical regulations and design documentation during the reconstruction of a capital construction facility "Reconstruction and technical re-equipment of the 330 kV Vladikavkaz2 substation"b taking measures to identify violations of mandatory requirements and to bring to justice persons who violated the requirements of Federal laws and other regulatory legal acts
# 00170802663544
Unscheduled inspection
Start date: 2017-10-11, end date: 2017-10-18, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the prescription from 10082017 g 420G3327J03
# 00170802421838
Unscheduled inspection
Start date: 2017-09-14, end date: 2017-09-26, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban development, including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation 500 kV ORU construction" on the basis of paragraphs 18 of the inspection program from 25082017the tasks of this audit are a prevention, detection and suppression of violations of the legislation on urban planning activities committed by JSC "CIUS UES", including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation 500 kV ORU construction"b taking measures to identify violations mandatory requirements and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts
# 00170801958218
Unscheduled inspection
Start date: 2017-09-12, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00170701845896
Unscheduled inspection
Start date: 2017-08-01, end date: 2017-08-10, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the prescription from 28062017 g 344G3327J03
# 00170701775139
Unscheduled inspection
Start date: 2017-07-17, end date: 2017-07-21, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution by a legal entity of a previously issued order dated 31032017 54727prvnP01642017
# 00170701773324
Unscheduled inspection
Start date: 2017-07-10, end date: 2017-07-17, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation from 31032017 g 142G3327J03
# 00170701722359
Unscheduled inspection
Start date: 2017-06-26, end date: 2017-06-28, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of regulation 85G3327J03 dated February 27, 2017
# 00170701563541
Unscheduled inspection
Start date: 2017-05-10, end date: 2017-05-15, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701563501
Unscheduled inspection
Start date: 2017-05-10, end date: 2017-05-15, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701615085
Unscheduled inspection
Start date: 2017-04-26, end date: 2017-04-27, duration: —
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to control the fulfillment of violations set out in paragraphs 1 11 12 13 14 15 16 17 18 19 110 111 regulations of 23122016 777 C2016 the objectives of this audit are to verify the elimination by a legal entity of the violations identified in paragraphs 111213141516171819110 111 regulations of 23122016 777 C2016 the subject of this audit is to verify the fulfillment by a legal entity of paragraphs 111 1213141516171819110 111 regulations from 23122016 777C2016 of the Prioksky Department of Rostechnadzor
# 00170701502689
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-28, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701484099
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-28, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701413018
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-03-31, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701412320
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-03-31, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701434035
Unscheduled inspection
Start date: 2017-03-02, end date: 2017-03-10, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation dated 27.012016 29G3327J043
# 00170701412284
Unscheduled inspection
Start date: 2017-03-02, end date: 2017-03-13, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation dated 01122016 g 602G3327J07
# 00170701512229
Unscheduled inspection
Start date: 2017-02-22, end date: 2017-02-22, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the fulfillment of the points of the previously issued prescription
# 00170701511007
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-02-21, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the fulfillment of the prescription
# 00170701512253
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-02-21, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the fulfillment of the points of the previously issued prescription
# 00170701399918
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-02-27, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701331787
Unscheduled inspection
Start date: 2017-01-23, end date: 2017-01-27, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation dated 01122016 601G3327J043
# 00160701229449
Unscheduled inspection
Start date: 2016-12-19, end date: 2016-12-21, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00160701160067
Unscheduled inspection
Start date: 2016-12-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160700637929
Unscheduled inspection
Start date: 2016-09-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160700637401
Unscheduled inspection
Start date: 2016-09-01, end date: 2016-09-06, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 18052016 g 222G3327J01
# 00160700633322
Unscheduled inspection
Start date: 2016-09-01, end date: 2016-09-06, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 18052016 g 225G3327J07
# 00160700629150
Unscheduled inspection
Start date: 2016-09-01, end date: 2016-09-06, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation of 18052016 g 223G3327J02
# 00160700553973
Unscheduled inspection
Start date: 2016-09-22, end date: 2016-09-23, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials with the requirements of technical regulations, other regulatory legal acts and project documentation
# 00160700554580
Unscheduled inspection
Start date: 2016-09-20, end date: 2016-09-21, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials with the requirements of technical regulations, other regulatory legal acts and project documentation
# 00160700055310
Unscheduled inspection
Start date: 2016-08-22, end date: 2016-09-02, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development activities committed by the developer by the customer
# 00160601628418
Unscheduled inspection
Start date: 2016-05-04, end date: 2016-05-16, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken to ensure compliance by a legal entity with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, preventing the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory acts legal acts
# 00160601617064
Unscheduled inspection
Start date: 2016-05-10, end date: 2016-05-18, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken to ensure compliance by a legal entity with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, preventing the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory acts legal acts
# 00160601611125
Unscheduled inspection
Start date: 2016-05-10, end date: 2016-05-18, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken to ensure compliance by a legal entity with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, preventing the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory acts legal acts
# 00160601611105
Unscheduled inspection
Start date: 2016-05-10, end date: 2016-05-18, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken to ensure compliance by a legal entity with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, preventing the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory acts legal acts
# 00160601530626
Unscheduled inspection
Start date: 2016-03-21, end date: —, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00160601544193
Unscheduled inspection
Start date: 2016-02-04, end date: 2016-02-09, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken by a legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory legal acts
# 00160601544251
Unscheduled inspection
Start date: 2016-02-04, end date: 2016-02-09, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken by a legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory legal acts
# 142101367417
Unscheduled inspection
Start date: 2021-11-23, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection:
# 142101369944
Unscheduled inspection
Start date: 2021-11-24, end date: 2021-12-07, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: inspections in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Republic of Sakha (Yakutia), compliance with the construction of the capital construction facility by the developer, technical customer, person carrying out construction, mandatory requirements in the field of construction and applied building materials (products), the established procedure for construction, reconstruction of the capital construction facility, warning, identification and suppression of violations of legislation on urban development, including project documentation, compliance with mandatory requirements and (or) requirements established by municipal legal acts, committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer (hereinafter referred to as the contractor), compliance with the information contained in the notification on the commencement of certain types of entrepreneurial activity, mandatory requirements; compliance with the information contained in the application and documents of a legal entity or individual entrepreneur for the provision of legal status, a special permit (license) for the right to carry out certain types of activities or permission (approval) for other legally significant actions, if an appropriate unscheduled audit of the legal entity, an individual entrepreneur is provided for by the rules for granting legal status, special permission (license), issuance of permission (approval) to mandatory requirements, as well as data on these legal entities and individual entrepreneurs contained in the unified state register of legal entities, the unified state register of individual entrepreneurs and other federal information resources; compliance with the instructions of state control (supervision) bodies, municipal control bodies; holding events: to prevent harm to the life and health of citizens, harm to animals, plants, the environment, cultural heritage sites (historical and cultural monuments) of the peoples of the Russian Federation, museum objects and museum collections included in the Museum Fund of the Russian Federation, especially valuable, including unique, documents of the Archival Fund of the Russian Federation, documents, of special historical, scientific, and cultural significance, which are part of the national library fund; to prevent the occurrence of emergency situations of a natural and man-made nature; to ensure the security of the state; to eliminate the consequences of causing such harm.
# 422101077449
Unscheduled inspection
Start date: 2021-10-08, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: purpose: to verify the compliance of the work performed and the construction materials and products used during the reconstruction of the facility, as well as the results of such work, with the requirements of the design documentation (including taking into account the changes made to the working documentation and which, in accordance with Part 1.3 of Article 52 of the Civil Code of the Russian Federation, are part of such design documentation), in accordance with paragraph 2 inspection Program No. 5, approved by Order No. 134/02-OS dated 04/15/2021.
Task: verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility.
Subject: compliance with the requirements of the legislation of the Russian Federation on urban development.
# 212101284956
Unscheduled inspection
Start date: 2021-10-26, end date: —, duration: —
Authority: Ministerstvo stroitelstva, arhitektury i zhilischno-kommunalnogo hozyaistva CHuvashskoi Respubliki
Purpose of inspection: the construction stage
# 212101284900
Unscheduled inspection
Start date: 2021-10-26, end date: —, duration: —
Authority: Ministerstvo stroitelstva, arhitektury i zhilischno-kommunalnogo hozyaistva CHuvashskoi Respubliki
Purpose of inspection: stage
# 142100771544
Unscheduled inspection
Start date: 2021-09-20, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection:
# 562100539148
Unscheduled inspection
Start date: 2021-08-27, end date: —, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: implementation of regional state construction supervision on the basis of the inspection program dated 04/09/2021.
- the objectives of this inspection are: identification and suppression of violations of the requirements of project documentation, legislation on urban development (Part 2 of Article 51, Part 2, 3.1, 4, 6 of Article 52, Part 2, 4 of Article 53 of the Urban Planning Code of the Russian Federation).
- The subject of this audit is: compliance of the work performed and the construction materials and products used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (including taking into account the changes made to the working documentation and which are in accordance with Part 1.3 Article 52 of this Code as part of such project documentation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code); requirements for a construction permit; requirements established by parts 2 and 3.1 of Article 52 of this Code; requirements for the procedure for carrying out construction control, established by this Code and other regulatory legal acts; (paragraphs 1, 3, 4 of the inspection program approved on 04/09/2021)
# 142100410771
Unscheduled inspection
Start date: 2021-08-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142100410077
Unscheduled inspection
Start date: 2021-08-03, end date: 2021-08-23, duration: 15
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: check in accordance with the inspection plan approved by the Director of the office of the state construction and housing supervision of the Republic of Sakha (Yakutia), compliance in the construction of the object of capital construction, developer, technical, customer, person engaged in the construction, mandatory requirements in the field of construction and construction materials used (products), the established order of construction, reconstruction of capital construction object, prevention, detection and suppression approved developer, technical coordinator and the person performing the construction on the basis of an agreement with the developer or the customer (hereinafter the contractor), violations of the legislation on town-planning activities, including project documentation, compliance with mandatory requirements and (or) the requirements established by municipal legal acts; the conformity of the information contained in the notice of initiation of certain types of entrepreneurial activities, the mandatory requirements; compliance of the information contained in the statement and the documents of the legal entity or the individual entrepreneur on the legal status, special permission (license) to carry out certain types of activities or authorization (approval) to exercise other legal actions, if the conducting unscheduled inspections of the legal entity, individual entrepreneur provided the rules for the provision of legal status, a special permit (license), authorization (approval) the mandatory requirements, as well as data about the specified legal entities and individual entrepreneurs, contained in the unified state register of legal entities, the unified state register of individual entrepreneurs and other Federal information resources; implementation of the requirements of the state control (supervision) bodies and municipal control; events: to prevent harm to the life and health of citizens, harm to animals, plants, the environment, cultural heritage sites (historical and cultural monuments) of the peoples of the Russian Federation, museum objects and museum collections included in the Museum Fund of the Russian Federation, especially valuable, including unique, documents of the Archival Fund of the Russian Federation, documents, of special historical, scientific, cultural significance, which are part of the national library fund; to prevent the occurrence of emergency situations of a natural and man-made nature; to ensure the security of the state; to eliminate the consequences of causing such harm.
# 142100410601
Unscheduled inspection
Start date: 2021-08-04, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection:
# 422100270608
Unscheduled inspection
Start date: 2021-06-15, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives: to verify the conformity of the work performed and the construction materials used in
the production process. Tasks: compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 772100226328
Unscheduled inspection
Start date: 2021-06-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100226311
Unscheduled inspection
Start date: 2021-06-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 362100259589
Unscheduled inspection
Start date: 2021-06-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100179374
Unscheduled inspection
Start date: 2021-05-17, end date: 2021-02-18, duration: 8
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to implement the audit program approved by the acting Deputy Head
Rostechnadzor MTU A.V. Karabash on June 19, 2020
The objectives of this audit are:
to monitor the measures taken to ensure that a legal entity complies with the mandatory requirements of legislation
on urban planning during construction, reconstruction of a capital construction facility;
prevention, detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation;
taking measures to eliminate violations of mandatory requirements
(if they are identified) and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts.
7. The subject of this audit is:
compliance of the work performed and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved
in accordance with parts 15, 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the project documentation in accordance with parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation),
including the requirements of energy efficiency (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements for equipping a capital construction facility with metering devices for energy resources used;
availability of a building permit;
compliance with the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation
# 772100170208
Unscheduled inspection
Start date: 2021-05-31, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100108531
Unscheduled inspection
Start date: 2021-04-05, end date: —, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the performed works with the mandatory requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility; the task of this check is to prevent, identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on on the basis of an agreement with a developer or technical customer, violations of legislation on urban development, including design documentation, requirements for energy conservation and energy efficiency improvement;
The subject of this review is:compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the design documentation in accordance with Parts 3.8 and 3.9 of Article 49 of the Urban Planning Code Of the Russian Federation) and (or) an information model, including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices for used energy resources;
availability of a building permit;
compliance with the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 772100108566
Unscheduled inspection
Start date: 2021-04-05, end date: —, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the performed works with the mandatory requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility; the task of this check is to prevent, identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on on the basis of an agreement with a developer or a technical customer, violations of legislation on urban planning, including design documentation, requirements for energy conservation and energy efficiency improvement;
The subject of this review is:compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the design documentation in accordance with Parts 3.8 and 3.9 of Article 49 of the Urban Planning Code Of the Russian Federation) and (or) an information model, including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices for used energy resources;
availability of a building permit;
compliance with the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 562100172947
Unscheduled inspection
Start date: 2021-04-26, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: This inspection is carried out in order to: implement regional state construction supervision on the basis of the inspection program dated 04/09/2021.
The objectives of this inspection are: to identify and suppress violations of the requirements of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used, legislation on urban planning (Part 2 of Article 51, Parts 2, 3, 3.1, 6 of Article 52 of the Urban Planning Code of the Russian Federation).
The subject of this audit is: compliance with the mandatory requirements of urban planning legislation; compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the project documentation in in accordance with Parts 3.8 and 3.9 of Article 49 of the Urban Planning Code of the Russian Federation), including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for energy resources used (paragraphs 1-3 of the inspection program dated 04/09/2021).
# 772100073144
Unscheduled inspection
Start date: 2021-03-05, end date: 2021-03-12, duration: 4
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: -The inspection is carried out in order to: verify compliance of JSC "CIUS UES" with the mandatory requirements of legislation on urban development, including technical regulations and design documentation during the reconstruction of a capital construction facility: "Reconstruction of the 500 kV Nevinnomyssk substation with the expansion of 330 kV RU into two linear cells", on the basis of on the basis of notice No. 1 on completion construction, reconstruction of the capital construction facility from 02/19/2021, ex. No. M5/2/432 dated 02/20/2021 (ex. No. 410/3912 dated 02/24/2021).
- The objectives of this audit are:
a) verification of compliance by CIUS UES JSC with the requirements of project documentation, current legislation in the field of construction, fire safety, sanitary and epidemiological welfare, compliance with norms and rules in the field of environmental protection, energy conservation and energy efficiency at the completed capital construction facility: "Reconstruction of the 500 kV Nevinnomyssk substation with expansion of the 330 kV RC into two linear cells."
-The subject of this audit is -compliance with mandatory requirements - established - by legal acts.
# 422100021072
Unscheduled inspection
Start date: 2021-02-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002105331433
Unscheduled inspection
Start date: 2021-02-04, end date: 2021-02-18, duration: 11
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to implement the audit program approved by the acting Deputy Head
Rostechnadzor MTU A.V. Karabash on June 19, 2020
The objectives of this audit are:
to monitor the measures taken to ensure that a legal entity complies with the mandatory requirements of legislation
on urban planning during construction, reconstruction of a capital construction facility;
prevention, detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation;
taking measures to eliminate violations of mandatory requirements
(if they are identified) and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts.
7. The subject of this audit is:
compliance of the work performed and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved
in accordance with parts 15, 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the project documentation in accordance with parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation),
including the requirements of energy efficiency (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements for equipping a capital construction facility with metering devices for energy resources used;
availability of a building permit;
compliance with the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation
# 772100038222
Unscheduled inspection
Start date: 2021-01-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002005268459
Unscheduled inspection
Start date: 2020-12-14, end date: 2020-12-25, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipment of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made in the design documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of the article 52 of the Urban Planning Code of the Russian Federation
# 002005268445
Unscheduled inspection
Start date: 2020-12-14, end date: 2020-12-25, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipment of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made in the design documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of the article 52 of the Urban Planning Code of the Russian Federation
# 612005283416
Unscheduled inspection
Start date: 2020-12-22, end date: 2020-12-25, duration: 4
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: the inspection is carried out in order to fulfill the p3 program of inspections Verification of the completed capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation committed by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer hereinafter the contractor, the subject of this inspection is to verify compliance with mandatory requirements and or requirements established by municipal legal acts
# 612005249717
Unscheduled inspection
Start date: 2020-12-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002005250523
Unscheduled inspection
Start date: 2020-12-02, end date: 2020-12-04, duration: 3
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of monitoring the execution of the previously issued instruction of the Caucasian Department of Rostechnadzor dated 06112020 RP4102193o on the elimination of violations of JSC "CIUS UES" during the construction of the capital construction facility "Kochubeevskaya WPP Stage 5 of 330 kV Badgers with the construction of two 330 kV Nevinnomyssk Badgers I and II chain" located at Russia Stavropol Territory Kochubeevsky district Tasks of monitoring the accepted JSC "CIUS UES" measures to comply with the instruction of the Caucasian Department of Rostechnadzor dated 06112020 RP4102193o during the construction of the capital construction facility "Kochubeevskaya WPP Stage 5 of 330 kV Badgers with the construction of two 330 kV Nevinnomyssk Badgers I and II chain" located at Russia Stavropol Territory Kochubeevsky district Subject to compliance with the instructions of state control supervision bodies
# 002005285228
Unscheduled inspection
Start date: 2020-11-16, end date: 2020-12-02, duration: 13
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban development, including technical regulations and design documentation during the reconstruction of the capital construction facility "PS 330 kV Vladikavkaz2" under the title "Reconstruction and technical re-equipment of PS 330 kV Vladikavkaz2" on the basis of p1 p5 p7 p11 p26 inspection program from 19102020 Tasks of this inspection The following are the prevention, detection and suppression of violations of the legislation on urban planning activities committed by CIUS UES JSC, including technical regulations and design documentation during the reconstruction of the capital construction facility "330 kV Vladikavkaz2 PS" under the title "Reconstruction and technical re-equipment of 330 kV Vladikavkaz2 PS"The subject of this audit is compliance with mandatory requirements
# 002005205038
Unscheduled inspection
Start date: 2020-11-09, end date: 2020-11-24, duration: 12
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to implement the audit program approved by the acting Deputy head of the MTU Rostechnadzor AV Karabash on June 19, 2020. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to eliminate violations of mandatory requirements in case of their detection and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts7 The subject of this audit is the compliance of the work performed and the construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code the Code of the Russian Federation of project documentation, taking into account the changes made to the project documentation in accordance with parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to meet the requirements established by parts 2 3 and 31 Articles 52 of the Urban Planning Code of the Russian Federation
# 002005265980
Unscheduled inspection
Start date: 2020-11-13, end date: 2020-12-03, duration: 15
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban development, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the 500 kV Nevinnomyssk substation with the expansion of 330 kV RU into two linear cells" on the basis of paragraphs 111 of the inspection program from 27102020the tasks of this inspection are as follows: and the suppression of violations of the legislation on urban planning activities committed by CIUS UES JSC, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the 500 kV Nevinnomyssk substation with the expansion of 330 kV RU into two linear cells"The subject of this audit is compliance with mandatory requirements
# 422005176312
Unscheduled inspection
Start date: 2020-10-19, end date: 2020-10-21, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 002005196209
Unscheduled inspection
Start date: 2020-10-23, end date: 2020-11-06, duration: 10
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the purpose of verification of compliance by CIUS UES JSC with the mandatory requirements of legislation on urban planning activities, including technical regulations and design documentation during the reconstruction of the capital construction facility "Kochubeevskaya WPP Stage 5 330 kV Badgers with the construction of two 330 kV Nevinnomyssk Badgers I and II chain" located at Russia Stavropol Territory Kochubeevsky district Tasks Prevention detection and suppression violations of legislation on urban planning activities, including technical regulations and design documentation during the reconstruction of the capital construction facility "Kochubeevskaya WPP Stage 5 330 kV Badgers substation with the construction of two 330 kV power lines Nevinnomyssk Badgers I and II chain" located at Russia Stavropol Territory Kochubeevsky district subject to mandatory requirements
# 002005172992
Unscheduled inspection
Start date: 2020-10-07, end date: 2020-10-19, duration: 9
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to verify compliance with mandatory requirements in the field of urban development activities on the basis of the verification program. The objectives of this audit are to prevent identify and suppress violations in the implementation of measures to monitor compliance with the requirements of legislation on urban development
# 002005297643
Unscheduled inspection
Start date: 2020-08-06, end date: 2020-09-02, duration: 20
Authority: SeveroKavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: purpose control of the previously issued prescription from 22062020 2271212518 on the basis of the Petition of JSC "CIUS UES" from 28072020 C040997 letter of JSC "CIUS UES" from 04082020 C508253 Notification 1 on the elimination of violations during the construction of a capital construction facility sent by a cover letter from 29072020 C508250 Task verification of the elimination by a legal entity of the violations identified in paragraphs 137 of the prescription from 22062020 2271212518 subject to the fulfillment of the regulations bodies of state control supervision of municipal control bodies
# 002004496478
Unscheduled inspection
Start date: 2020-08-24, end date: 2020-09-04, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made in the design documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit, compliance with the requirements established by parts 2 3 and 31 Articles 52 of the Urban Planning Code of the Russian Federation
# 002004496462
Unscheduled inspection
Start date: 2020-08-24, end date: 2020-09-04, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipment of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made in the design documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of the article 52 of the Urban Planning Code of the Russian Federation
# 002004474131
Unscheduled inspection
Start date: 2020-08-10, end date: 2020-08-27, duration: 14
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to implement the audit program approved by the acting Deputy head of the MTU Rostechnadzor AV Karabash on June 19, 2020. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to eliminate violations of mandatory requirements in case of their detection and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts7 The subject of this audit is the compliance of the work performed and the construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code the Code of the Russian Federation of project documentation, taking into account the changes made to the project documentation in accordance with parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to meet the requirements established by parts 2 3 and 31 Articles 52 of the Urban Planning Code of the Russian Federation
# 002004455177
Unscheduled inspection
Start date: 2020-07-16, end date: 2020-08-05, duration: 15
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Purpose verification of compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban development, including technical regulations and design documentation during the reconstruction of the capital construction facility "Kochubeevskaya WPP Stage 5 330 kV Badgers with the construction of two 330 kV Nevinnomyssk Badgers I and II chain" located at Russia Stavropol Territory Kochubeevsky district Tasks prevention detection and suppression of violations of legislation on urban planning activities, including technical regulations and design documentation during the reconstruction of the capital construction facility "Kochubeevskaya WPP Stage 5 330 kV Badgers substation with the construction of two 330 kV Nevinnomyssk Badgers I and II chain" located at Russia Stavropol Territory Kochubeevsky district Subject to compliance with mandatory requirements
# 002004427532
Unscheduled inspection
Start date: 2020-06-08, end date: 2020-06-11, duration: 4
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the reconstruction of the capital construction facility the task of this check is to prevent identify and suppress the mistakes made by the developer by the technical customer as well as by the person carrying out the reconstruction on the basis of an agreement with the developer or technical customer violations of legislation on urban planning activities, including technical regulations and design documentation requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements the requirements for equipping a capital construction facility with metering devices for energy resources used do not apply either. Compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 242004421793
Unscheduled inspection
Start date: 2020-06-01, end date: 2020-06-29, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the onset of completion dates that are subject to verification in accordance with the approved program from 03022020 of inspections during the construction of a capital construction facility the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities including design documentation7 The subject of this audit is 71 Verification of the compliance of the work performed and the construction materials used in the construction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation If the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used72 Compliance with the requirements established by parts 2 3 and 31 Article 52 of the Urban Planning Code of the Russian Federation73 Checking the availability of a construction permit
# 002004451497
Unscheduled inspection
Start date: 2020-06-19, end date: 2020-06-30, duration: 7
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban development, including technical regulations and design documentation during the reconstruction of the capital construction facility "Construction of 330 kV overhead line ArtemDerbent Adjustment" Stage IV on the basis of the notice of completion of the reconstruction of the capital construction facility from 29052020 M521999 vx 4109331 from 03062020the tasks of this inspection are and the prevention, detection and suppression of violations of the legislation on urban planning activities committed by CIUS UES JSC, including technical regulations and design documentation during the reconstruction of the capital construction facility "Construction of 330 kV overhead line ArtemDerbent Adjustment" IV This is the subject of this audit to note the necessary compliance with mandatory requirements
# 002004435230
Unscheduled inspection
Start date: 2020-06-10, end date: 2020-06-24, duration: 9
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004440662
Unscheduled inspection
Start date: 2020-05-26, end date: 2020-06-15, duration: 14
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban planning, including technical regulations and design documentation during the reconstruction of the capital construction facility "Construction of 330 kV overhead line ArtemDerbent Adjustment" reconstruction of 330 kV Derbent substation stage 3 on the basis of paragraphs 124 of the inspection program from 26022020 case number 190403 The tasks of this inspection are as follows prevention detection and suppression of violations of the legislation on urban planning activities committed by JSC "CIUS UES", including technical regulations and design documentation during the reconstruction of the capital construction facility "Construction of 330 kV overhead line ArtemDerbent Correction" reconstruction of 330 kV Derbent 3 substation This is the subject of this inspection is to note the necessary compliance with mandatory requirements
# 232004420422
Unscheduled inspection
Start date: 2020-05-28, end date: 2020-06-25, duration: —
Authority: Departament po nadzoru v stroitelnoi sfere Krasnodarskogo kraya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities, including project documentation, committed by the developer, the technical customer, as well as by the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer contractor, the subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 232004413244
Unscheduled inspection
Start date: 2020-05-18, end date: 2020-06-15, duration: —
Authority: Departament po nadzoru v stroitelnoi sfere Krasnodarskogo kraya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities, including project documentation, committed by the developer, the technical customer, as well as by the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer contractor, the subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 002004398815
Unscheduled inspection
Start date: 2020-04-01, end date: 2020-04-13, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to prevent violations of legislation on urban development activities, including design documentationthe objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to eliminate violations of mandatory requirements in case of their identification and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts
# 002004387125
Unscheduled inspection
Start date: 2020-04-20, end date: 2020-05-21, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to control the fulfillment by a legal entity, an individual entrepreneur, of the previously issued by the state construction supervision authority of the points of the instruction on the elimination of identified violations of mandatory requirements 570904318R dated December 10, 2018. The tasks of this audit are to verify the elimination by a legal entity of identified violations specified in the paragraphs of the instruction 570904318R dated December 10, 2018. The purpose of this audit is to comply with the instructions of the state control bodies supervision bodies municipal control
# 242004248181
Unscheduled inspection
Start date: 2020-02-03, end date: 2020-03-02, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification 10 dated 27.012020 on the beginning of construction of the capital construction facility, the objectives of this inspection are to prevent identify and suppress violations of the legislation on urban development activities, including project documentation
# 002004291252
Unscheduled inspection
Start date: 2020-02-27, end date: 2020-03-19, duration: 14
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the reconstruction of the capital construction facility the task of this check is to prevent identify and suppress the mistakes made by the developer by the technical customer as well as by the person carrying out the reconstruction on the basis of an agreement with the developer or technical customer violations of legislation on urban planning activities, including technical regulations and design documentation requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction projects for which the requirements of energy efficiency efficiency does not apply to the requirements of equipping a capital construction facility with metering devices for energy resources used, compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004291245
Unscheduled inspection
Start date: 2020-02-27, end date: 2020-03-19, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of reconstruction of the capital construction facility the task of this audit is to prevent identify and suppress violations committed by the developer by the technical customer as well as by the person carrying out the reconstruction on the basis of an agreement with the developer or technical customer violations of legislation on urban planning activities, including technical regulations and design documentation requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements the requirements for equipping a capital construction facility with metering devices for energy resources used do not apply either. Compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004272520
Unscheduled inspection
Start date: 2020-01-22, end date: 2020-02-03, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban planning activities, including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok construction of 500 kV ORU" on the basis of paragraphs 4 58 60 62 64 66 68 70 72 74 76 77 79 inspection programs dated 09102019the objectives of this inspection are to prevent, identify and suppress violations of the legislation on urban development activities committed by JSC CIUS UES, including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok with the expansion of 500 kV Nevinnomyssk and 330 kV Mozdok substations construction of a 500 kV ORU"The subject of this audit is to note the necessary compliance with mandatory requirements or requirements established by municipal legal acts
# 001904144151
Unscheduled inspection
Start date: 2019-12-20, end date: 2019-12-27, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: compliance with the legislation of urban development
# 001904175991
Unscheduled inspection
Start date: 2019-12-24, end date: 2019-12-26, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to control the execution of JSC "CIUS UES" of the previously issued order dated 29102019 5711RVA18C on the elimination of violations during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok construction of 500 kV ORU" on the basis of the notice on the elimination of violations from 2112019 C512081THE tasks of this inspection are the implementation of control over the measures taken by CIUS UES JSC to comply with the order dated 29102019 5711RVA18C during the construction of the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation 500 kV ORU"The subject of this audit is the fulfillment of the instructions of the state control bodies
# 001904066366
Unscheduled inspection
Start date: 2019-12-06, end date: 2019-12-10, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of the order dated October 31, 2019 653G3320J01THE tasks of this audit are to monitor the measures taken by a legal entity to comply with the order and comply with the mandatory requirements of legislation on urban development during the construction reconstruction of a capital construction facility, to take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws laws and other regulatory legal acts7 The subject of verification is the fulfillment of the instruction of the state control body supervision
# 141904073522
Unscheduled inspection
Start date: 2019-12-11, end date: 2019-12-27, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, of violations of the legislation on urban development, including technical regulations and design documentation1 compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation in including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation
# 561904001774
Unscheduled inspection
Start date: 2019-11-26, end date: 2019-11-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: Implementation of regional state construction supervision on the basis of the inspection program identification and suppression of violations of the requirements of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources legislation on urban development h 2 st 51 h 2 3 31 6 st 52 h 2 4 7 st 53 of the Urban Planning Code of the Russian Federation compliance urban planning legislation during the period of a mothballed capital construction facility h 2 st 51 h 2 3 31 6 st 52 h 2 4 7 st 53 of the Urban Planning Code of the Russian Federation
# 561904001836
Unscheduled inspection
Start date: 2019-11-26, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection:
# 561904001597
Unscheduled inspection
Start date: 2019-11-26, end date: 2019-11-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: Implementation of regional state construction supervision on the basis of the inspection program identification and suppression of violations of the requirements of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources legislation on urban development h 2 st 51 h 2 3 31 6 st 52 h 2 4 7 st 53 of the Urban Planning Code of the Russian Federation Compliance urban planning legislation during the period of a mothballed capital construction facility h 2 st 51 h 2 3 31 6 st 52 h 2 4 7 st 53 of the Urban Planning Code of the Russian Federation
# 001904066398
Unscheduled inspection
Start date: 2019-11-27, end date: 2019-12-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to prevent violations of legislation on urban development activities, including project documentation. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to eliminate violations of mandatory requirements in the event of their identification and prosecution of persons who have committed violations of the requirements of Federal laws and other regulatory legal acts7 The subject of this audit is the compliance of the work performed and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation project documentation taking into account the changes made to the design documentation in accordance with parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of the article 52 of the Urban Planning Code of the Russian Federation
# 611904002126
Unscheduled inspection
Start date: 2019-11-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 141903998446
Unscheduled inspection
Start date: 2019-11-25, end date: 2019-12-20, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, of violations of the legislation on urban development, including technical regulations and design documentation1 compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation in including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation
# 001903899047
Unscheduled inspection
Start date: 2019-11-07, end date: 2019-11-11, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of the regulations dated August 14, 2019 517G3320J02THE objectives of this audit are to monitor the measures taken by a legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban development during the construction reconstruction of a capital construction facility, to take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws laws and other regulatory legal acts7 The subject of verification is the fulfillment of the instruction of the state control body supervision
# 141903897125
Unscheduled inspection
Start date: 2019-11-13, end date: 2019-12-03, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, of violations of the legislation on urban development, including technical regulations and design documentation1 compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation in including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation
# 001904030606
Unscheduled inspection
Start date: 2019-11-19, end date: 2019-11-20, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is conducted in order to monitor the implementation of the regulations dated July 17, 2019 469G3320J01 dated August 14, 2019 518G3320J01 The objectives of this audit are to monitor the measures taken by a legal entity to comply with the regulations and comply with mandatory requirements of legislation on urban development during the construction reconstruction of a capital construction facility, taking measures to eliminate violations of mandatory requirements if they are identified and to involve the responsibility of persons who have committed violations of the requirements of Federal laws and other regulatory legal acts7 The subject of verification is the fulfillment of the instructions of the state control supervision body
# 001903898983
Unscheduled inspection
Start date: 2019-11-19, end date: 2019-11-20, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is conducted in order to monitor the implementation of the regulations dated July 17, 2019 469G3320J01 dated August 14, 2019 518G3320J01 The objectives of this audit are to monitor the measures taken by a legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban development during the construction reconstruction of a capital construction facility, taking measures to eliminate violations of mandatory requirements if they are identified and to involve liability of persons who have committed violations of the requirements of Federal laws and other regulatory legal acts
# 001904063688
Unscheduled inspection
Start date: 2019-10-23, end date: 2019-11-11, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to prevent violations of legislation on urban development activities, including project documentation. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to eliminate violations of mandatory requirements in the event of their identification and prosecution of persons who have committed violations of the requirements of Federal laws and other regulatory legal acts7 The subject of this audit is the compliance of the work performed and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation project documentation taking into account the changes made to the design documentation in accordance with parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of the article 52 of the Urban Planning Code of the Russian Federation
# 001903712358
Unscheduled inspection
Start date: 2019-10-23, end date: 2019-10-31, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to implement the audit program approved by the Deputy head of Rostechnadzor MTU AA Kulakov on February 11, 2019. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to elimination of violations of mandatory requirements in case of their detection and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts7 The subject of this audit is the compliance of the work performed and the construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation including energy efficiency requirements with the exception of capital construction facilities which the requirements of energy efficiency do not apply to and the requirements for equipping a capital construction facility with metering devices for used energy resources, the need for a construction permit to comply with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001903899218
Unscheduled inspection
Start date: 2019-10-22, end date: 2019-11-11, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to prevent violations of legislation on urban development activities, including project documentation. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to eliminate violations of mandatory requirements in the event of their identification and prosecution of persons who have committed violations of the requirements of Federal laws and other regulatory legal acts7 The subject of this audit is the compliance of the work performed and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation project documentation taking into account the changes made to the design documentation in accordance with parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of the article 52 of the Urban Planning Code of the Russian Federation
# 661903876719
Unscheduled inspection
Start date: 2019-10-28, end date: 2019-11-25, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose of the implementation of the inspection program 080310210 of 27092019 Task implementation of state construction supervision is to verify the compliance of work and applicable building materials at the capital construction facility stages 3 4 and 5 of the reconstruction of the 220 Kv Kamenskaya substation located at the address Sverdlovsk region Kamenskuralsky st. Boksitovaya d 2 the results of such work with building codes and safety rules and state standards as well as the requirements of other regulatory legal acts of the Russian Federation and regulatory legal acts of federal executive authorities that are subject to mandatory execution during the construction of capital construction facilities
# 661903876553
Unscheduled inspection
Start date: 2019-10-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001903799081
Unscheduled inspection
Start date: 2019-10-08, end date: 2019-10-11, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the fulfillment by JSC "CIUS UES" of the points of the previously issued instruction on the elimination of identified violations from 22062018 CB2958R The purpose of this audit is to implement measures to control the elimination of violations specified in the previously issued instruction on the elimination of identified violations from 22062018 Cb2958r
# 001903937798
Unscheduled inspection
Start date: 2019-10-17, end date: 2019-10-29, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to verify compliance by CIUS UES JSC with the mandatory requirements of legislation on urban planning activities, including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok construction of 500 kV ORU" on the basis of paragraphs 74129 of the inspection program from 05062019 tasks The purpose of this audit is to prevent, identify and suppress violations of the legislation on urban planning activities committed by CIUS UES JSC, including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation 500 kV ORU"7 The subject of this audit is to note the necessary compliance with mandatory requirements
# 001903853184
Unscheduled inspection
Start date: 2019-10-15, end date: 2019-11-01, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in accordance with the notice of completion of construction reconstruction of the capital construction facility in order to control the compliance of the completed works with the mandatory requirements of the design documentation requirements for energy conservation and energy efficiency improvement and other regulatory legal acts during the construction of the capital construction facility the task of this inspection is to prevent identify and suppress the mistakes made by the developer the technical customer as well as the person carrying out construction on the basis of an agreement with a developer or a technical customer for violations of legislation on urban planning activities, including design documentation requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements approved in accordance with parts 15 152 and 153 of Article 48 of this Urban Planning Code project documentation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of this Code and or the information model, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used
# 001903148825
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-09-30, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to control the execution of JSC "CIUS UES" of the previously issued order dated 19072019 3088RVA18C on the elimination of violations during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation 500 kV ORU"The objectives of this audit are to monitor the measures taken by JSC "CIUS UES" to comply with the regulation dated 19072019 3088RVA18. The purpose of this audit is to comply with the instructions of state control bodies
# 741903554728
Unscheduled inspection
Start date: 2019-09-23, end date: 2019-09-27, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to verify compliance with mandatory requirements in the field of urban development activities on the basis of the verification program. The objectives of this audit are to prevent identify and suppress violations in the implementation of measures to monitor compliance with the requirements of legislation on urban development
# 001903018330
Unscheduled inspection
Start date: 2019-09-02, end date: 2019-09-13, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used for construction, compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001903018261
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-09-27, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used for construction, compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902961329
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-08-14, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of the regulation dated April 24, 2019 271G3320J02THE tasks of this audit are to monitor the measures taken by a legal entity to comply with the regulation and comply with the mandatory requirements of legislation on urban development during the construction reconstruction of a capital construction facility, to take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws laws and other regulatory legal acts7 The subject of verification is the fulfillment of the instruction of the state control body supervision
# 001902961260
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-08-14, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of the regulation dated April 24, 2019 271G3320J02THE tasks of this audit are to monitor the measures taken by a legal entity to comply with the regulation and comply with the mandatory requirements of legislation on urban development during the construction reconstruction of a capital construction facility, to take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws laws and other regulatory legal acts7 The subject of verification is the fulfillment of the instruction of the state control body supervision
# 791902947845
Unscheduled inspection
Start date: 2019-08-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 261903003756
Unscheduled inspection
Start date: 2019-08-21, end date: 2019-09-13, duration: —
Authority: Gosudarstvennaya inspekciya truda v Stavropolskom krae
Purpose of inspection: protection of the rights and interests of employees in connection with the consideration of the appeal dated 14082019 2672336190B of remuneration
# 001903009116
Unscheduled inspection
Start date: 2019-08-27, end date: 2019-09-09, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with legislation on urban planning activities, including technical regulations and project documentation on the basis of paragraph 1 of the inspection program dated 17062019 agreed with JSC "CIUS UES"
# 001902944154
Unscheduled inspection
Start date: 2019-08-09, end date: 2019-08-21, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to control the execution of JSC "CIUS UES" of the previously issued order dated 28052019 1969RVA181 on the elimination of violations during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation 500 kV ORU construction"The objectives of this audit are to monitor the measures taken by CIUS UES JSC to comply with the regulation dated 28052019 1969.1181 The subject of this audit is the implementation of the instructions of the state control and supervision bodies
# 141903020971
Unscheduled inspection
Start date: 2019-08-28, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 001902900497
Unscheduled inspection
Start date: 2019-07-25, end date: 2019-07-31, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the completed construction of the capital construction facility Verification of compliance of the work and construction materials used in the process of construction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements of equipping the capital construction facility with metering devices for used energy resources availability of a permit for construction of compliance with the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation dated 29122004 190FZ
# 501903330797
Unscheduled inspection
Start date: 2019-07-26, end date: 2019-08-01, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the execution of the prescription from 18042019 0225062600503 with a deadline of 18072019
# 001902820296
Unscheduled inspection
Start date: 2019-07-04, end date: 2019-07-17, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to implement the audit program approved by the Deputy head of Rostechnadzor MTU AA Kulakov on February 11, 2019. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to elimination of violations of mandatory requirements in case of their detection and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts7 The subject of this audit is the compliance of the work performed and the construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation including energy efficiency requirements with the exception of capital construction facilities which the requirements of energy efficiency do not apply to and the requirements for equipping a capital construction facility with metering devices for used energy resources, the need for a construction permit to comply with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 501902773764
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-17, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the fulfillment of the instruction from 03042019 0658015700503 assessment of compliance of the work performed with the requirements of technical regulations and design documentation at the capital construction facility complex technical re-equipment and reconstruction of the 220 kV Oka substation at the address Moscow region Serpukhov district Bolshevik district
# 791902795305
Unscheduled inspection
Start date: 2019-06-26, end date: 2019-06-27, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora i ekspertizy Evreiskoi avtonomnoi oblasti
Purpose of inspection: the inspection is carried out on the basis of a notice received from the developer on the completion of the construction of a capital construction facility in order to verify the compliance of the completed works with the requirements of the project documentation, the project of work production, technical regulations and regulatory documents regulating norms in construction, verification of the maintenance of executive documentation, verification of compliance and completeness of construction control by the developer and the person carrying out construction on the basis of an agreement with the developer, hereinafter referred to as the contractor, verification of performance compliance with the requirements established by parts 2 3 31 and 5 of Article 52 of the Urban Planning Code of the Russian Federation The objectives of this audit are to identify violations of mandatory requirements to prevent identify and suppress violations of legislation on urban development activities committed by the developer technical customer contractor, including technical regulations and design documentationthe subject of this audit is the compliance of the work and the applicable construction materials in the process of construction of a capital construction facility as well as the results of such work to the requirements of technical regulations other regulations and design documentation, including requirements for energy efficiency and requirements for equipment of a capital construction facility for energy resources used availability of a construction permit compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 791902754047
Unscheduled inspection
Start date: 2019-06-04, end date: 2019-06-06, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora i ekspertizy Evreiskoi avtonomnoi oblasti
Purpose of inspection: the inspection is carried out on the basis of the developed inspection program for the 2nd quarter of 2019 in order to verify the compliance of the completed works and the work performed with the requirements of the project documentation, technical regulations and regulatory documents, verification of the maintenance of executive documentation, verification of compliance and completeness of ongoing construction control by the technical customer and the person carrying out construction on the basis of an agreement with the developer, hereinafter referred to as the contractor, verification of compliance with the requirements safety and fire safety at the facility The objectives of this audit are to identify violations of mandatory requirements, to prevent, identify and suppress violations of legislation on urban development, including technical regulations and design documentation, committed by the developer, technical customer and contractor, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of a capital construction facility, as well as the results of such the requirements of technical regulations, other normative acts and project documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for energy resources used compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 281902711676
Unscheduled inspection
Start date: 2019-05-15, end date: 2019-06-11, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: the implementation of the inspection program approved on 29102018the tasks of this inspection are to prevent identify and suppress violations committed by the developer, the technical customer, the person carrying out the construction of compliance with the requirements of the project documentation performed during the construction of the capital construction facility, as well as the results of such work, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for used energy resources
# 281902675071
Unscheduled inspection
Start date: 2019-05-15, end date: 2019-06-11, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: checking the completed construction of the facility and resolving the issue of issuing an opinion on the compliance of the constructed object of work with regulatory legal acts and project documentation The objectives of this audit are to prevent identify and suppress violations of compliance by the developer, the technical customer, the person carrying out the construction, performed during the construction of the capital construction project documentation The subject of this audit is to verify the compliance of the work and the construction materials used in the the process of construction of the capital construction facility as well as the results of such work project documentation
# 001902669281
Unscheduled inspection
Start date: 2019-05-13, end date: 2019-05-21, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban planning activities verification of compliance of completed works and applied building materials during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used verification of compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law the Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 001902707865
Unscheduled inspection
Start date: 2019-05-20, end date: 2019-06-17, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 501902662358
Unscheduled inspection
Start date: 2019-04-16, end date: 2019-04-18, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the execution of the order dated 15012019 0225062600502 with a deadline of 15042019
# 001902594692
Unscheduled inspection
Start date: 2019-04-16, end date: 2019-04-23, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken to ensure compliance by a legal entity with the mandatory requirements of legislation on urban planning during the construction reconstruction of a capital construction facility prevention detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and regulations 7 The subject of this audit is the compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements of equipping the capital construction facility with metering devices for energy resources used availability of a construction permit compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 771902674136
Unscheduled inspection
Start date: 2019-04-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001902594728
Unscheduled inspection
Start date: 2019-04-23, end date: 2019-04-24, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is conducted in order to monitor the implementation of the regulations dated December 28, 2018 949G3320J01 dated January 21, 2019 18G3320J01 The objectives of this audit are to monitor the measures taken by a legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban development during the construction reconstruction of a capital construction facility taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts 7 The subject of verification is the fulfillment of the instructions of the state control supervision body
# 001902594750
Unscheduled inspection
Start date: 2019-04-23, end date: 2019-04-24, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is conducted in order to monitor the implementation of the regulation dated January 21, 2019 19G3320J02 The objectives of this audit are to monitor the measures taken by a legal entity to comply with the regulation and comply with the mandatory requirements of legislation on urban development during the construction reconstruction of a capital construction facility, take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice those who committed violations of the requirements of Federal laws and other regulatory legal acts 7 The subject of verification is the fulfillment of the instructions of the state control supervision body
# 261902692926
Unscheduled inspection
Start date: 2019-04-26, end date: 2019-05-21, duration: —
Authority: Gosudarstvennaya inspekciya truda v Stavropolskom krae
Purpose of inspection: protection of the rights and interests of employees in connection with the consideration of the appeal dated 23042019 2671280190B of remuneration
# 791902620850
Unscheduled inspection
Start date: 2019-04-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001902556807
Unscheduled inspection
Start date: 2019-03-11, end date: 2019-04-05, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the fulfillment of the instruction previously issued to the person being checked from 04122018 09721 on the elimination of previously identified violations, the deadline for which expires 040319 The task of the audit is to establish the fact of elimination of previously identified violations specified in the instruction from 04122018 09721 The subject of this audit is the fulfillment of the instruction of the state construction supervision authority from 04122018 09721
# 001902426377
Unscheduled inspection
Start date: 2019-01-16, end date: 2019-01-21, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 13092018 665G3320J01 Execution of the order of 13092018 666G3320J01 Execution of the order of 29102018 793G3320J01
# 001902426367
Unscheduled inspection
Start date: 2019-01-16, end date: 2019-01-21, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 13092018 685G3320J02 Execution of the order of 13092018 686G3320J02 Execution of the order of 31102018 803G3320J02
# 001902481519
Unscheduled inspection
Start date: 2019-01-25, end date: 2019-02-07, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 281902454402
Unscheduled inspection
Start date: 2019-01-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 281902454373
Unscheduled inspection
Start date: 2019-01-24, end date: 2019-02-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations committed by the developer, the technical customer, the person carrying out the construction of violations of compliance performed during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used by the subject of this audit The purpose of the audit is to verify the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 001802163075
Unscheduled inspection
Start date: 2018-12-05, end date: 2018-12-11, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban planning activities verification of compliance of completed works and applied building materials during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used verification of compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law the Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 501802303278
Unscheduled inspection
Start date: 2018-12-11, end date: 2019-01-15, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the information set out in the submission of the Head of the Construction Supervision Department 2 of the Construction Supervision Department of Glavgosstroynadzor of the Moscow Region EM Babenko dated 28112018 NW22590902
# 001802195535
Unscheduled inspection
Start date: 2018-12-17, end date: 2018-12-28, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001802193309
Unscheduled inspection
Start date: 2018-11-21, end date: 2018-11-27, duration: —
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: it is carried out in order to monitor the implementation of pp 1 15 of the previously issued prescription from 27042018 10105C2018B1 during the construction of the capital construction facility "Construction of the 500 kV Beloberezhskaya substation with 500 kV Novobryanskaya Yeletskaya overhead line 220 kV Beloberezhskaya Cement overhead line 220 kV Beloberezhskaya Machine Plant and 220 kV Beloberezhskaya Bryanskaya overhead line" located at Bryansk region Karachevsky district Mylinskoye rural settlement The Berezovsky deadline for which expired on 27072018 and 27102018 the objectives of this audit are to verify the elimination by a legal entity of the violations identified in paragraphs 1 15 of the previously issued prescription from 27042018 10105C2018B1 The subject of this audit is to verify the fulfillment by a legal entity of paragraphs 115 of the previously issued prescription from 27042018 10105C2018B1
# 741802190010
Unscheduled inspection
Start date: 2018-11-26, end date: 2018-12-05, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out within the framework of federal state construction supervision during the construction and reconstruction of facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation with the exception of facilities in respect of which state construction supervision by decrees of the President of the Russian Federation is entrusted to other federal executive authorities registry number 10001515438 This inspection is carried out in order to verify compliance with mandatory requirements in the field of urban planning based on the verification program
# 001802130122
Unscheduled inspection
Start date: 2018-11-28, end date: 2018-12-25, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development activities, including design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor. The subject of this audit is to control the compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements project documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for used energy resources availability of a construction permit compliance with the requirements established by parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation during the construction of a capital construction facility "PS 500 kV Sunrise with approaches 500 kV and 220 kV overhead lines" located at the address Omsk region Kormilovsky district Georgievskoye rural settlement
# 281802115336
Unscheduled inspection
Start date: 2018-11-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 141802009020
Unscheduled inspection
Start date: 2018-10-24, end date: 2018-11-07, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: In order to verify, in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Russian Federation on December 28, 2017, compliance with mandatory requirements in the field of construction and applied building materials products of the established procedure for construction reconstruction of the capital construction facility by the developer, the technical customer, the person carrying out construction, with the established procedure for construction reconstruction of the capital construction facility, the objectives of this audit are to prevent, identify and suppress violations committed by the customer and also, the person carrying out construction on the basis of an agreement with the developer or with the customer hereinafter referred to as the contractor of violations of the legislation on urban planning activities, including technical regulations and project documentation, the subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts 1 compliance of the work and the construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements of parts 23 and 316 of Article 52 of the Urban Planning Code of the Russian Federation
# 001801762185
Unscheduled inspection
Start date: 2018-10-25, end date: 2018-10-29, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 12072018 491G3327J01 Execution of the order of 24072018 555G3327J01
# 001801763115
Unscheduled inspection
Start date: 2018-10-30, end date: 2018-10-31, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 12072018 492G3327J02 Execution of the order of 24072018 556G3327J02
# 001801763102
Unscheduled inspection
Start date: 2018-10-30, end date: 2018-10-31, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 12072018 492G3327J02 Execution of the order of 24072018 556G3327J02
# 001801762392
Unscheduled inspection
Start date: 2018-10-30, end date: 2018-10-31, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 12072018 492G3327J02 Execution of the order of 24072018 556G3327J02
# 001800769860
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-09-13, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800769845
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-09-13, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800765826
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-09-13, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800673467
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-09-13, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the execution of the order dated May 24, 2018 363G3327J01
# 001800673454
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-09-13, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the execution of the order dated May 24, 2018 364G3327J02
# 001800687123
Unscheduled inspection
Start date: 2018-08-30, end date: 2018-09-26, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation with the requirements for energy saving and energy efficiency improvement during the construction of the capital construction facility "500 kV Voskhod substation with 500 kV and 220 kV overhead lines" located at Omsk region Kormilovsky district Georgievskoye rural settlement on the basis of the inspection program C2512018 dated 17042018 g
# 001800499065
Unscheduled inspection
Start date: 2018-07-16, end date: 2018-08-03, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the fulfillment of the instruction previously issued to the person being checked from 05032018 0983 on the elimination of violations identified earlier, the deadline for which has expired The task of the audit is to establish the fact of elimination of previously identified violations specified in the instruction from 05032018 0983 The subject of this audit is the fulfillment of the instruction of the state construction supervision authority from 05032018 0983
# 001800496286
Unscheduled inspection
Start date: 2018-07-16, end date: 2018-07-24, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800492524
Unscheduled inspection
Start date: 2018-07-16, end date: 2018-07-24, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800578692
Unscheduled inspection
Start date: 2018-07-30, end date: 2018-08-24, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of state construction supervision during the construction of the specified capital construction facility in connection with the onset of completion dates of works that are subject to verification in accordance with the approved program of inspections during the construction of the capital construction facility
# 001800496308
Unscheduled inspection
Start date: 2018-07-10, end date: 2018-07-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order from 09042018 g 225G3327J01 Execution of the order from 19042018 g 257G3327J01
# 001800492598
Unscheduled inspection
Start date: 2018-07-10, end date: 2018-07-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order from 09042018 g 226G3327J02 Execution of the order from 19042018 g 256G3327J02
# 001800524569
Unscheduled inspection
Start date: 2018-07-05, end date: 2018-07-13, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development activities, including technical regulations and project documentation, committed by the developer, the customer, as well as by persons carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor
# 001800528977
Unscheduled inspection
Start date: 2018-07-02, end date: 2018-07-03, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to control the execution of JSC "CIUS UES" previously issued instruction from 06042018 821RVPA18 on the elimination of violations during the reconstruction of the capital construction facility "Reconstruction and technical re-equipment of 330 kV Vladikavkaz2" the objectives of this inspection are to monitor the measures taken by JSC "CIUS UES" to comply with the instruction from 06042018 821RVPA18 and compliance with mandatory requirements regulatory acts in the field of construction during the construction of the reconstruction of the capital construction facility "Reconstruction and technical re-equipment of the 330 kV Vladikavkaz2 substation" b taking measures to identify violations of mandatory requirements and to bring to justice persons who committed violations of the requirements of federal laws and other regulatory legal acts
# 001800465843
Unscheduled inspection
Start date: 2018-07-02, end date: 2018-07-27, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the fulfillment of the instruction previously issued to the person being checked from 28122017 09864C on the elimination of previously identified violations, the deadline for which has expired The task of the audit is to establish the fact of elimination of previously identified violations specified in the instruction from 28122017 09864C The subject of this audit is the fulfillment of the instruction of the state construction supervision authority from 28122017 09864C
# 001802512110
Unscheduled inspection
Start date: 2018-07-02, end date: 2018-07-03, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to control the execution of JSC CIUS UES of the previously issued instruction from 06042018 821RVPA18 on the elimination of violations during the reconstruction of the capital construction facility "Reconstruction and technical re-equipment of 330 kV Vladikavkaz2" the objectives of this inspection are to monitor the measures taken by JSC CIUS UES to comply with the instruction from 06042018 821RVPA18 and compliance with mandatory regulatory requirements acts in the field of construction during the construction of the reconstruction of the capital construction facility "Reconstruction and technical re-equipment of 330 kV Vladikavkaz2" b taking measures to identify violations of mandatory requirements and to bring to justice persons who committed violations of the requirements of federal laws and other regulatory legal acts The subject of this audit is the fulfillment of the instructions of state control bodies supervision of municipal control bodies carrying out measures to prevent causing harm to the life and health of citizens, harm to animals, plants, the environment, cultural heritage sites, historical and cultural monuments of the peoples of the Russian Federation, museum objects and museum collections included in the Museum Fund of the Russian Federation, especially valuable, including unique documents of the Archival Fund of the Russian Federation, documents of special historical scientific and cultural significance that are part of the national library fund
# 741800482505
Unscheduled inspection
Start date: 2018-06-19, end date: 2018-06-22, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the fulfillment by JSC "CIUS EU" of the points of the previously issued instruction on the elimination of identified violations from 02022018 Cb299 The task of this audit is to implement measures to control the elimination of violations specified in the previously issued instruction on the elimination of identified violations from 02022018 Cb299
# 001800442724
Unscheduled inspection
Start date: 2018-06-13, end date: 2018-06-15, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the fulfillment of the previously issued instruction on the elimination of identified violations 351415rp12 of 30032018, the deadline for the elimination of which expired 31052018
# 001800511105
Unscheduled inspection
Start date: 2018-06-29, end date: 2018-07-26, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to control the fulfillment by a legal entity, an individual entrepreneur, previously issued by the state construction supervision authority of the points of the instruction on the elimination of identified violations of mandatory requirements 570900518C dated January 12, 2018. The objectives of this audit are to verify the elimination by a legal entity of the identified violation specified in paragraphs of the instruction 570900518C dated January 12, 2018. The subject of this audit is the fulfillment of the instructions of state control bodies supervision of municipal control bodies
# 001800511140
Unscheduled inspection
Start date: 2018-06-29, end date: 2018-07-26, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to control the fulfillment by a legal entity, an individual entrepreneur, previously issued by the state construction supervision authority of the points of the order on the elimination of identified violations of mandatory requirements 570900118C dated January 12, 2018. The objectives of this audit are to verify the elimination by a legal entity of the identified violation specified in paragraphs of the order 570900118C dated January 12, 2018. The subject of this audit is the fulfillment of the instructions of state control bodies supervision of municipal control bodies
# 001800511124
Unscheduled inspection
Start date: 2018-06-29, end date: 2018-07-26, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to control the fulfillment by a legal entity, an individual entrepreneur, previously issued by the state construction supervision authority of the points of the order on the elimination of identified violations of mandatory requirements 570900318C dated January 12, 2018. The objectives of this audit are to verify the elimination by a legal entity of the identified violation specified in paragraphs of the order 570900318C dated January 12, 2018. The subject of this audit is the fulfillment of the instructions of state control bodies supervision of municipal control bodies
# 001800499383
Unscheduled inspection
Start date: 2018-06-20, end date: 2018-06-21, duration: —
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the implementation of pp 1 2 of the previously issued regulation dated 20042018 09105S2018B during the construction of the capital construction facility "Construction of 500 kV Beloberezhskaya substation with 500 kV Novobryanskaya Yeletskaya overhead line 220 kV Beloberezhskaya Cement overhead line 220 kV Beloberezhskaya Machine Plant and 220 kV Beloberezhskaya Bryanskaya overhead line" located at Bryansk region Karachevsky district Mylinsky rural settlement Berezovsky the deadline for which expired in 2006-2018, the objectives of this audit are to verify the elimination by a legal entity of the violations identified in paragraphs 1 to 2 of the previously issued prescription from 20042018 09105C2018B The subject of this audit is to verify the fulfillment by a legal entity of paragraph 12 of the previously issued prescription from 20042018 09105C2018B
# 001800458101
Unscheduled inspection
Start date: 2018-05-21, end date: 2018-06-01, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban planning activities, including technical regulations and design documentation during the construction of the capital construction facility "Construction of 330 kV ArtemDerbent overhead line" on the basis of paragraphs 1 to 8 of the inspection program dated 31102017, the objectives of this audit are: prevention, identification and suppression of violations committed by JSC "CIUS UES" violations of legislation on urban planning activities, including technical regulations and design documentation during the construction of the capital construction facility "Construction of the 330 kV ArtemDerbent overhead line" b taking measures to identify violations of mandatory requirements and to bring to justice persons who violated the requirements of Federal laws and other regulatory legal acts
# 001800301080
Unscheduled inspection
Start date: 2018-05-21, end date: 2018-05-24, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution of the regulation dated February 12, 2018 91G3327J02
# 001800301076
Unscheduled inspection
Start date: 2018-05-21, end date: 2018-05-24, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the execution of the regulation dated February 12, 2018 90G3327J01
# 141800384616
Unscheduled inspection
Start date: 2018-05-22, end date: 2018-05-31, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: In order to verify, in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Russian Federation on December 28, 2017, compliance during the construction of a capital construction facility by the developer, the technical customer, the person carrying out the construction of mandatory requirements in the field of construction and used building materials, products of the established procedure for the construction of reconstruction of a capital construction facility, the objectives of this audit are to prevent, identify and suppress violations committed by the customer and also, the person carrying out construction on the basis of an agreement with the developer or with the customer hereinafter referred to as the contractor of violations of the legislation on urban planning activities, including technical regulations and project documentation, the subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts 1 compliance with the performance of works and applied building materials during the construction reconstruction of a capital construction facility as well as the results of such the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements of parts 23 and 316 of Article 52 of the Urban Planning Code of the Russian Federation
# 001800358902
Unscheduled inspection
Start date: 2018-05-22, end date: 2018-05-28, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development activities, including technical regulations and project documentation, committed by the developer, the customer, as well as by persons carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor
# 001800224828
Unscheduled inspection
Start date: 2018-04-12, end date: 2018-04-19, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800224268
Unscheduled inspection
Start date: 2018-04-12, end date: 2018-04-19, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800285064
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-04-20, duration: —
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the implementation of pp 1 12 of the previously issued regulation dated 13122017 3372S2017B during the construction of the capital construction facility "Construction of 500 kV Beloberezhskaya substation with 500 kV Novobryanskaya Yeletskaya overhead line 220 kV Beloberezhskaya Cement overhead line 220 kV Beloberezhskaya Machine Plant and 220 kV Beloberezhskaya Bryanskaya overhead line" located at Bryansk region Karachevsky district Mylinsky rural settlement Berezovsky the deadline for which expired on 04/100/2018 the objectives of this audit are to verify the elimination by a legal entity of the violations identified in paragraphs 1-12 of the previously issued regulation dated 13122017 3372C2017B The subject of this audit is to verify the fulfillment by a legal entity of paragraphs 112 of the previously issued regulation dated 13122017 3372C2017B
# 001800286744
Unscheduled inspection
Start date: 2018-04-23, end date: 2018-04-30, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban planning activities verification of compliance of completed works and applied building materials during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used verification of compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law the Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 001800224732
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-09, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation dated 25.012018 37G3327J01
# 001800224384
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-09, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation dated 25.012018 38G3327J02
# 001800167487
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-06, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to control the execution of JSC "CIUS UES" previously issued regulation No. 27112017 7087rV18 on the elimination of violations during the reconstruction of the capital construction facility "Reconstruction and technical re-equipment of 330 kV Vladikavkaz2" the objectives of this inspection are to monitor the measures taken by JSC "CIUS UES" to comply with the regulation of 27112017 7087rV18 and compliance with mandatory requirements regulatory acts in the field of construction during the construction of the reconstruction of the capital construction facility "Reconstruction and technical re-equipment of the 330 kV Vladikavkaz2 substation" b taking measures to identify violations of mandatory requirements and to bring to justice persons who violated the requirements of federal laws and other regulatory legal acts
# 001800292406
Unscheduled inspection
Start date: 2018-03-20, end date: 2018-04-09, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban planning activities, including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation 500 kV ORU construction" on the basis of paragraphs 930 of the inspection program from 25082017 the objectives of this audit are: a prevention, detection and suppression of violations of the legislation on urban planning activities committed by CIUS UES JSC, including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation construction of 500 kV ORU" b taking measures to to identify violations of mandatory requirements and to bring to justice persons who have committed violations of the requirements of federal laws and other regulatory legal acts
# 001800167324
Unscheduled inspection
Start date: 2018-03-20, end date: 2018-04-09, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban planning activities, including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation 500 kV ORU construction" on the basis of paragraphs 930 of the inspection program from 25082017 the objectives of this audit are: a prevention, detection and suppression of violations of the legislation on urban planning activities committed by CIUS UES JSC, including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation construction of 500 kV ORU" b taking measures to to identify violations of mandatory requirements and to bring to justice persons who have committed violations of the requirements of federal laws and other regulatory legal acts
# 001800225008
Unscheduled inspection
Start date: 2018-03-22, end date: 2018-03-29, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation dated 25.012018 g 30G3327J03
# 001800211499
Unscheduled inspection
Start date: 2018-03-22, end date: 2018-03-30, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development activities, including technical regulations and project documentation, committed by the developer, the customer, as well as by persons carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor
# 001800103111
Unscheduled inspection
Start date: 2018-03-01, end date: 2018-03-30, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to control the fulfillment by a legal entity, an individual entrepreneur, previously issued by the state construction supervision authority of the points of the instruction on the elimination of identified violations of mandatory requirements 570910917R dated October 23, 2017. The objectives of this audit are to verify the elimination by a legal entity of the identified violation specified in the paragraphs of the instruction 570910917R dated October 23, 2017. The subject of this audit is the fulfillment of the instructions of state control bodies supervision of municipal control bodies for the Reconstruction of the 500 kV Tyumen substation
# 001800103115
Unscheduled inspection
Start date: 2018-03-01, end date: 2018-03-30, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to control the fulfillment by a legal entity, an individual entrepreneur, of the previously issued by the state construction supervision authority of the points of the instruction on the elimination of identified violations of mandatory requirements 570910717R dated October 23, 2017. The objectives of this audit are to verify the elimination by a legal entity of the identified violation specified in the paragraphs of the instruction 570910717R dated October 23, 2017. The subject of this audit is the fulfillment of the instructions of state control bodies supervision of municipal control bodies for the facility "Reconstruction of the 500 kV Demyanskaya substation"
# 141800240241
Unscheduled inspection
Start date: 2018-03-28, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 001800064016
Unscheduled inspection
Start date: 2018-02-12, end date: 2018-02-19, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban planning activities verification of compliance of completed works and applied building materials during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used verification of compliance with the requirements of parts 2 and 3 of Article 52 of the Federal Law the Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 001800099081
Unscheduled inspection
Start date: 2018-02-26, end date: 2018-03-27, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the implementation of state construction supervision during the construction of the specified capital construction facility in connection with the onset of completion dates of works that are subject to verification in accordance with the approved program of inspections during the construction of the capital construction facility The objectives of this audit are to prevent identify and suppress violations of the legislation on urban planning activities committed by the person carrying out the construction, including technical regulations and project documentation The subject of this audit The purpose of the audit is to verify the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 001800104557
Unscheduled inspection
Start date: 2018-02-05, end date: 2018-02-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800104474
Unscheduled inspection
Start date: 2018-02-05, end date: 2018-02-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800051253
Unscheduled inspection
Start date: 2018-02-05, end date: 2018-02-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800051223
Unscheduled inspection
Start date: 2018-02-05, end date: 2018-02-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800172162
Unscheduled inspection
Start date: 2018-02-07, end date: 2018-02-19, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800051960
Unscheduled inspection
Start date: 2018-02-07, end date: 2018-02-19, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Compliance with the requirements of the legislation on urban planning during the construction and reconstruction of a capital construction facility
# 001800170719
Unscheduled inspection
Start date: 2018-01-22, end date: 2018-01-25, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation from 18102017 574G3327J03
# 001800170523
Unscheduled inspection
Start date: 2018-01-22, end date: 2018-01-25, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation of 14122017 g 748G3327Z09
# 001800170635
Unscheduled inspection
Start date: 2018-01-22, end date: 2018-01-25, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation from 12102017 g 565G3327J02
# 741800309089
Unscheduled inspection
Start date: 2018-01-29, end date: 2018-02-02, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of JSC "CIUS EU" previously issued regulations H3921 of 05082016 and H5631 of 11112016, the deadline for which has expired The task of this unscheduled on-site inspection is to implement measures to control the elimination of violations specified in regulations H3921 of 05082016 and H5631 of 11112016
# 741700078960
Unscheduled inspection
Start date: 2017-12-29, end date: 2018-01-26, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to comply with mandatory requirements in the field of urban planning activities The tasks of inspections are to prevent identify and suppress violations in the implementation of measures to monitor compliance with the requirements of legislation on urban planning activities
# 00170802996796
Unscheduled inspection
Start date: 2017-12-25, end date: 2017-12-28, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: inspections of the completed construction of the capital construction facility "Reconstruction of the 500 kV substation and the transfer of panels to the OPU3 with the dismantling of the OPU1" on the basis of the notice of completion of the BN dated November 20, 2017 in order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation requirements for energy saving and energy efficiency improvement during the construction of the capital construction facility warning identification and suppression of violations of mandatory requirements of regulatory documents and legislative acts compliance of work and construction materials used in the process of construction reconstruction of a capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used availability of a construction permit compliance with the requirements established by parts 2 3 and 3_1 of Article 52 of this Code
# 00170802907053
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-11-29, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170802866228
Unscheduled inspection
Start date: 2017-11-16, end date: 2017-11-27, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban development, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction and technical re-equipment of the 330 kV Vladikavkaz2 substation" on the basis of paragraph 1 of the inspection program from 30062017the tasks of this audit are prevention detection and suppression of admitted JSC "CIUS UES"violations of legislation on urban planning activities, including technical regulations and design documentation during the reconstruction of a capital construction facility "Reconstruction and technical re-equipment of the 330 kV Vladikavkaz2 substation"b taking measures to identify violations of mandatory requirements and to bring to justice persons who violated the requirements of Federal laws and other regulatory legal acts
# 00170802714341
Unscheduled inspection
Start date: 2017-10-09, end date: 2017-10-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 31032017 141 G3327J02 Fulfillment of the order of 28042017 213 G3327J02 Fulfillment of the order of 15052017 230 G3327J02
# 00170802714240
Unscheduled inspection
Start date: 2017-10-09, end date: 2017-10-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 31032017 140G3327J01 Execution of the order of 28042017 212G3327J01 Execution of the order of 15052017 229G3327J01
# 00170802663544
Unscheduled inspection
Start date: 2017-10-11, end date: 2017-10-18, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the prescription from 10082017 g 420G3327J03
# 00170802421838
Unscheduled inspection
Start date: 2017-09-14, end date: 2017-09-26, duration: —
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify compliance by JSC "CIUS UES" with the mandatory requirements of legislation on urban development, including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation 500 kV ORU construction" on the basis of paragraphs 18 of the inspection program from 25082017the tasks of this audit are a prevention, detection and suppression of violations of the legislation on urban planning activities committed by JSC "CIUS UES", including technical regulations and design documentation during the reconstruction of the capital construction facility "500 kV Nevinnomyssk Mozdok overhead line with the expansion of 500 kV Nevinnomyssk substation and 330 kV Mozdok substation 500 kV ORU construction"b taking measures to identify violations mandatory requirements and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts
# 00170801958218
Unscheduled inspection
Start date: 2017-09-12, end date: 2017-09-28, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 50170701907559
Unscheduled inspection
Start date: 2017-08-14, end date: 2017-08-16, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the fulfillment of the instruction from 13062017 0658015700501 compliance with mandatory requirements established by law assessment of compliance of the work performed with the requirements of technical regulations and design documentation at the capital construction facility complex technical re-equipment and reconstruction of the 220 kV Oka substation at the address Moscow region Serpukhov district district pos Bolshevik
# 00170701845896
Unscheduled inspection
Start date: 2017-08-01, end date: 2017-08-10, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the prescription from 28062017 g 344G3327J03
# 00170701775139
Unscheduled inspection
Start date: 2017-07-17, end date: 2017-07-21, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution by a legal entity of a previously issued order dated 31032017 54727prvnP01642017
# 74170701801975
Unscheduled inspection
Start date: 2017-07-14, end date: —, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00170701773324
Unscheduled inspection
Start date: 2017-07-10, end date: 2017-07-17, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation from 31032017 g 142G3327J03
# 00170701825132
Unscheduled inspection
Start date: 2017-06-13, end date: 2017-06-28, duration: —
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The test is carried out to monitor compliance of the performed works with the mandatory requirements of technical regulations of other regulatory legal acts of the design documentation requirements on energy saving and increase of energy efficiency in the construction of capital construction object "Construction of 500 kV beloberezhskaya with overhead 500 kV Novobryanskaya Yelets 220 kV overhead line beloberezhskaya Cement 220 kV overhead line beloberezhskaya Mashzavod and 220 kV overhead line beloberezhskaya Bryansk" 242524 Bryansk oblast Karachevsky district Ilinskoe rural settlement p Berezovsky on the basis of a programme of inspections in the case 117С0058Б2014 approved by Oka Department of Rostechnadzor from 18042017г 568 Objectives of this review are to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder customer violations of the legislation on town-planning activities including technical regulations and project documentation of the Subject of this review is to check the construction of the facility in accordance with the requirements of article 51 of the parts 2 and 3 of article 52 article 53 54 the town-planning code of the Russian Federation of electrical safety and emergency fire safety, environmental protection sanitary and epidemiological norms of labor legislation compliance of the performed works and construction materials used in the construction process of the facility and the results of such work to the requirements of technical regulations and project documentation other regulatory legal acts including the requirements of energy efficiency and the requirements of the equipment of a capital construction object metering devices of energy resources to the availability of building permits
# 50170701716224
Unscheduled inspection
Start date: 2017-06-09, end date: 2017-06-13, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the facts set out in the memo of the head of the ONzS 6 GS Kashkarov dated 26052017 SZ1150606 compliance with mandatory requirements established by law assessment of compliance of the work performed with the requirements of technical regulations and design documentation at the capital construction facility complex technical re-equipment and reconstruction of the 220 kV Oka substation at the address Moscow region Serpukhov district district pos Bolshevik
# 00170701722359
Unscheduled inspection
Start date: 2017-06-26, end date: 2017-06-28, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of regulation 85G3327J03 dated February 27, 2017
# 00170701563541
Unscheduled inspection
Start date: 2017-05-10, end date: 2017-05-15, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701563501
Unscheduled inspection
Start date: 2017-05-10, end date: 2017-05-15, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701615085
Unscheduled inspection
Start date: 2017-04-26, end date: 2017-04-27, duration: —
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to control the fulfillment of violations set out in paragraphs 1 11 12 13 14 15 16 17 18 19 110 111 regulations of 23122016 777 C2016 the objectives of this audit are to verify the elimination by a legal entity of the violations identified in paragraphs 111213141516171819110 111 regulations of 23122016 777 C2016 the subject of this audit is to verify the fulfillment by a legal entity of paragraphs 111 1213141516171819110 111 regulations from 23122016 777C2016 of the Prioksky Department of Rostechnadzor
# 00170701502689
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-28, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701484099
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-28, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701413075
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-03-31, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701413018
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-03-31, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701412320
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-03-31, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701434035
Unscheduled inspection
Start date: 2017-03-02, end date: 2017-03-10, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation dated 27.012016 29G3327J043
# 00170701412284
Unscheduled inspection
Start date: 2017-03-02, end date: 2017-03-13, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation dated 01122016 g 602G3327J07
# 75170701483206
Unscheduled inspection
Start date: 2017-03-23, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya Zabaikalskogo kraya
Purpose of inspection:
# 66170701355206
Unscheduled inspection
Start date: 2017-02-06, end date: 2017-03-03, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: based on the inspection program 080310210 dated 25.012017
# 66170701344253
Unscheduled inspection
Start date: 2017-02-06, end date: 2017-03-06, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: based on the inspection program 080310210 dated 25.012017
# 00170701512229
Unscheduled inspection
Start date: 2017-02-22, end date: 2017-02-22, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the fulfillment of the points of the previously issued prescription
# 00170701511007
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-02-21, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the fulfillment of the prescription
# 00170701512253
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-02-21, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the fulfillment of the points of the previously issued prescription
# 00170701399918
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-02-27, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00170701331787
Unscheduled inspection
Start date: 2017-01-23, end date: 2017-01-27, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation dated 01122016 601G3327J043
# 00160701229449
Unscheduled inspection
Start date: 2016-12-19, end date: 2016-12-21, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00160701229411
Unscheduled inspection
Start date: 2016-12-19, end date: 2016-12-21, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 00160701229349
Unscheduled inspection
Start date: 2016-12-19, end date: 2016-12-21, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance by a legal entity with the requirements of legislation on urban planning activities during the construction and reconstruction of capital construction facilities
# 74160701232508
Unscheduled inspection
Start date: 2016-12-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741600029223
Unscheduled inspection
Start date: 2016-12-29, end date: 2018-01-26, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to comply with mandatory requirements in the field of urban planning activities The tasks of inspections are to prevent identify and suppress violations in the implementation of measures to monitor compliance with the requirements of legislation on urban planning activities
# 50160701248403
Unscheduled inspection
Start date: 2016-12-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160701160067
Unscheduled inspection
Start date: 2016-12-01, end date: 2016-12-09, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 74160701070209
Unscheduled inspection
Start date: 2016-11-09, end date: 2016-11-30, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The actual condition of the object2the presence of a construction permit 3The fulfillment of the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 00160701142727
Unscheduled inspection
Start date: 2016-11-23, end date: 2016-12-01, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The list of documents required to be submitted in order to achieve the goals and objectives of the audit
# 00160701142805
Unscheduled inspection
Start date: 2016-11-23, end date: 2016-12-01, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The list of documents required to be submitted in order to achieve the goals and objectives of the audit
# 74160701051086
Unscheduled inspection
Start date: 2016-10-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160700637929
Unscheduled inspection
Start date: 2016-09-01, end date: 2016-09-06, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 18052016 g 224G3327J03
# 00160700637401
Unscheduled inspection
Start date: 2016-09-01, end date: 2016-09-06, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 18052016 g 222G3327J01
# 00160700633322
Unscheduled inspection
Start date: 2016-09-01, end date: 2016-09-06, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the order of 18052016 g 225G3327J07
# 00160700629150
Unscheduled inspection
Start date: 2016-09-01, end date: 2016-09-06, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Execution of the regulation of 18052016 g 223G3327J02
# 00160700553973
Unscheduled inspection
Start date: 2016-09-22, end date: 2016-09-23, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials with the requirements of technical regulations, other regulatory legal acts and project documentation
# 00160700554580
Unscheduled inspection
Start date: 2016-09-20, end date: 2016-09-21, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials with the requirements of technical regulations, other regulatory legal acts and project documentation
# 66160700791229
Unscheduled inspection
Start date: 2016-09-19, end date: 2016-10-14, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: In order to implement the verification program 080310210 dated 01072016
# 00160700055310
Unscheduled inspection
Start date: 2016-08-22, end date: 2016-09-02, duration: —
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development activities committed by the developer by the customer
# 74160601739359
Unscheduled inspection
Start date: 2016-07-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 14160601730415
Unscheduled inspection
Start date: 2016-07-20, end date: 2016-07-25, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: in order to verify the actual elimination during the construction of a capital construction facility of previously identified violations prescribed for elimination by regulation 5816 of June 20, 2016, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the customer as well as by the person carrying out construction on the basis of an agreement with the developer or with the customer hereinafter referred to as the contractor the purpose of this check is to note the necessary 1 compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code the Code of the Russian Federation the availability of a certificate of admission to construction and reconstruction works that affect the safety of a capital construction facility, including a certificate of admission to work on the organization of a contract of an individual or legal entity
# 00160601628418
Unscheduled inspection
Start date: 2016-05-04, end date: 2016-05-16, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken to ensure compliance by a legal entity with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, preventing the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory acts legal acts
# 00160601617064
Unscheduled inspection
Start date: 2016-05-10, end date: 2016-05-18, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken to ensure compliance by a legal entity with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, preventing the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory acts legal acts
# 00160601617050
Unscheduled inspection
Start date: 2016-05-10, end date: 2016-05-18, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken to ensure compliance by a legal entity with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, preventing the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory acts legal acts
# 00160601611125
Unscheduled inspection
Start date: 2016-05-10, end date: 2016-05-18, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken to ensure compliance by a legal entity with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, preventing the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory acts legal acts
# 00160601611105
Unscheduled inspection
Start date: 2016-05-10, end date: 2016-05-18, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken to ensure compliance by a legal entity with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, preventing the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory acts legal acts
# 52160601638045
Unscheduled inspection
Start date: 2016-04-04, end date: 2016-04-07, duration: —
Authority: VolzhskoOkskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: carrying out supervision measures provided for by the Regulation on the Implementation of State Construction Supervision in the Russian Federation approved by Decree of the Government of the Russian Federation 54 of 01022006
# 00160601530626
Unscheduled inspection
Start date: 2016-03-21, end date: 2016-03-28, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160601544221
Unscheduled inspection
Start date: 2016-02-04, end date: 2016-02-09, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken by a legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory legal acts
# 00160601544193
Unscheduled inspection
Start date: 2016-02-04, end date: 2016-02-09, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken by a legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory legal acts
# 00160601544251
Unscheduled inspection
Start date: 2016-02-04, end date: 2016-02-09, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken by a legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory legal acts
# 00160601544317
Unscheduled inspection
Start date: 2016-02-04, end date: 2016-02-09, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the measures taken by a legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban planning during the construction reconstruction of capital construction facilities, taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory legal acts
# 00150601451285
Unscheduled inspection
Start date: 2015-11-30, end date: 2015-12-21, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to comply with mandatory requirements for the construction and reconstruction of capital construction facilities
# 00150601275697
Unscheduled inspection
Start date: 2015-10-19, end date: 2015-11-16, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development