# 002105314487
Unscheduled inspection
Start date: 2021-01-25, end date: 2021-01-29, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: - verification of the elimination of violations of compliance of completed works with the requirements of technical regulations (norms and rules), other regulatory legal acts and project documentation identified during the implementation of state construction supervision, as well as compliance with the prohibition to proceed with the continuation of work before drawing up acts on the elimination of such violations;
- verification of compliance with the instruction of the West Ural Department of Rostechnadzor No. 35-5018-rp-25 dated 04.10.2019.
# 002105314457
Unscheduled inspection
Start date: 2021-01-25, end date: 2021-01-29, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the elimination of violations of compliance of completed works with the requirements of technical regulations (norms and rules), other regulatory legal acts and project documentation identified during the implementation of state construction supervision, as well as compliance with the prohibition to proceed with the continuation of work before drawing up acts on the elimination of such violations;
- verification of compliance with the instruction of the West Ural Department of Rostechnadzor No. 35-3141-28 dated 07.12.2020.
# 002105314470
Unscheduled inspection
Start date: 2021-01-25, end date: 2021-01-29, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: - verification of the elimination of violations of compliance of completed works with the requirements of technical regulations (norms and rules), other regulatory legal acts and project documentation identified during the implementation of state construction supervision, as well as compliance with the prohibition to proceed with the continuation of work before drawing up acts on the elimination of such violations;
- verification of compliance with the instruction of the West Ural Department of Rostechnadzor No. 35-2037-14 dated 08/21/2020.
# 002105314477
Unscheduled inspection
Start date: 2021-01-25, end date: 2021-01-29, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: - verification of the elimination of violations of compliance of completed works with the requirements of technical regulations (norms and rules), other regulatory legal acts and project documentation identified during the implementation of state construction supervision, as well as compliance with the prohibition to proceed with the continuation of work before drawing up acts on the elimination of such violations;
- verification of compliance with the instruction of the West Ural Department of Rostechnadzor No. 35-691-11 dated 03/13/2020.
# 002005269249
Unscheduled inspection
Start date: 2020-12-15, end date: 2020-12-21, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005269224
Unscheduled inspection
Start date: 2020-12-15, end date: 2020-12-21, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005232315
Unscheduled inspection
Start date: 2020-12-01, end date: 2020-12-11, duration: 9
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the work specified in paragraph 10 of the program for conducting inspections of the capital construction facility of JSC Gaisky GOK "Opening and development of mountains 8301310m underground mine" 19 this is a verification of compliance of completed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of mountains 8301310m underground mine" stage 19 as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used checking the availability of a construction permit checking compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005237019
Unscheduled inspection
Start date: 2020-11-24, end date: 2020-11-30, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005237009
Unscheduled inspection
Start date: 2020-11-24, end date: 2020-12-07, duration: 10
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005236997
Unscheduled inspection
Start date: 2020-11-24, end date: 2020-11-30, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005236978
Unscheduled inspection
Start date: 2020-11-24, end date: 2020-11-30, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005237088
Unscheduled inspection
Start date: 2020-11-24, end date: 2020-12-07, duration: 10
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005201546
Unscheduled inspection
Start date: 2020-10-26, end date: 2020-10-30, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the performance of the works specified in paragraph 2 of the Program for conducting inspections of the capital Construction facility of PJSC Gaisky GOK
# 002005201522
Unscheduled inspection
Start date: 2020-10-26, end date: 2020-10-30, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the performance of the works specified in paragraph 2 of the Program for conducting inspections of the capital Construction facility of PJSC Gaisky GOK
# 002004471400
Unscheduled inspection
Start date: 2020-08-10, end date: —, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002004479258
Unscheduled inspection
Start date: 2020-07-28, end date: 2020-08-03, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK Capital mine workings of the horizon 1150 m Central trenches 1 2 chambers, etc. without the complex of workings "VM Warehouse go1150m" Mountains 1150 m Hanging side drift Eastern Mountains 1150m Recumbent side drift Western Mountains 1150m Central ort Mountains 1150m to the shaft of the mine "Severnaya Ventilation2" as well as the results of such work to the requirements of the design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002004479240
Unscheduled inspection
Start date: 2020-07-28, end date: 2020-08-03, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK Horizon 1310 m of Workings of the trunk yards of the central yards of the central group of trunks the central UPC chamber and other chamber workings Horizon 1310 m of Workings of the pumping station of the main drainage of the Underground mine Mining Capital construction and commissioning works on capital construction facilities as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used. verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002004372803
Unscheduled inspection
Start date: 2020-04-06, end date: 2020-04-17, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, the complex for the production of condensed dump tailings of the concentrating plant for mining reclamation of quarries 1 3" Stage 1, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy used resources verification of the availability of a construction permit verification of compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002004372768
Unscheduled inspection
Start date: 2020-04-06, end date: 2020-04-08, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the elimination of violations of compliance of completed works with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation identified during the implementation of state construction supervision, as well as compliance with the prohibition to proceed with the continuation of work before drawing up acts on the elimination of such violations verification of compliance with the instruction of the West Ural Department of Rostechnadzor 355018rp25 dated 04102019
# 002004298523
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-13, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the performed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 19, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, availability of a construction permit requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002004383202
Unscheduled inspection
Start date: 2020-03-10, end date: 2020-03-20, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the performed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK installation of technological equipment as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with metering devices for energy resources used verification of compliance with the requirements of parts 23 and 3_1 of Article 52 of the Federal Law dated 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002004209640
Unscheduled inspection
Start date: 2020-02-17, end date: —, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001904114522
Unscheduled inspection
Start date: 2019-12-18, end date: 2019-12-30, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the implementation of paragraphs 3235 3739 41 with a deadline of 20112019 paragraphs 4547 with a deadline of 29112019 paragraphs 48 49 52 with a deadline of 01102019 paragraph 51 with a deadline of 01122019 previously issued regulation 33GN4219rp153 of 16092019
# 001903924555
Unscheduled inspection
Start date: 2019-11-01, end date: 2019-11-29, duration: —
Authority: Uralskoe upravlenie gosudarstvennogo zheleznodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: 1
# 001903891896
Unscheduled inspection
Start date: 2019-11-18, end date: 2019-11-29, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, a complex for the production of condensed dump tailings of an enrichment plant for mining reclamation of quarries 1 3" Stage 1, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy used verification of the availability of a construction permit verification of compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 001903810257
Unscheduled inspection
Start date: 2019-10-28, end date: —, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001903014138
Unscheduled inspection
Start date: 2019-09-23, end date: 2019-10-18, duration: —
Authority: Upravlenie gosudarstvennogo aviacionnogo nadzora i nadzora za obespecheniem transportnoi bezopasnosti po Privolzhskomu federalnomu okrugu Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: Control of the execution of the regulation from 22042019 6OR07AV19 with a deadline of 20092019
# 001902920198
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-09-13, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the performed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 19, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, availability of a construction permit requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 001902749956
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-17, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the performed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 19, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, availability of a construction permit requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 001902772072
Unscheduled inspection
Start date: 2019-06-17, end date: 2019-06-19, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of compliance of the activities or actions inaction carried out by a legal entity with the requirements established by federal laws and regulatory legal acts adopted in accordance with them in the field of safety of hydraulic structures
# 001902797004
Unscheduled inspection
Start date: 2019-05-27, end date: —, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001902690642
Unscheduled inspection
Start date: 2019-05-27, end date: 2019-05-29, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to monitor the implementation of the measures prescribed
# 001902543503
Unscheduled inspection
Start date: 2019-03-26, end date: 2019-04-22, duration: —
Authority: Upravlenie gosudarstvennogo aviacionnogo nadzora i nadzora za obespecheniem transportnoi bezopasnosti po Privolzhskomu federalnomu okrugu Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: Control of the execution of the regulation dated 29062018 6OR16AV18 with a deadline of up to 25032019
# 001902504465
Unscheduled inspection
Start date: 2019-02-11, end date: —, duration: —
Authority: Upravlenie Federalnoi sluzhby po akkreditacii po Privolzhskomu federalnomu okrugu
Purpose of inspection:
# 001801774119
Unscheduled inspection
Start date: 2018-11-13, end date: 2018-12-10, duration: —
Authority: Upravlenie gosudarstvennogo aviacionnogo nadzora i nadzora za obespecheniem transportnoi bezopasnosti po Privolzhskomu federalnomu okrugu Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: Control of the execution of the regulation dated 29062018 6OR15AV18 with a deadline of up to 12112018
# 001802115449
Unscheduled inspection
Start date: 2018-11-19, end date: 2018-12-14, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the compliance of the cylinder inspection point with the requirements of Federal Norms and Rules in the field of industrial safety "Rules for industrial safety of hazardous production facilities where pressure equipment is used" approved by order of the Federal Service for Environmental Technological and Nuclear Supervision dated 28032014 116 and verifying the completeness and reliability of the information contained in the application of PJSC Gaisky GOK 096225 dated 30102018 0724119 dated 01112018 and the materials submitted for the assignment of the cylinder branding cipher
# 001800664536
Unscheduled inspection
Start date: 2018-09-03, end date: 2018-09-07, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility "Opening and development of the 8301310m underground mine" stage 17, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 001800643885
Unscheduled inspection
Start date: 2018-09-03, end date: —, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001800201276
Unscheduled inspection
Start date: 2018-03-01, end date: 2018-03-02, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Constant supervision of the OPO of the 1st class of danger
# 001800201105
Unscheduled inspection
Start date: 2018-03-01, end date: 2018-03-02, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Constant supervision of the OPO of the 1st class of danger
# 00180803054455
Unscheduled inspection
Start date: 2018-01-17, end date: 2018-01-30, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the implementation of the previously issued instruction of the West Ural Department of Rostechnadzor 33GN955rpo080 dated 28072017 the deadline for the execution of paragraph 119 of which expired on 25102017
# 00170802922839
Unscheduled inspection
Start date: 2017-11-23, end date: —, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00170802822870
Unscheduled inspection
Start date: 2017-11-17, end date: 2017-11-30, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the fulfillment of a previously issued prescription
# 00170802449204
Unscheduled inspection
Start date: 2017-10-16, end date: —, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00170701886233
Unscheduled inspection
Start date: 2017-08-04, end date: 2017-08-08, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of paragraph 22707175 of regulation 33GN1739 rpo134 of 28102016
# 00170701845397
Unscheduled inspection
Start date: 2017-07-25, end date: 2017-07-26, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: conducting an on-site unscheduled inspection
# 00170701567139
Unscheduled inspection
Start date: 2017-04-17, end date: 2017-04-18, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the prescription
# 00170701528320
Unscheduled inspection
Start date: 2017-04-10, end date: 2017-04-21, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the fulfillment of a previously issued prescription
# 00170701448338
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-14, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00170701448337
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-14, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00170701418340
Unscheduled inspection
Start date: 2017-02-15, end date: 2017-02-22, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the implementation of a previously issued prescription
# 00160700867821
Unscheduled inspection
Start date: 2016-10-04, end date: 2016-10-06, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160700676827
Unscheduled inspection
Start date: 2016-09-12, end date: 2016-09-14, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160700867573
Unscheduled inspection
Start date: 2016-08-01, end date: 2016-08-19, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the progress of preparation of electric power and heat supply facilities for operation in the 2016-2017 OZP
# 00160601679548
Unscheduled inspection
Start date: 2016-07-12, end date: 2016-07-14, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160601650929
Unscheduled inspection
Start date: 2016-06-06, end date: 2016-06-10, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160601595345
Unscheduled inspection
Start date: 2016-05-26, end date: 2016-05-30, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160601561665
Unscheduled inspection
Start date: 2016-04-25, end date: 2016-04-27, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160601532503
Unscheduled inspection
Start date: 2016-03-14, end date: 2016-03-18, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160601460250
Unscheduled inspection
Start date: 2016-01-20, end date: 2016-01-22, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00150601318626
Unscheduled inspection
Start date: 2015-11-09, end date: 2015-11-12, duration: —
Authority: Federalnaya sluzhba po akkreditacii
Purpose of inspection: Verification of the Report of the Gaisky Mining and Processing Plant Joint Stock Company on the elimination of identified inconsistencies dated 08102015 367291 PFOvx912 dated 15102015 and documents attached to the report on the elimination of identified inconsistencies with the accreditation criteria specified in the Notification of the Federal Accreditation Service dated 26082015 3011103CN
# 00150600633838
Unscheduled inspection
Start date: 2015-09-14, end date: 2015-09-17, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00150600627997
Unscheduled inspection
Start date: 2015-09-14, end date: 2015-09-17, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 562101209006
Unscheduled inspection
Start date: 2021-10-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 562100369021
Unscheduled inspection
Start date: 2021-07-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 592100257409
Unscheduled inspection
Start date: 2021-06-17, end date: —, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, inclined exit in int. 1230-1310 m with serifs on the sub-floors of mountains. 1257 m, 1285 m (underground transport mining - for descent/ascent of self-propelled and drilling equipment, fresh air supply and emergency exit). The horizon is 1310 m. Workings of the ore zone (the western field drift in the volume of the entrance to the bunker of the DK No. 12, a complex of unloading chambers for the bunker of unbroken ore of the crushing complex No. 12 "Rudny-2" tract to the shaft of the mine "Operational")
# 592100257362
Unscheduled inspection
Start date: 2021-06-17, end date: —, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, Inclined flank exit in the range of 1310-1390 m of the Underground mine, horizon of 1390 m.
# 562100267361
Unscheduled inspection
Start date: 2021-06-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 592100198264
Unscheduled inspection
Start date: 2021-05-13, end date: —, duration: 10
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the performed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, installation of technological equipment, including individual and complex tests, NDT, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy used resources;
- verification of compliance with the requirements of Parts 2,3 and 3_1 of Article 52 of Federal Law No. 190-FZ dated December 29, 2004 "Urban Planning Code of the Russian Federation".
# 592100198228
Unscheduled inspection
Start date: 2021-05-13, end date: —, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and the applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, crushing and conveyor complex "Rock-2" tract installation of plate feeder No. 2 (heavy type) in the DZK mountain.1260 m of the Skipovaya mine shaft, check-in to the conveyor reloading chamber No.17/17a from the central turnout, arrivals to the bunkers of the unbroken rock mass of complexes No. 22 and No. 23 along the mountains of 1310 m.
- verification of compliance with the requirements of Parts 2,3 and 3_1 of Article 52 of Federal Law No. 190-FZ dated December 29, 2004 "Urban Planning Code of the Russian Federation"
# 592100174679
Unscheduled inspection
Start date: 2021-05-11, end date: —, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: - verification of the compliance of the completed works and the applied building materials during the construction of the capital construction facility of JSC Gaisky GOK. Opening and development of the mountains. 830-1310m of the underground mine" Stage 19, as well as the results of such work to the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for used energy resources;
- checking the availability of a building permit;
- verification of compliance with the requirements of Parts 2, 3 and 3_1 of Article 52 of Federal Law No. 190-FZ dated December 29, 2004 "Urban Planning Code of the Russian Federation".
# 562100309281
Unscheduled inspection
Start date: 2021-05-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 592100139587
Unscheduled inspection
Start date: 2021-04-20, end date: 2021-04-26, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and the applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, the shaft of the Skipovaya mine (the deepened part of the trunk in the range of 1070-1310 m) to otm. the horizon is 1310 m with a technical discharge to the horizons of 1075 m, 1150 m, 1230 m and 1310 m. The turnout to the shaft of the Skipovaya mine according to otm. horizon of 1310 m (purpose -cleaning of the spillage from the shaft of the Skip mine), connecting the shaft of the Skip mine with the trunk of the Kletevaya mine according to otm. the horizon is 1310 m (purpose - ventilation and emergency exit).
- verification of compliance with the requirements of Parts 2,3 and 3_1 of Article 52 of Federal Law No. 190-FZ dated December 29, 2004 "Urban Planning Code of the Russian Federation"
# 592100139381
Unscheduled inspection
Start date: 2021-04-12, end date: 2021-04-23, duration: 10
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility "Reconstruction of the underground mine of PJSC Gaisky GOK with an increase in productivity to 9 million tons per year" Stage 14 consisting of: Ruddworks of the mine shaft "Operational" according to the horizon marks of 1070m., 1150m., 1230m., as well as the results of such work to the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for used energy resources;
- availability of a building permit;
- verification of compliance with the requirements of Parts 2,3 and 3_1 of Article 52 of Federal Law No. 190-FZ dated December 29, 2004 "Urban Planning Code of the Russian Federation"
# 592100139326
Unscheduled inspection
Start date: 2021-04-12, end date: 2021-04-23, duration: 10
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used;
- availability of a building permit;
- verification of compliance with the requirements of Parts 2,3 and 3_1 of Article 52 of Federal Law No. 190-FZ dated December 29, 2004 "Urban Planning Code of the Russian Federation"
# 592100139286
Unscheduled inspection
Start date: 2021-04-12, end date: 2021-04-23, duration: 10
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility "Reconstruction of the underground mine of PJSC Gaisky GOK with an increase in productivity to 9 million tons per year" 41 stages consisting of: The shaft of the mine "Operational" in the range of mountains. 1310-1419 m, the ruddworks of the shaft of the mine "Operational" at the horizon marks of 910 m, 990 m, the shaft of the mine "Northern ventilation 2" in the range of 1230-1310 m with technical waste to the horizon of 1150 m, 1230 m and 1310, as well as the results of such work according to the requirements of design documentation, in including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used;
- availability of a building permit;
- verification of compliance with the requirements of Parts 2,3 and 3_1 of Article 52 of Federal Law No. 190-FZ dated December 29, 2004 "Urban Planning Code of the Russian Federation".
# 592100081751
Unscheduled inspection
Start date: 2021-04-26, end date: 2021-04-30, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: - verification of the compliance of the completed works and the applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK. The complex of production of condensed dump tailings of an enrichment plant for mining and technical reclamation of quarries No. 1-No. 3" Stage 1, as well as the results of such work to the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources;
- checking the availability of a building permit;
- verification of compliance with the requirements of Parts 2, 3 and 3_1 of Article 52 of Federal Law No. 190-FZ dated December 29, 2004 "Urban Planning Code of the Russian Federation".
# 562100068449
Unscheduled inspection
Start date: 2021-03-17, end date: 2021-03-24, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: This inspection is carried out for the purpose of: implementation of regional state construction supervision on the basis of the inspection program approved on 12/27/2019;
The objectives of this audit are: to identify and suppress violations of the requirements of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used, legislation on urban planning (Part 2 of Article 51, Part 2, 3, 3.1, 6 of Article 52 of the Urban Planning Code of the Russian Federation).
The subject of this audit is: compliance with the mandatory requirements of urban planning legislation; compliance of the work and construction materials used in the process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of the Urban Planning Code of the Russian Federation), including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, paragraphs 1, 6,7,8 of the inspection program dated 12/27/2019).
# 592100018433
Unscheduled inspection
Start date: 2021-03-15, end date: 2021-03-26, duration: 10
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: - verification of the compliance of the completed works and the applied building materials during the construction of the capital construction facility of JSC Gaisky GOK. Opening and development of the mountains. 830-1310m of the underground mine" Stage 19, as well as the results of such work to the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for used energy resources;
- checking the availability of a building permit;
- verification of compliance with the requirements of Parts 2, 3 and 3_1 of Article 52 of Federal Law No. 190-FZ dated December 29, 2004 "Urban Planning Code of the Russian Federation".
# 592100036242
Unscheduled inspection
Start date: 2021-03-11, end date: 2021-03-24, duration: 10
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility "Reconstruction of the underground mine of PJSC Gaisky GOK with an increase in productivity to 9 million tons per year" Stage 20 consisting of: The horizon is 1310 m. The pumping station of the main drainage (at the trunk of the Kletevaya mine), as well as the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used;
- availability of a building permit;
- verification of compliance with the requirements of Parts 2,3 and 3_1 of Article 52 of Federal Law No. 190-FZ dated December 29, 2004 "Urban Planning Code of the Russian Federation"
# 592100035842
Unscheduled inspection
Start date: 2021-03-11, end date: 2021-03-24, duration: 10
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility "Reconstruction of the underground mine of PJSC Gaisky GOK with an increase in productivity to 9 million tons per year" Stage 40 consisting of Horizon 1390 m. The pumping station of the district drainage from the pumping station "Pumpnaya" (at the trunk of the Kletevaya mine), as well as the results of such work, meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used;
- availability of a building permit;
- verification of compliance with the requirements of Parts 2,3 and 3_1 of Article 52 of Federal Law No. 190-FZ dated December 29, 2004 "Urban Planning Code of the Russian Federation".
# 592100040111
Unscheduled inspection
Start date: 2021-03-11, end date: 2021-03-17, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, Horizon 1390 m. Workings of the near-trunk yards of the central group of trunks (central turnout No. 1, turnout of the Skipovaya mine, turnout of the Kletevaya mine, turnout of the Novaya mine, turnout of the Operational mine with bypass work, chambers for various purposes, etc.) Mining, construction, installation and commissioning of the capital construction facility.;
- verification of compliance with the requirements of Parts 2,3 and 3_1 of Article 52 of Federal Law No. 190-FZ dated December 29, 2004 "Urban Planning Code of the Russian Federation"
# 562100042404
Unscheduled inspection
Start date: 2021-03-04, end date: 2021-04-01, duration: —
Authority: Upravlenie Federalnoi sluzhby gosudarstvennoi registracii, kadastra i kartografii po Orenburgskoi oblasti
Purpose of inspection: Purpose: verification of the elimination of violations of land legislation in accordance with the Order on the elimination of the identified violation of the requirements of the land legislation of the Russian Federation No. 20 dated 08/23/2018; the purpose of this audit is to ensure compliance by the Public Joint Stock Company Gaisky Mining and Processing Plant (PJSC Gaisky GOK); the subject: compliance with the instructions of state control (supervision) bodies, municipal control bodies
# 592100040081
Unscheduled inspection
Start date: 2021-03-04, end date: 2021-03-11, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, the shaft of the Exploitational mine (up to m. 1419m from the DZK mountain.1310m), construction, installation and commissioning works on the ore yards of m. mountains.990m and 1150m of the shaft of the Exploitational mine;
- verification of compliance with the requirements of Parts 2,3 and 3_1 of Article 52 of Federal Law No. 190-FZ dated December 29, 2004 "Urban Planning Code of the Russian Federation"
# 592100041300
Unscheduled inspection
Start date: 2021-02-11, end date: 2021-02-16, duration: 4
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the elimination of violations of compliance of completed works with the requirements of technical regulations (norms and rules), other regulatory legal acts and project documentation identified during the implementation of state construction supervision, as well as compliance with the prohibition to proceed with the continuation of work before drawing up acts on the elimination of such violations;
- verification of compliance with the order of the West Ural Department of Rostechnadzor No. 33GN-RP-283-1733- O-067 from 06/23/2020
# 002105314487
Unscheduled inspection
Start date: 2021-01-25, end date: 2021-01-29, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: - verification of the elimination of violations of compliance of completed works with the requirements of technical regulations (norms and rules), other regulatory legal acts and project documentation identified during the implementation of state construction supervision, as well as compliance with the prohibition to proceed with the continuation of work before drawing up acts on the elimination of such violations;
- verification of compliance with the instruction of the West Ural Department of Rostechnadzor No. 35-5018-rp-25 dated 04.10.2019.
# 002105314457
Unscheduled inspection
Start date: 2021-01-25, end date: 2021-01-29, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the elimination of violations of compliance of completed works with the requirements of technical regulations (norms and rules), other regulatory legal acts and project documentation identified during the implementation of state construction supervision, as well as compliance with the prohibition to proceed with the continuation of work before drawing up acts on the elimination of such violations;
- verification of compliance with the instruction of the West Ural Department of Rostechnadzor No. 35-3141-28 dated 07.12.2020.
# 002105314470
Unscheduled inspection
Start date: 2021-01-25, end date: 2021-01-29, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: - verification of the elimination of violations of compliance of completed works with the requirements of technical regulations (norms and rules), other regulatory legal acts and project documentation identified during the implementation of state construction supervision, as well as compliance with the prohibition to proceed with the continuation of work before drawing up acts on the elimination of such violations;
- verification of compliance with the instruction of the West Ural Department of Rostechnadzor No. 35-2037-14 dated 08/21/2020.
# 002105314477
Unscheduled inspection
Start date: 2021-01-25, end date: 2021-01-29, duration: 5
Authority: Zapadno-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: - verification of the elimination of violations of compliance of completed works with the requirements of technical regulations (norms and rules), other regulatory legal acts and project documentation identified during the implementation of state construction supervision, as well as compliance with the prohibition to proceed with the continuation of work before drawing up acts on the elimination of such violations;
- verification of compliance with the instruction of the West Ural Department of Rostechnadzor No. 35-691-11 dated 03/13/2020.
# 002005269249
Unscheduled inspection
Start date: 2020-12-15, end date: 2020-12-21, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005269224
Unscheduled inspection
Start date: 2020-12-15, end date: 2020-12-21, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005232370
Unscheduled inspection
Start date: 2020-12-01, end date: 2020-12-11, duration: 9
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the work specified in paragraph 11 of the program for conducting inspections of the capital construction facility of PJSC Gaisky GOK, the complex for the production of condensed dump tails of the concentrating plant for mining reclamation of quarries 1 3" 1 this is a verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, the complex for the production of condensed dump tails of the concentrating plant factories for carrying out mining and technical reclamation of quarries 1 3" Stage 1 as well as the results of such work to the requirements of design documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources verification of a construction permit verification of compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation Federation"
# 002005232315
Unscheduled inspection
Start date: 2020-12-01, end date: 2020-12-11, duration: 9
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the work specified in paragraph 10 of the program for conducting inspections of the capital construction facility of JSC Gaisky GOK "Opening and development of mountains 8301310m underground mine" 19 this is a verification of compliance of completed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of mountains 8301310m underground mine" stage 19 as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used checking the availability of a construction permit checking compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 562005255254
Unscheduled inspection
Start date: 2020-12-03, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection:
# 002005237019
Unscheduled inspection
Start date: 2020-11-24, end date: 2020-11-30, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005237009
Unscheduled inspection
Start date: 2020-11-24, end date: 2020-12-07, duration: 10
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005236997
Unscheduled inspection
Start date: 2020-11-24, end date: 2020-11-30, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005236978
Unscheduled inspection
Start date: 2020-11-24, end date: 2020-11-30, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002005237088
Unscheduled inspection
Start date: 2020-11-24, end date: 2020-12-07, duration: 10
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 562005253484
Unscheduled inspection
Start date: 2020-11-30, end date: 2020-12-07, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of completion of the capital construction facility dated 20112020 155727 bx dated 23112020 2717 The objectives of this inspection are to identify and suppress violations of the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used legislation on urban planning activities 2 st 51 h 2 3 31 6 st 52 h 2 4 7 st 53 of the Urban Planning Code of the Russian Federation The subject of this audit is compliance with the mandatory requirements of urban planning legislation compliance of work and construction materials used in the construction of a capital construction facility as well as the results of such work with the requirements approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation project documentation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources notice of completion of construction of the capital construction facility dated 20112020 155727 bx dated 23112020 2717
# 562005150373
Unscheduled inspection
Start date: 2020-10-01, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection:
# 002005201546
Unscheduled inspection
Start date: 2020-10-26, end date: 2020-10-30, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the performance of the works specified in paragraph 2 of the Program for conducting inspections of the capital Construction facility of PJSC Gaisky GOK
# 002005201522
Unscheduled inspection
Start date: 2020-10-26, end date: 2020-10-30, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the performance of the works specified in paragraph 2 of the Program for conducting inspections of the capital Construction facility of PJSC Gaisky GOK
# 002005201421
Unscheduled inspection
Start date: 2020-10-26, end date: 2020-10-30, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the performance of the works specified in paragraph 2 of the Program for conducting inspections of the capital construction facility of PJSC Gaisky GOK
# 002005186039
Unscheduled inspection
Start date: 2020-10-28, end date: 2020-11-06, duration: 7
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 17, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used checking the availability of a construction permit checking fulfillment of the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002004483639
Unscheduled inspection
Start date: 2020-08-19, end date: 2020-08-25, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002004471400
Unscheduled inspection
Start date: 2020-08-10, end date: 2020-08-21, duration: 10
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 19, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used checking the availability of a construction permit checking fulfillment of the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002004479258
Unscheduled inspection
Start date: 2020-07-28, end date: 2020-08-03, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK Capital mine workings of the horizon 1150 m Central trenches 1 2 chambers, etc. without the complex of workings "VM Warehouse go1150m" Mountains 1150 m Hanging side drift Eastern Mountains 1150m Recumbent side drift Western Mountains 1150m Central ort Mountains 1150m to the shaft of the mine "Severnaya Ventilation2" as well as the results of such work to the requirements of the design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002004479240
Unscheduled inspection
Start date: 2020-07-28, end date: 2020-08-03, duration: 5
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK Horizon 1310 m of Workings of the trunk yards of the central yards of the central group of trunks the central UPC chamber and other chamber workings Horizon 1310 m of Workings of the pumping station of the main drainage of the Underground mine Mining Capital construction and commissioning works on capital construction facilities as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used. verification of compliance with the requirements of Parts 23 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002004440781
Unscheduled inspection
Start date: 2020-07-02, end date: 2020-07-10, duration: 7
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, the complex for the production of condensed dump tailings of the concentrating plant for mining reclamation of quarries 1 3" Stage 1, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy used resources verification of the availability of a construction permit verification of compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 562004466465
Unscheduled inspection
Start date: 2020-07-30, end date: 2020-08-20, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with mandatory requirements of labor legislation and other regulatory legal acts containing norms of labor law receipt of notification 5667820IZ of 130720
# 562004475295
Unscheduled inspection
Start date: 2020-07-31, end date: 2020-08-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program approved on December 27, 2019. The objectives of this inspection are to identify and suppress violations of the requirements of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used legislation on urban development h 2 st 51 h 2 3 31 6 st 52 of the Urban Planning Code of the Russian Federation The subject of this audit is compliance with the mandatory requirements of urban planning legislation compliance of work and construction materials used in the process of reconstruction of a capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, paragraphs 1 to 8 of the inspection program dated 27122019
# 562004432282
Unscheduled inspection
Start date: 2020-06-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002004372803
Unscheduled inspection
Start date: 2020-04-06, end date: 2020-04-17, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, the complex for the production of condensed dump tailings of the concentrating plant for mining reclamation of quarries 1 3" Stage 1, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy used resources verification of the availability of a construction permit verification of compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 002004372768
Unscheduled inspection
Start date: 2020-04-06, end date: 2020-04-08, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the elimination of violations of compliance of completed works with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation identified during the implementation of state construction supervision, as well as compliance with the prohibition to proceed with the continuation of work before drawing up acts on the elimination of such violations verification of compliance with the instruction of the West Ural Department of Rostechnadzor 355018rp25 dated 04102019
# 562004395057
Unscheduled inspection
Start date: 2020-04-20, end date: 2020-04-30, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with mandatory requirements of labor legislation and other regulatory legal acts containing norms of labor law Written appeal of a citizen 567 3211 20 ON from 02042020
# 002004298523
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-13, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the performed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 19, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, availability of a construction permit requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 562004319366
Unscheduled inspection
Start date: 2020-03-04, end date: 2020-03-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: Implementation of regional state construction supervision on the basis of the regulation of 30012020 4007033430508p identification and suppression of violations of the requirements of design documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources legislation on urban development h 2 st 51 h 2 3 31 6 st 52 h 2 4 7 st 53 of the Urban Planning Code of the Russian Federation The subject of this inspection is the implementation of measures according to the prescription 30012020 4007033430508p
# 562004350033
Unscheduled inspection
Start date: 2020-03-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002004383202
Unscheduled inspection
Start date: 2020-03-10, end date: 2020-03-20, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the performed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK installation of technological equipment as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with metering devices for energy resources used verification of compliance with the requirements of parts 23 and 3_1 of Article 52 of the Federal Law dated 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 562004303497
Unscheduled inspection
Start date: 2020-02-25, end date: 2020-02-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: Implementation of regional state construction supervision on the basis of the inspection program the objectives of this inspection are to identify and suppress violations of the requirements of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources legislation on urban development h 2 st 51 h 2 3 31 6 st 52 h 2 4 7 st 53 The subject of this audit is the compliance of the work performed and the construction materials used in the construction of the capital construction facility as well as the results of such work with the requirements of design documentation code 0080016 positive expert opinion 66212003917 from 05072017, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used compliance with urban planning legislation h 2 st 51 h 2 3 31 6 st 52 h 2 4 7 st 53 of the Urban Planning Code of the Russian Federation
# 562004233608
Unscheduled inspection
Start date: 2020-02-10, end date: 2020-03-05, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with mandatory requirements of labor legislation and other regulatory legal acts containing norms of labor law notice 566420IZ
# 002004209640
Unscheduled inspection
Start date: 2020-02-17, end date: 2020-02-21, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the performed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 17, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, availability of a construction permit verification of compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 562004189527
Unscheduled inspection
Start date: 2020-01-30, end date: 2020-01-31, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: PROTECTION OF THE RIGHTS AND INTERESTS OF THE EMPLOYEE
# 562004202474
Unscheduled inspection
Start date: 2020-01-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002004109725
Unscheduled inspection
Start date: 2020-01-20, end date: 2020-01-31, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, the complex for the production of condensed dump tailings of the concentrating plant for mining reclamation of quarries 1 3" Stage 1, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy used verification of the availability of a construction permit verification of compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 001904068796
Unscheduled inspection
Start date: 2019-12-10, end date: 2019-12-11, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Purpose control over the implementation of paragraphs 5467 of regulation 33GN4219rp153 of 16092019 issued by the West Ural Department of Rostechnadzor of PJSC Gaisky GOK, the deadline for which expired on 16102019 Task assessment of compliance of activities or actions of omissions carried out by PJSC Gaisky GOK with the requirements established by federal laws and regulatory legal acts of the Russian Federation adopted in accordance with them in the field of industrial safety, subject to verification of compliance with the regulations of state bodies Control supervision
# 001904114522
Unscheduled inspection
Start date: 2019-12-18, end date: 2019-12-30, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the implementation of paragraphs 3235 3739 41 with a deadline of 20112019 paragraphs 4547 with a deadline of 29112019 paragraphs 48 49 52 with a deadline of 01102019 paragraph 51 with a deadline of 01122019 previously issued regulation 33GN4219rp153 of 16092019
# 001903924555
Unscheduled inspection
Start date: 2019-11-01, end date: 2019-11-29, duration: —
Authority: Uralskoe upravlenie gosudarstvennogo zheleznodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: 1
# 561903872832
Unscheduled inspection
Start date: 2019-11-05, end date: 2019-11-08, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: PROTECTION OF THE RIGHTS AND INTERESTS OF THE EMPLOYEE
# 561903874145
Unscheduled inspection
Start date: 2019-11-07, end date: 2019-11-08, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: PROTECTION OF THE RIGHTS AND INTERESTS OF THE EMPLOYEE
# 561903873947
Unscheduled inspection
Start date: 2019-11-07, end date: 2019-11-08, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: PROTECTION OF THE RIGHTS AND INTERESTS OF THE EMPLOYEE
# 001903891896
Unscheduled inspection
Start date: 2019-11-18, end date: 2019-11-29, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, a complex for the production of condensed dump tailings of an enrichment plant for mining reclamation of quarries 1 3" Stage 1, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy used verification of the availability of a construction permit verification of compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 561903700260
Unscheduled inspection
Start date: 2019-10-01, end date: 2019-10-03, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: Implementation of regional state construction supervision on the basis of the notice of the beginning of construction dated 17092019 155225 the objectives of this audit are to identify and suppress violations of the requirements of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used legislation on urban development h 2 st 51 h 2 3 31 6 st 52 of the Urban Planning Code Russian Federation
# 561903852415
Unscheduled inspection
Start date: 2019-10-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001903810257
Unscheduled inspection
Start date: 2019-10-28, end date: 2019-11-08, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the completed construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m mountains of the underground mine" 16 This is a verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m mountains of the underground mine" stage 16 as well as the results of such work with the requirements of technical regulations of project documentation in including the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, verification of compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 001903651686
Unscheduled inspection
Start date: 2019-10-07, end date: 2019-10-11, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the performed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 17, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, availability of a construction permit verification of compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 561903810454
Unscheduled inspection
Start date: 2019-10-08, end date: 2019-10-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: implementation of regional state construction supervision on the basis of a notice of completion of construction of a capital construction facility dated 01102019 155443 identification and suppression of violations of the requirements of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used legislation on urban development h 2 st 51 h 2 3 31 6 st 52 h 2 4 7 article 53 of the Urban Planning Code of the Russian Federation compliance of completed works with the requirements of design documentation code 011800000 positive expert opinions 562120000022019 from 07032019 562120000132019 from 21082019, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used compliance with urban planning legislation h 2 st 51 h 2 3 31 6 st 52 h 2 4 7 st 53 The Urban Planning Code of the Russian Federation
# 561903157171
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-10-11, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: PROTECTION OF THE RIGHTS AND INTERESTS OF THE EMPLOYEE
# 001903014138
Unscheduled inspection
Start date: 2019-09-23, end date: 2019-10-18, duration: —
Authority: Upravlenie gosudarstvennogo aviacionnogo nadzora i nadzora za obespecheniem transportnoi bezopasnosti po Privolzhskomu federalnomu okrugu Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: Control of the execution of the regulation from 22042019 6OR07AV19 with a deadline of 20092019
# 001903168707
Unscheduled inspection
Start date: 2019-09-23, end date: 2019-10-04, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of PJSC Gaisky GOK, a complex for the production of condensed dump tailings of an enrichment plant for mining reclamation of quarries 1 3" Stage 1, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy used verification of the availability of a construction permit verification of compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 001905217951
Unscheduled inspection
Start date: 2019-09-24, end date: 2019-09-26, duration: 3
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to comply with the Order of the West Ural Department of the Federal Service for Environmental Technological and Nuclear Supervision "On checking the readiness of municipalities for the heating period 20192020" dated 16092019 1119PR The tasks of this audit are to verify the compliance of the activities of the audited local governments with regulatory legal acts of the Russian Federation in the field of preparation for the heating period. The subject of this audit is compliance with mandatory requirements
# 561903011207
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-09-13, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: compliance with the requirements of labor legislation
# 001902920198
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-09-13, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the performed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 19, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, availability of a construction permit requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 561902933396
Unscheduled inspection
Start date: 2019-08-08, end date: 2019-08-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: implementation of regional state construction supervision on the basis of the inspection program approved on 11012019 the objectives of this audit are to identify and suppress violations of the requirements of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used legislation on urban development h 2 st 51 h 2 3 31 6 st 52 h 2 4 7 article 53 of the Urban Planning Code of the Russian Federation Compliance of the work and construction materials used in the construction of the capital construction facility as well as the results of such work with the requirements of project documentation code 0080016 positive expert opinion 66212003917 from 05072017, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used compliance with urban planning legislation h 2 st 51 h 2 3 31 6 st 52 h 2 4 7 st 53 of the Urban Planning Code of the Russian Federation inspection programs
# 561902916778
Unscheduled inspection
Start date: 2019-07-31, end date: 2019-08-02, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Orenburgskoi oblasti
Purpose of inspection: this inspection is carried out in order to monitor the implementation of the regulation GPN 1011 of 28062018 on the elimination of violations of fire safety requirements on carrying out measures to ensure fire safety at protection facilities and to prevent the threat of fire, the objectives of this inspection are to verify compliance by organizations and citizens with fire safety requirements. The subject of this inspection is to comply with the instructions of state control bodies supervision of municipal control bodies
# 001902819497
Unscheduled inspection
Start date: 2019-07-15, end date: 2019-07-25, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the performed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 17, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, availability of a construction permit verification of compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 001902749956
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-17, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the performed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 19, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, availability of a construction permit requirements of Parts 2 3 and 3_1 of Article 52 of the Federal Law of 29122004 190FZ "Urban Planning Code of the Russian Federation"
# 561902801714
Unscheduled inspection
Start date: 2019-06-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001902772072
Unscheduled inspection
Start date: 2019-06-17, end date: 2019-06-19, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of compliance of the activities or actions inaction carried out by a legal entity with the requirements established by federal laws and regulatory legal acts adopted in accordance with them in the field of safety of hydraulic structures
# 561902750691
Unscheduled inspection
Start date: 2019-06-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001902797004
Unscheduled inspection
Start date: 2019-05-27, end date: 2019-06-05, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: It is carried out in order to monitor the implementation of paragraphs 1 3 4 722 2427 of regulation 33GN1084rp038 of 29032019
# 001902690642
Unscheduled inspection
Start date: 2019-05-27, end date: 2019-05-29, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to monitor the implementation of the measures prescribed
# 561902621317
Unscheduled inspection
Start date: 2019-04-12, end date: 2019-04-30, duration: —
Authority: Upravlenie Federalnoi sluzhby po veterinarnomu i fitosanitarnomu nadzoru po Orenburgskoi oblasti
Purpose of inspection: this audit is conducted in order to establish and eliminate the identified violations according to the order dated August 02, 2018 560503339 the deadline for the execution of the order is April 01, 2019. The subject of this audit is the fulfillment of the order of the state land supervision authority. The objectives of this audit are to prevent, identify and suppress violations by a legal entity of the requirements established by the legislation of the Russian Federation in the field of state land supervision
# 561902621279
Unscheduled inspection
Start date: 2019-04-19, end date: 2019-04-30, duration: —
Authority: Upravlenie Federalnoi sluzhby po veterinarnomu i fitosanitarnomu nadzoru po Orenburgskoi oblasti
Purpose of inspection: this audit is conducted in order to establish and eliminate the violations identified according to the order dated August 02, 2018 560503340 the deadline for the execution of the order is April 01, 2019. The subject of this audit is the fulfillment of the order of the state land supervision authority. The objectives of this audit are to prevent, identify and suppress violations by a legal entity of the requirements established by the legislation of the Russian Federation in the field of state land supervision
# 001902580135
Unscheduled inspection
Start date: 2019-04-01, end date: 2019-04-12, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the work specified in paragraph 2 of the program for conducting inspections of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" Stage 19 prevention detection and suppression of violations of the legislation on urban development, including technical regulations, committed by the developer, the customer, as well as by persons carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor and design documentation verification of compliance of completed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 19, as well as the results of such work with the requirements of technical regulations of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used verification compliance with the requirements of Parts 2 and 3 of Article 52 of the Federal Law of 29122004 190 FZ "Urban Planning Code of the Russian Federation"
# 001902580128
Unscheduled inspection
Start date: 2019-04-01, end date: 2019-04-12, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the work specified in paragraph 4 of the program for conducting inspections of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 17 prevention detection and suppression of violations of the legislation on urban development, including technical regulations, committed by the developer, the customer, as well as by persons carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor and project documentation verification of compliance of the completed works and applied building materials during the construction of the capital construction facility of JSC Gaisky GOK "Opening and development of the 8301310m underground mine" stage 17, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources verification compliance with the requirements of Parts 2 and 3 of Article 52 of the Federal Law of 29122004 190 FZ "Urban Planning Code of the Russian Federation"
# 561902621335
Unscheduled inspection
Start date: 2019-04-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001902543503
Unscheduled inspection
Start date: 2019-03-26, end date: 2019-04-22, duration: —
Authority: Upravlenie gosudarstvennogo aviacionnogo nadzora i nadzora za obespecheniem transportnoi bezopasnosti po Privolzhskomu federalnomu okrugu Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: Control of the execution of the regulation dated 29062018 6OR16AV18 with a deadline of up to 25032019
# 561902508198
Unscheduled inspection
Start date: 2019-03-04, end date: 2019-03-05, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: Ensuring the observance and protection of the labor rights and freedoms of citizens, including the right to safe working conditions
# 001902504465
Unscheduled inspection
Start date: 2019-02-11, end date: 2019-03-11, duration: —
Authority: Upravlenie Federalnoi sluzhby po akkreditacii po Privolzhskomu federalnomu okrugu
Purpose of inspection: in order to verify the Report of the Gaisky Mining and Processing Plant Public Joint Stock Company on the elimination of identified inconsistencies dated 29122018 372 dated 18012019 PFO119 and the documents attached to the report on the elimination of identified inconsistencies with the accreditation criteria specified in the Notification of the Federal Accreditation Agency for the Volga Federal District dated 14012019 PFO79YUD, the objectives of this audit are to ensure compliance with the requirements of the legislation of the Russian Federation in the field of accreditation, including Federal Law No. 412FZ dated 28122013 "On Accreditation in the National Accreditation System" of the Order of the Ministry of Economic Development of the Russian Federation dated 30052014 326 "On Approval of Accreditation Criteria for a list of documents confirming the applicant's compliance with the Accredited Person's accreditation criteria and a list of documents in the field of standardization, compliance with the requirements of which by applicants accredited persons ensures their compliance with the accreditation criteria" The subject of this audit is compliance with mandatory requirements or requirements compliance by an accredited person with the mandatory requirements of the legislation of the Russian Federation for the activities of accredited persons established by municipal legal acts in the course of carrying out activities
# 561902498755
Unscheduled inspection
Start date: 2019-02-25, end date: 2019-02-28, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: Ensuring the observance and protection of the labor rights and freedoms of citizens, including the right to safe working conditions
# 561802336446
Unscheduled inspection
Start date: 2018-12-24, end date: 2018-12-25, duration: —
Authority: Ministerstvo obrazovaniya Orenburgskoi oblasti
Purpose of inspection: The purpose of the check is to control the execution by the object of the check of the instruction on the elimination of violations The task of the check is to establish the fact of execution of non-fulfillment of the instruction on the elimination of violations The subject of the check is the execution of the instruction on the elimination of violations
# 001802129538
Unscheduled inspection
Start date: 2018-12-10, end date: 2018-12-12, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Article 10 of Federal Law 294FZ of 26122008 "On the Protection of the Rights of Legal Entities and Individual Entrepreneurs in the exercise of State Control supervision and Municipal Control" Article 13 of Federal Law 21071997 117FZ "On the Safety of Hydraulic Structures" paragraph 5319 of the Regulations on the Federal Service for Environmental Technological and Nuclear Supervision approved by Decree of the Government of the Russian Federation of 30072004 401 verification of compliance with the regulation
# 001802381875
Unscheduled inspection
Start date: 2018-12-17, end date: 2018-12-21, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the fulfillment of the prescription
# 001801774119
Unscheduled inspection
Start date: 2018-11-13, end date: 2018-12-10, duration: —
Authority: Upravlenie gosudarstvennogo aviacionnogo nadzora i nadzora za obespecheniem transportnoi bezopasnosti po Privolzhskomu federalnomu okrugu Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: Control of the execution of the regulation dated 29062018 6OR15AV18 with a deadline of up to 12112018
# 001802115449
Unscheduled inspection
Start date: 2018-11-19, end date: 2018-12-14, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the compliance of the cylinder inspection point with the requirements of Federal Norms and Rules in the field of industrial safety "Rules for industrial safety of hazardous production facilities where pressure equipment is used" approved by order of the Federal Service for Environmental Technological and Nuclear Supervision dated 28032014 116 and verifying the completeness and reliability of the information contained in the application of PJSC Gaisky GOK 096225 dated 30102018 0724119 dated 01112018 and the materials submitted for the assignment of the cylinder branding cipher
# 001800664570
Unscheduled inspection
Start date: 2018-09-03, end date: 2018-09-07, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of completed works and applied building materials during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 001800664536
Unscheduled inspection
Start date: 2018-09-03, end date: 2018-09-07, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance of the completed works and applied building materials during the construction of the capital construction facility "Opening and development of the 8301310m underground mine" stage 17, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 001800643885
Unscheduled inspection
Start date: 2018-09-03, end date: 2018-09-06, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prescription control
# 561800617536
Unscheduled inspection
Start date: 2018-08-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 561800507576
Unscheduled inspection
Start date: 2018-07-05, end date: 2018-08-01, duration: —
Authority: Upravlenie Federalnoi sluzhby po veterinarnomu i fitosanitarnomu nadzoru po Orenburgskoi oblasti
Purpose of inspection: this check is carried out in order to establish the elimination of the identified violations according to the order 27072017 560503232 the deadline for the execution of the order is 01072018 The subject of this check is the fulfillment of the instructions of the state land supervision authorities
# 561800524161
Unscheduled inspection
Start date: 2018-07-20, end date: 2018-07-25, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: Federal State supervision of compliance with labor legislation
# 001800374682
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-06-22, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by persons carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, verification of compliance of completed works and applied building materials during the construction of the capital construction facility "Opening and development of the 8301310m underground mine" 17 stage a also, the results of such work meet the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 561800495144
Unscheduled inspection
Start date: 2018-06-05, end date: 2018-07-03, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Orenburgskoi oblasti
Purpose of inspection: The inspection is carried out in order to monitor the implementation of the order GPN 1611 of 19062017 on the elimination of violations of fire safety requirements on carrying out measures to ensure fire safety at protection facilities and to prevent the threat of fire The objectives of this inspection are to verify compliance by organizations and citizens with fire safety requirements The subject of this inspection is the fulfillment of the instructions of state control bodies supervision of municipal control bodies
# 561800456693
Unscheduled inspection
Start date: 2018-06-08, end date: 2018-06-29, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Orenburgskoi oblasti
Purpose of inspection: This audit is conducted in order to establish the facts of compliance with the regulations of 17112016 PNV2523 PNV2525 on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements The objectives of this audit are to confirm the facts of compliance with the regulations of 17112016 PNV2522 PNV2523 the expiration date of which is 01062018 The subject of this audit is the implementation of the regulations of state control supervision bodies
# 561800369804
Unscheduled inspection
Start date: 2018-05-25, end date: 2018-05-31, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: Consideration of the appeal
# 001800250635
Unscheduled inspection
Start date: 2018-04-09, end date: 2018-05-08, duration: —
Authority: Privolzhskoe mezhregionalnoe territorialnoe upravlenie Federalnogo agentstva po tehnicheskomu regulirovaniyu i metrologii
Purpose of inspection: Assessment of the fulfillment of the Prescription from 250717g 55 in connection with the expiration of the deadline for completing the Task assessment of the conformity of measurements with established requirements The subject of verification compliance with mandatory requirements compliance with regulations
# 561800229653
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-20, duration: —
Authority: Upravlenie Federalnoi sluzhby po veterinarnomu i fitosanitarnomu nadzoru po Orenburgskoi oblasti
Purpose of inspection: The inspection is carried out in order to establish the elimination of identified violations according to the order dated June 02, 2017 560503169 the deadline for the execution of the order until 01042017 The subject of the inspection is the fulfillment of the order of the state land supervision authority The objectives of this inspection are to prevent identify and suppress violations of the requirements established by the land legislation of the Russian Federation
# 561800321404
Unscheduled inspection
Start date: 2018-04-25, end date: 2018-05-25, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Orenburgskoi oblasti
Purpose of inspection: Objectives execution of the order of the Federal Service for Supervision of Consumer Rights Protection and Human Welfare dated 15012018 10 "On conducting unscheduled on-site inspections of children's recreation and recreation organizations in 2018" in accordance with the instruction of the Government of the Russian Federation dated 27122017 OGP128751 in accordance with paragraph 3 h 2 st 10 of the Federal Law of the Russian Federation dated December 26, 2008 g 294 "On the protection of the rights of legal entities and individual entrepreneurs in the implementation of state control supervision of municipal control Tasks supervision and control over the implementation of mandatory requirements of the legislation of the Russian Federation in the field of ensuring sanitary and epidemiological welfare of the population Subject compliance with mandatory requirements
# 561800325603
Unscheduled inspection
Start date: 2018-04-28, end date: 2018-05-18, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Orenburgskoi oblasti
Purpose of inspection: Compliance with the regulation of 08122017 PNE3031
# 001800242776
Unscheduled inspection
Start date: 2018-03-13, end date: 2018-03-15, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Permanent state supervision
# 001800243272
Unscheduled inspection
Start date: 2018-03-14, end date: 2018-03-15, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Permanent state supervision
# 001800201276
Unscheduled inspection
Start date: 2018-03-01, end date: 2018-03-02, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Constant supervision of the OPO of the 1st class of danger
# 001800201105
Unscheduled inspection
Start date: 2018-03-01, end date: 2018-03-02, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Constant supervision of the OPO of the 1st class of danger
# 561800215530
Unscheduled inspection
Start date: 2018-03-28, end date: 2018-04-02, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: Federal State supervision of compliance with labor legislation and other regulatory legal acts containing norms of labor law compliance with mandatory requirements and or requirements established by municipal legal acts
# 561800069797
Unscheduled inspection
Start date: 2018-02-07, end date: 2018-03-07, duration: —
Authority: Upravlenie Federalnoi sluzhby gosudarstvennoi registracii kadastra i kartografii po Orenburgskoi oblasti
Purpose of inspection: Purpose verification of the elimination of violations of land legislation in accordance with the Order on the elimination of the identified violation of the requirements of the land legislation of the Russian Federation 2017 dated 18072017 the purpose of this audit is to ensure compliance of LLC Gaisky Mining and Processing Plant with land legislation requirements for the protection and use of land subject to compliance with the instructions of state control bodies supervision of municipal control bodies
# 00180803054455
Unscheduled inspection
Start date: 2018-01-17, end date: 2018-01-30, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the implementation of the previously issued instruction of the West Ural Department of Rostechnadzor 33GN955rpo080 dated 28072017 the deadline for the execution of paragraph 119 of which expired on 25102017
# 001800069058
Unscheduled inspection
Start date: 2018-01-22, end date: 2018-01-24, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of a previously issued prescription
# 56170802906905
Unscheduled inspection
Start date: 2017-11-24, end date: 2017-12-08, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Orenburgskoi oblasti
Purpose of inspection: This audit is carried out within the framework of state environmental supervision and unscheduled measures to comply with the requirements of environmental legislation in order to establish the facts of compliance with the regulations of 17112016 PNE2521 PNE2522 PNE2523 on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements The purpose of this audit is to confirm compliance with the regulations on the elimination of violations of legislation in the field of environmental protection of 17112016 PNE2521 PNE2522 PNE2523 The subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 00170802922839
Unscheduled inspection
Start date: 2017-11-23, end date: 2017-11-24, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the prescription
# 00170802822870
Unscheduled inspection
Start date: 2017-11-17, end date: 2017-11-30, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the fulfillment of a previously issued prescription
# 56170802823979
Unscheduled inspection
Start date: 2017-11-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 56170802823863
Unscheduled inspection
Start date: 2017-11-14, end date: —, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Orenburgskoi oblasti
Purpose of inspection:
# 00170802449204
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-10-20, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00170802782835
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-29, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the progress of preparation for work in the OSP 2017-2018
# 00170701886233
Unscheduled inspection
Start date: 2017-08-04, end date: 2017-08-08, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of paragraph 22707175 of regulation 33GN1739 rpo134 of 28102016
# 00170701845397
Unscheduled inspection
Start date: 2017-07-25, end date: 2017-07-26, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: conducting an on-site unscheduled inspection
# 56170701751549
Unscheduled inspection
Start date: 2017-06-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 56170701642214
Unscheduled inspection
Start date: 2017-05-25, end date: 2017-06-22, duration: —
Authority: Upravlenie Federalnoi sluzhby gosudarstvennoi registracii kadastra i kartografii po Orenburgskoi oblasti
Purpose of inspection: Legal grounds for conducting an audit of Article 71, paragraph 6, Article 711 of the Land Code of the Russian Federation, Article 10 of the Federal Law No. 294 FZ dated December 26, 2008 "On the Protection of the Rights of Legal Entities and Individual Entrepreneurs in the exercise of State Control supervision and Municipal Control"The purpose of confirming the facts of identifying signs of violations of the requirements of the legislation of the Russian Federation based on the results of an administrative survey of an object of land relations Of the Russian Federation for which the legislation of the Russian Federation provides for administrative and other responsibility act of administrative inspection of the object of land relations from 05052017 representation on the appointment of an unscheduled inspection of compliance with land legislation from 10052017 031439198 Task ensuring compliance of PJSC Gaisky GOK with land legislation requirements for the protection and use of land
# 56170701592376
Unscheduled inspection
Start date: 2017-05-03, end date: 2017-05-16, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Orenburgskoi oblasti
Purpose of inspection: This audit is carried out in order to establish the facts of compliance with the regulation of 17112016 PNE2524 on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements The purpose of this audit is to confirm the facts of compliance with the regulation of 17112016 PNE2524 The subject of this audit is to comply with the regulations of state control and supervision bodies
# 00170701567139
Unscheduled inspection
Start date: 2017-04-17, end date: 2017-04-18, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the prescription
# 00170701528320
Unscheduled inspection
Start date: 2017-04-10, end date: 2017-04-21, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the fulfillment of a previously issued prescription
# 00170701448338
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-14, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00170701448337
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-14, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00170701448360
Unscheduled inspection
Start date: 2017-03-13, end date: 2017-03-24, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00170701418340
Unscheduled inspection
Start date: 2017-02-15, end date: 2017-02-22, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the implementation of a previously issued prescription
# 00170701334510
Unscheduled inspection
Start date: 2017-02-06, end date: 2017-02-08, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 56160700992378
Unscheduled inspection
Start date: 2016-10-17, end date: 2016-11-14, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Orenburgskoi oblasti
Purpose of inspection: implementation of the regulation of 12052016 PNH96
# 00160700867821
Unscheduled inspection
Start date: 2016-10-04, end date: 2016-10-06, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160700676827
Unscheduled inspection
Start date: 2016-09-12, end date: 2016-09-14, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160700867573
Unscheduled inspection
Start date: 2016-08-01, end date: 2016-08-19, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the progress of preparation of electric power and heat supply facilities for operation in the 2016-2017 OZP
# 56160601746430
Unscheduled inspection
Start date: 2016-08-01, end date: 2016-08-05, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: protection of the rights and interests of the employee
# 00160601679548
Unscheduled inspection
Start date: 2016-07-12, end date: 2016-07-14, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160601650929
Unscheduled inspection
Start date: 2016-06-06, end date: 2016-06-10, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160601595351
Unscheduled inspection
Start date: 2016-05-26, end date: 2016-05-30, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160601595345
Unscheduled inspection
Start date: 2016-05-26, end date: 2016-05-30, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160601561665
Unscheduled inspection
Start date: 2016-04-25, end date: 2016-04-27, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 56160601557176
Unscheduled inspection
Start date: 2016-04-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160601557227
Unscheduled inspection
Start date: 2016-03-09, end date: 2016-03-30, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the fulfillment of points of a previously issued prescription
# 00160601571116
Unscheduled inspection
Start date: 2016-03-21, end date: 2016-03-29, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: for the implementation of previously issued regulations
# 00160601532503
Unscheduled inspection
Start date: 2016-03-14, end date: 2016-03-18, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160601460260
Unscheduled inspection
Start date: 2016-01-20, end date: 2016-01-22, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00160601460250
Unscheduled inspection
Start date: 2016-01-20, end date: 2016-01-22, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 56150601340913
Unscheduled inspection
Start date: 2015-11-09, end date: 2015-12-04, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Orenburgskoi oblasti
Purpose of inspection: control over the execution of the regulation on the elimination of violations of established requirements and measures in the field of civil defense 3 dated 25042014
# 00150601318626
Unscheduled inspection
Start date: 2015-11-09, end date: 2015-11-12, duration: —
Authority: Federalnaya sluzhba po akkreditacii
Purpose of inspection: Verification of the Report of the Gaisky Mining and Processing Plant Joint Stock Company on the elimination of identified inconsistencies dated 08102015 367291 PFOvx912 dated 15102015 and documents attached to the report on the elimination of identified inconsistencies with the accreditation criteria specified in the Notification of the Federal Accreditation Service dated 26082015 3011103CN
# 00150601271071
Unscheduled inspection
Start date: 2015-10-05, end date: 2015-10-07, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the readiness for the OPP
# 00150600213905
Unscheduled inspection
Start date: 2015-09-07, end date: 2015-09-11, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the implementation of the previously issued regulation 33GN687pr0302015 of 23032015
# 00150600633838
Unscheduled inspection
Start date: 2015-09-14, end date: 2015-09-17, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development
# 00150600627997
Unscheduled inspection
Start date: 2015-09-14, end date: 2015-09-17, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance with the requirements of Federal legislation in the field of urban development