# 772101447135
Unscheduled inspection
Start date: 2021-12-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101335710
Unscheduled inspection
Start date: 2021-11-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101211250
Unscheduled inspection
Start date: 2021-10-14, end date: 2021-10-15, duration: 2
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772101123189
Unscheduled inspection
Start date: 2021-10-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100706692
Unscheduled inspection
Start date: 2021-09-13, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100559246
Unscheduled inspection
Start date: 2021-09-01, end date: 2021-09-14, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772100473262
Unscheduled inspection
Start date: 2021-08-18, end date: 2021-08-19, duration: 2
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the order issued by Mosgosstroynadzor
# 772100267930
Unscheduled inspection
Start date: 2021-06-07, end date: 2021-06-22, duration: 11
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance by the person carrying out construction with the requirements of part 3 of Article 52 of the Urban Planning Code compliance of the work and the construction materials used in the process construction, reconstruction of the capital construction facility, as well as the results of such work to the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations identified during construction control and state construction supervision of compliance of completed works with the requirements of the design documentation
# 772100206327
Unscheduled inspection
Start date: 2021-05-14, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: The audit is conducted in order to: protect the rights and interests of the employee in connection with the consideration of the appeal dated 08.04.2021 no.77/7-11267-21- On the issue of violation of labor legislation regarding non-payment of wages.
The objectives of the audit are: supervision and control over compliance with legislation and other regulatory legal acts containing labor law norms.
The subject of this audit is: - compliance with mandatory requirements and (or) requirements established by municipal legal acts; - compliance of the information contained in the notification of the commencement of certain types of business activities with the mandatory requirements; - matching information. information contained in the application and documents of a legal entity or individual entrepreneur for granting legal status, special permission (license), granting permission (approval) to mandatory requirements, as well as information about these legal entities and individual entrepreneurs contained in the unified state register of individual Entrepreneurs and other federal information resources; - compliance with the instructions of state control bodies (supervision), municipal control bodies; - carrying out measures; - to prevent harm to the life and health of citizens, harm to animals, plants, the environment, cultural heritage sites (historical and cultural monuments) of the peoples of the Russian Federation, museum objects and museum collections included in the Museum Fund of the Russian Federation, documents of special importance historical, scientific, and cultural significance, which are part of the national library fund; - to prevent the occurrence of natural and man-made emergencies; - to ensure the security of the state; - to eliminate the consequences of causing such harm.
# 772100156579
Unscheduled inspection
Start date: 2021-04-19, end date: 2021-04-23, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance by the person carrying out construction with the requirements of part 3 of Article 52 of the Urban Planning Code compliance of the work and the construction materials used in the process construction, reconstruction of the capital construction facility, as well as the results of such work to the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations identified during construction control and state construction supervision of compliance of completed works with the requirements of the design documentation
# 772100035438
Unscheduled inspection
Start date: 2021-02-20, end date: 2021-02-25, duration: 3
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the order issued by Mosgosstroynadzor
# 772100026767
Unscheduled inspection
Start date: 2021-02-20, end date: 2021-02-25, duration: 3
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the order issued by Mosgosstroynadzor
# 772105305704
Unscheduled inspection
Start date: 2021-01-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005239132
Unscheduled inspection
Start date: 2020-12-01, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772005171368
Unscheduled inspection
Start date: 2020-10-05, end date: 2020-10-16, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the inspection are to carry out control measures in connection with the implementation of the inspection program. The objectives of the inspection are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development by the person being checked. The subject of the inspection is the fulfillment by the person carrying out the construction of the requirements of part 3 of Article 52 of the Urban Planning Code. The conformity of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work requirements of the project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance with the requirements of the project documentation identified during construction control and state construction supervision
# 772004480850
Unscheduled inspection
Start date: 2020-08-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004429110
Unscheduled inspection
Start date: 2020-06-09, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772004412344
Unscheduled inspection
Start date: 2020-05-20, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77180803045295
Unscheduled inspection
Start date: 2018-01-15, end date: 2018-02-09, duration: —
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: Protection of the rights and interests of employees in connection with the receipt by the Inspectorate of an employee's appeal dated 04/122017 3724017PV regarding remuneration, registration and termination of an employment contract
# 50170701673871
Unscheduled inspection
Start date: 2017-04-24, end date: 2017-05-22, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Moskovskoi oblasti
Purpose of inspection: assessment of the activity of the license applicant for compliance with mandatory requirements on the basis of the received application for a license to the licensing authority