# 002005292049
Unscheduled inspection
Start date: 2020-12-25, end date: 2020-12-25, duration: 1
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this check is carried out in order to control the execution by a legal entity of a previously issued prescription. The task of this check is to eliminate the facts of compliance with the previously issued prescription. The subject of this check is the execution of an instruction to eliminate identified violations
# 001902631405
Unscheduled inspection
Start date: 2019-03-20, end date: —, duration: —
Authority: VolzhskoOkskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001902578871
Unscheduled inspection
Start date: 2019-03-20, end date: 2019-03-26, duration: —
Authority: VolzhskoOkskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of monitoring the implementation by a legal entity of paragraph 1 of the previously issued instruction of the Volga Region Department of Rostechnadzor dated July 17, 2018 PR113018P is to carry out state control supervision over compliance with industrial safety requirements and comply with the instructions of the state control supervision body
# 001802415228
Unscheduled inspection
Start date: 2018-11-01, end date: 2018-12-12, duration: —
Authority: VolzhskoOkskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation by a legal entity of paragraphs 2 3 6 of the previously issued regulation of the Volga Region Department of Rostechnadzor dated 17072018 PR113018P Tasks implementation of state control supervision over compliance with industrial safety requirements Subject to the implementation of the regulation of the state control supervision body
# 001802414518
Unscheduled inspection
Start date: 2018-09-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160700894963
Unscheduled inspection
Start date: 2016-09-28, end date: 2016-10-25, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Tverskoi oblasti
Purpose of inspection: to establish the fulfillment of the instruction on the elimination of the detected violation
# 00160601662390
Unscheduled inspection
Start date: 2016-06-08, end date: 2016-07-01, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Tverskoi oblasti
Purpose of inspection: Verification of compliance with the requirements of the Water Code of the Russian Federation for the implementation of regulation 36331512015 of
# 00150601308562
Unscheduled inspection
Start date: 2015-11-05, end date: —, duration: —
Authority: FGKU Specialnoe upravlenie FPS 3 MCHS Rossii
Purpose of inspection: verification of the fulfillment of the previously issued instruction on the elimination of violations of fire safety requirements 1491166 dated 29082014
# 00150600814609
Unscheduled inspection
Start date: 2015-09-01, end date: 2015-10-05, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Tverskoi oblasti
Purpose of inspection: Establishment of compliance of economic activity with the requirements of the Water Code of the Russian Federation
# 772100246778
Unscheduled inspection
Start date: 2021-06-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100246728
Unscheduled inspection
Start date: 2021-06-03, end date: —, duration: 3
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This check is carried out in order to control the execution of a previously issued prescription by a legal entity. The purpose of this check is to eliminate the facts of fulfillment /non-fulfillment of a previously issued prescription. The subject of this audit is the execution of the order to eliminate the identified violations.
# 772100246679
Unscheduled inspection
Start date: 2021-06-03, end date: —, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 772100246569
Unscheduled inspection
Start date: 2021-06-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100244015
Unscheduled inspection
Start date: 2021-06-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100175597
Unscheduled inspection
Start date: 2021-05-11, end date: —, duration: 11
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the performed works with the mandatory requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility; the task of this check is to prevent, identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on on the basis of an agreement with a developer or a technical customer, violations of legislation on urban planning, including design documentation, requirements for energy conservation and energy efficiency improvement;
The subject of this review is:compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the design documentation in accordance with Parts 3.8 and 3.9 of Article 49 of the Urban Planning Code Of the Russian Federation) and (or) an information model, including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices for used energy resources;
availability of a building permit;
compliance with the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 772100182583
Unscheduled inspection
Start date: 2021-04-19, end date: —, duration: 1
Authority: Centralnoe Mezhregionalnoe upravlenie gosudarstvennogo avtodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: State supervision in the field of motor transport and urban ground electric transport, dated 08.11.2007 N 259-FZ
# 772100135029
Unscheduled inspection
Start date: 2021-04-12, end date: 2021-04-16, duration: 5
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This check is carried out in order to control the execution by a legal entity of a previously issued prescription. The purpose of this check is to eliminate the facts of fulfillment /non-fulfillment of a previously issued prescription. The subject of this audit is the execution of the order to eliminate the identified violations
# 002105326655
Unscheduled inspection
Start date: 2021-01-28, end date: 2021-02-10, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the compliance of the work performed with the mandatory requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources and other regulatory legal acts. The purpose of this audit is to prevent, identify and suppress violations of legislation on urban development, including project documentation, requirements for energy conservation and energy efficiency improvement, committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of a contract with the developer or the technical customer. The subject of this review is: compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used; availability of a construction permit; compliance with the requirements established by parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code Of the Russian Federation
# 002005252607
Unscheduled inspection
Start date: 2020-12-07, end date: 2020-12-15, duration: 7
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipment of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made in the design documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of the article 52 of the Urban Planning Code of the Russian Federation
# 002005237545
Unscheduled inspection
Start date: 2020-12-07, end date: 2020-12-28, duration: 18
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in accordance with the notice of completion of construction reconstruction of the capital construction facility in order to control the compliance of the completed works with the mandatory requirements of the design documentation requirements for energy conservation and energy efficiency improvement and other regulatory legal acts during the construction of the capital construction facility the task of this inspection is to prevent identify and suppress the mistakes made by the developer the technical customer as well as the person carrying out construction on the basis of an agreement with a developer or a technical customer for violations of legislation on urban planning activities, including design documentation requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements approved in accordance with parts 15 152 and 153 of Article 48 of this Urban Planning Code project documentation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of this Code and or the information model, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used
# 002005292049
Unscheduled inspection
Start date: 2020-12-25, end date: 2020-12-25, duration: 1
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this check is carried out in order to control the execution by a legal entity of a previously issued prescription. The task of this check is to eliminate the facts of compliance with the previously issued prescription. The subject of this check is the execution of an instruction to eliminate identified violations
# 002005203028
Unscheduled inspection
Start date: 2020-10-30, end date: 2020-11-18, duration: 13
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004492023
Unscheduled inspection
Start date: 2020-08-20, end date: 2020-09-02, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipment of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made in the design documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of the article 52 of the Urban Planning Code of the Russian Federation
# 002004442795
Unscheduled inspection
Start date: 2020-07-02, end date: 2020-07-15, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004436758
Unscheduled inspection
Start date: 2020-06-08, end date: 2020-06-18, duration: 9
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004294083
Unscheduled inspection
Start date: 2020-03-10, end date: 2020-03-20, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004248307
Unscheduled inspection
Start date: 2020-02-03, end date: 2020-02-21, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used for construction, compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004232760
Unscheduled inspection
Start date: 2020-02-10, end date: 2020-02-28, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used for construction, compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004169628
Unscheduled inspection
Start date: 2020-01-09, end date: 2020-01-24, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004170117
Unscheduled inspection
Start date: 2020-01-20, end date: 2020-01-31, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 501904188319
Unscheduled inspection
Start date: 2019-12-18, end date: 2019-12-31, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Moskovskoi oblasti
Purpose of inspection: Purpose implementation of measures according to the instruction of the Ministry of Emergency Situations of the Russian Federation in the Moscow region 6 dated 05032019 to eliminate violations established in the field of civil defense Task control over the previously issued instruction of the Ministry of Emergency Situations of the Russian Federation in the Moscow region dated 05032019 6 to eliminate violations of established requirements and measures in the field of civil defense Subject to the fulfillment of instructions from state control bodies supervision bodies of municipal control
# 501904130780
Unscheduled inspection
Start date: 2019-12-18, end date: 2019-12-31, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Moskovskoi oblasti
Purpose of inspection: Purpose implementation of measures according to the instruction of the Ministry of Emergency Situations of the Russian Federation in the Moscow region 6 dated 05032019 to eliminate violations of established requirements in the field of civil defense Tasks control over the previously issued instruction of the Ministry of Emergency Situations of the Russian Federation in the Moscow region dated 05032019 6 to eliminate violations of established requirements and measures in the field of civil defense
# 001903931219
Unscheduled inspection
Start date: 2019-11-07, end date: 2019-11-26, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used for construction, compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001903805965
Unscheduled inspection
Start date: 2019-10-14, end date: 2019-10-30, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used for construction, compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902988724
Unscheduled inspection
Start date: 2019-09-13, end date: 2019-09-30, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used for construction, compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902983333
Unscheduled inspection
Start date: 2019-09-13, end date: 2019-09-30, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used for construction, compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902824594
Unscheduled inspection
Start date: 2019-07-09, end date: 2019-07-29, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902771166
Unscheduled inspection
Start date: 2019-06-06, end date: 2019-06-20, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902771147
Unscheduled inspection
Start date: 2019-06-06, end date: 2019-06-20, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902686980
Unscheduled inspection
Start date: 2019-05-16, end date: 2019-05-29, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902613005
Unscheduled inspection
Start date: 2019-04-04, end date: 2019-04-17, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902612841
Unscheduled inspection
Start date: 2019-04-04, end date: 2019-04-17, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902631405
Unscheduled inspection
Start date: 2019-03-20, end date: 2019-03-26, duration: —
Authority: VolzhskoOkskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation by a legal entity of paragraph 1 of the previously issued instruction of the Volga Region Department of Rostechnadzor dated July 17, 2018 pr113018P The task is to carry out state control supervision over compliance with industrial safety requirements The subject is to comply with the instruction of the state control supervision body
# 001902578871
Unscheduled inspection
Start date: 2019-03-20, end date: 2019-03-26, duration: —
Authority: VolzhskoOkskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of monitoring the implementation by a legal entity of paragraph 1 of the previously issued instruction of the Volga Region Department of Rostechnadzor dated July 17, 2018 PR113018P is to carry out state control supervision over compliance with industrial safety requirements and comply with the instructions of the state control supervision body
# 501902482612
Unscheduled inspection
Start date: 2019-02-25, end date: 2019-03-11, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Moskovskoi oblasti
Purpose of inspection: Monitoring of previously issued regulations to eliminate violations of established requirements and measures in the field of civil defense
# 001902498909
Unscheduled inspection
Start date: 2019-01-21, end date: 2019-01-31, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902742193
Unscheduled inspection
Start date: 2019-01-23, end date: 2019-01-23, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: establishing the facts of the fulfillment of the non-fulfillment of the previously issued instruction on the elimination of identified violations
# 001802415228
Unscheduled inspection
Start date: 2018-11-01, end date: 2018-12-12, duration: —
Authority: VolzhskoOkskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation by a legal entity of paragraphs 2 3 6 of the previously issued regulation of the Volga Region Department of Rostechnadzor dated 17072018 PR113018P Tasks implementation of state control supervision over compliance with industrial safety requirements Subject to the implementation of the regulation of the state control supervision body
# 001802414518
Unscheduled inspection
Start date: 2018-09-28, end date: 2018-10-08, duration: —
Authority: VolzhskoOkskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of monitoring the fulfillment by a legal entity of paragraphs 4 5 7 8 of the previously issued order of the Volga Region Department of Rostechnadzor dated 17072018 PR113018P The task is to carry out state control supervision over compliance with industrial safety requirements and comply with the instructions of the state control supervision body
# 501800363009
Unscheduled inspection
Start date: 2018-06-04, end date: 2018-06-11, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Moskovskoi oblasti
Purpose of inspection: Monitoring of previously issued regulations to eliminate violations of established requirements and measures in the field of civil defense
# 50170802920098
Unscheduled inspection
Start date: 2017-11-27, end date: 2017-12-01, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the fulfillment of the order dated 27102017 0845014900502 due date until 17112017
# 50170701883494
Unscheduled inspection
Start date: 2017-06-29, end date: 2017-06-29, duration: —
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection: protection of the rights and interests of employees
# 50170701883286
Unscheduled inspection
Start date: 2017-06-26, end date: 2017-06-26, duration: —
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection: protection of the rights and interests of employees
# 50170701883412
Unscheduled inspection
Start date: 2017-06-25, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection:
# 50170701883592
Unscheduled inspection
Start date: 2017-06-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160700894963
Unscheduled inspection
Start date: 2016-09-28, end date: 2016-10-25, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Tverskoi oblasti
Purpose of inspection: to establish the fulfillment of the instruction on the elimination of the detected violation
# 50160700069024
Unscheduled inspection
Start date: 2016-09-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160601662390
Unscheduled inspection
Start date: 2016-06-08, end date: 2016-07-01, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Tverskoi oblasti
Purpose of inspection: Verification of compliance with the requirements of the Water Code of the Russian Federation for the implementation of regulation 36331512015 of
# 00150601308562
Unscheduled inspection
Start date: 2015-11-05, end date: —, duration: —
Authority: FGKU Specialnoe upravlenie FPS 3 MCHS Rossii
Purpose of inspection: verification of the fulfillment of the previously issued instruction on the elimination of violations of fire safety requirements 1491166 dated 29082014
# 00150600814609
Unscheduled inspection
Start date: 2015-09-01, end date: 2015-10-05, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Tverskoi oblasti
Purpose of inspection: Establishment of compliance of economic activity with the requirements of the Water Code of the Russian Federation