# 00170701565985
Unscheduled inspection
Start date: 2017-04-17, end date: 2017-04-21, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control and supervision of the execution of the previously issued regulation 4321201218122830475996110128135141 dated 01062016
# 001702410392
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-04-03, duration: —
Authority: Privolzhskoe mezhregionalnoe territorialnoe upravlenie Federalnogo agentstva po tehnicheskomu regulirovaniyu i metrologii
Purpose of inspection: In order to assess the fulfillment of the previously issued instruction No. 54m dated May 26, 2016, due to the expiration of its execution on March 01, 2017, the objectives of this audit are to assess the compliance of measurements performed in the field of state regulation to ensure the uniformity of measurements with established requirements. The subject of this audit is the fulfillment of the instructions of the state control and supervision bodies
# 00170701438206
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-04-03, duration: —
Authority: Privolzhskoe mezhregionalnoe territorialnoe upravlenie Federalnogo agentstva po tehnicheskomu regulirovaniyu i metrologii
Purpose of inspection: assessment of the fulfillment of the previously issued order dated May 26, 2016 54m in connection with the expiration of its execution on March 01, 2017
# 00160701260724
Unscheduled inspection
Start date: 2016-12-15, end date: 2017-01-18, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Respublike Tatarstan
Purpose of inspection: confirmation of the fulfillment of regulation 3673 dated 06062016 issued following the results of an audit of JSC Tatavtodor conducted in compliance with the orders of Farit Yusupovich Khairutdinov, Head of the Federal Service for Supervision of Natural Resources in the Republic of Tatarstan, 393 dated 29042015, acting Head of the Rosprirodnadzor Department for the Republic of Tatarstan, Lilia Akhatovna Gainutdinova 429 dated 13052016 to the act of inspection by the state control authority for the supervision of a legal entity persons 367 from 06062016
# 00160701032149
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used based on the Inspection notice dated 04102016 8703 on the completion dates that are subject to verification at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 00160701032121
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used based on the Inspection notice dated 04102016 8707 on the completion dates that are subject to verification at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 00160701032105
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notice dated 04102016 8705 on the completion dates that are subject to verification. at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 00160701032085
Unscheduled inspection
Start date: 2016-10-25, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 00160701032057
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notice dated 04102016 8704 on the completion dates that are subject to verification. at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 00160701051954
Unscheduled inspection
Start date: 2016-10-26, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 00160701051828
Unscheduled inspection
Start date: 2016-10-26, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 00160701051908
Unscheduled inspection
Start date: 2016-10-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160701051871
Unscheduled inspection
Start date: 2016-10-26, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the notice received by the Inspectorate dated 17102016 9206 on the completion dates that are subject to verification At the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this audit is to comply with mandatory requirements
# 00160700937926
Unscheduled inspection
Start date: 2016-10-04, end date: 2016-10-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notice dated 22092016 8278 on the completion dates that are subject to verification. at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 162101188138
Unscheduled inspection
Start date: 2021-10-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162101243920
Unscheduled inspection
Start date: 2021-10-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162101219173
Unscheduled inspection
Start date: 2021-10-21, end date: —, duration: 7
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works, the construction materials used in the process of reconstruction of the capital construction facility, and the results of such work with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 09/10/2021 case No. 19-04-2019/0054. The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is: compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 162100730172
Unscheduled inspection
Start date: 2021-09-16, end date: —, duration: 7
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 06/11/2021 case No. 19-04-2019/0040.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation.
The subject of this audit is: compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 162100692428
Unscheduled inspection
Start date: 2021-09-13, end date: —, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine the compliance of the completed works, the construction materials used in the process of reconstruction of the capital construction facility, and the results of such work with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 06/16/2021 case No. 19-04-2019/0046.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements and/or requirements established by municipal legal acts.;
# 162100576174
Unscheduled inspection
Start date: 2021-09-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100575781
Unscheduled inspection
Start date: 2021-09-08, end date: —, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the completed works, the construction materials used in the process of reconstruction of the capital construction facility, and the results of such work with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 02/26/2020 case No. 19-04-2020/0005.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is (select the appropriate one):
compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 162100905531
Unscheduled inspection
Start date: 2021-09-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100845796
Unscheduled inspection
Start date: 2021-09-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100844416
Unscheduled inspection
Start date: 2021-09-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100529755
Unscheduled inspection
Start date: 2021-08-24, end date: —, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 01/31/2020 case No. 19-04-2019/0059.
The objectives of this audit are:
prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 162100535033
Unscheduled inspection
Start date: 2021-08-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100359407
Unscheduled inspection
Start date: 2021-07-19, end date: —, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 05/18/2021 case No. 19-04-2019/0047.
The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts.
# 162100359442
Unscheduled inspection
Start date: 2021-07-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100337697
Unscheduled inspection
Start date: 2021-07-12, end date: —, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the completed works, the construction materials used in the process of reconstruction of the capital construction facility, and the results of such work with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/24/2021 case No. 19-04-2020/0028.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is: compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 162100344220
Unscheduled inspection
Start date: 2021-07-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100361178
Unscheduled inspection
Start date: 2021-07-27, end date: —, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 01/31/2020 case No. 19-04-2019/0059.
The objectives of this audit are:
prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 162100361047
Unscheduled inspection
Start date: 2021-07-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100360821
Unscheduled inspection
Start date: 2021-07-27, end date: —, duration: 19
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 07.10.2020 case No. 19-04-2020/0027.
The objectives of this audit are:
prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 162100360400
Unscheduled inspection
Start date: 2021-07-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100358790
Unscheduled inspection
Start date: 2021-07-21, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the completed works, the construction materials used in the process of reconstruction of the capital construction facility, and the results of such work with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 02/26/2020 case No. 19-04-2020/0005.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is (select the appropriate one):
compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 162100358741
Unscheduled inspection
Start date: 2021-07-21, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162100291254
Unscheduled inspection
Start date: 2021-06-16, end date: —, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 05/18/2021 case No. 19-04-2019/0048.
The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation.The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts.
# 162100280772
Unscheduled inspection
Start date: 2021-06-15, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 08/03/2020 case No.19-04-2019/0031.
The objectives of this audit are:
prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation.
The subject of this audit is (select the appropriate one):
compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 162100314641
Unscheduled inspection
Start date: 2021-06-28, end date: —, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 06/11/2021 case No. 19-04-2019/0040.
The objectives of this audit are:
prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation.
The subject of this audit is: compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 162100291296
Unscheduled inspection
Start date: 2021-06-28, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 05/21/2021 case No. 19-04-2020/0010.
The objectives of this audit are:
prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation.
The subject of this audit is: compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 162100291210
Unscheduled inspection
Start date: 2021-06-28, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works, the construction materials used in the process of reconstruction of the capital construction facility, and the results of such work with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 04/29/2021 case No. 19-04-2019/0044.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is: compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 162100290862
Unscheduled inspection
Start date: 2021-06-21, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162100303404
Unscheduled inspection
Start date: 2021-06-22, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine the compliance of the completed works, the construction materials used in the process of reconstruction of the capital construction facility, and the results of such work with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 06/16/2021 case No. 19-04-2019/0046.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements and/or requirements established by municipal legal acts.;
# 162100198016
Unscheduled inspection
Start date: 2021-05-11, end date: —, duration: 13
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/24/2021 case No. 19-04-2020/0028.
The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this review is:
☑ compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 162100244031
Unscheduled inspection
Start date: 2021-05-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100244093
Unscheduled inspection
Start date: 2021-05-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100244178
Unscheduled inspection
Start date: 2021-05-27, end date: —, duration: 12
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 07.10.2020 case No. 19-04-2020/0027.
The objectives of this audit are:
prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 162100243439
Unscheduled inspection
Start date: 2021-05-27, end date: —, duration: 7
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 05/18/2021 case No. 19-04-2019/0048.
The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts.
# 162100239772
Unscheduled inspection
Start date: 2021-05-27, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162100218113
Unscheduled inspection
Start date: 2021-05-20, end date: —, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine the compliance of the completed works, the construction materials used in the process of reconstruction of the capital construction facility, and the results of such work with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 04/29/2021 case No. 19-04-2019/0044.
The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.The subject of this audit is: compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 162005260131
Unscheduled inspection
Start date: 2020-12-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162005224476
Unscheduled inspection
Start date: 2020-11-16, end date: 2020-11-27, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 01102020 case 190420200041 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation
# 162005224393
Unscheduled inspection
Start date: 2020-11-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162005209464
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-12-04, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 02072020 case 190420190044the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations and other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out reconstruction on the basis of a contract with the developer or the customer with the requirements of technical regulations and other regulatory legal acts and project documentation. The purpose of this inspection is to comply with mandatory requirements and or requirements established by municipal legal acts. acts
# 162005209586
Unscheduled inspection
Start date: 2020-11-09, end date: 2020-11-10, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the Inspection notice dated 28102020 11963 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the regulation from 09102020 1912023901 to 09112020PREDMET The purpose of this audit is to comply with the instructions of the state control and supervision bodies of the municipal control bodies
# 162005209516
Unscheduled inspection
Start date: 2020-11-11, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162005178364
Unscheduled inspection
Start date: 2020-10-19, end date: 2020-10-30, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such works, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 14072020 case 190420190040 The objectives of this audit are to prevent, identify and suppress violations of compliance with the requirements of technical regulations other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of the work performed during the construction of the capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation The subject of this audit is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162005141300
Unscheduled inspection
Start date: 2020-10-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162005196468
Unscheduled inspection
Start date: 2020-10-26, end date: 2020-11-13, duration: 15
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 07102020 case 190420190048 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162005191035
Unscheduled inspection
Start date: 2020-10-21, end date: 2020-11-02, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 07102020 case 190420200027 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162005151384
Unscheduled inspection
Start date: 2020-10-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162005202795
Unscheduled inspection
Start date: 2020-10-06, end date: 2020-11-02, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: Implementation of federal State supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms Letter from the law enforcement agency 164101620PV dated 24092020
# 162005172983
Unscheduled inspection
Start date: 2020-10-08, end date: 2020-10-16, duration: 7
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 01102020 case 190420200041 Objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162005168451
Unscheduled inspection
Start date: 2020-10-08, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162005172098
Unscheduled inspection
Start date: 2020-10-12, end date: 2020-10-16, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 03082020 case 190420200011 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation
# 162004470251
Unscheduled inspection
Start date: 2020-08-03, end date: 2020-08-10, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 02042020 case 190420200011 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004470118
Unscheduled inspection
Start date: 2020-08-03, end date: 2020-08-14, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 22062020 case 190420200012 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004486817
Unscheduled inspection
Start date: 2020-08-20, end date: 2020-08-31, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 02072020 case 190420190044 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004490693
Unscheduled inspection
Start date: 2020-08-19, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004489409
Unscheduled inspection
Start date: 2020-08-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004490228
Unscheduled inspection
Start date: 2020-08-18, end date: 2020-08-27, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program of 27072020 case 190420200027 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004490200
Unscheduled inspection
Start date: 2020-08-18, end date: 2020-08-28, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program of 13042020 case 190420200013 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004486815
Unscheduled inspection
Start date: 2020-08-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004486811
Unscheduled inspection
Start date: 2020-08-18, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004516825
Unscheduled inspection
Start date: 2020-08-31, end date: 2020-09-04, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 03082020 case 190420200011 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004515614
Unscheduled inspection
Start date: 2020-08-31, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004479108
Unscheduled inspection
Start date: 2020-08-10, end date: 2020-08-14, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 03082020 case 190420190031 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004475985
Unscheduled inspection
Start date: 2020-08-10, end date: 2020-08-21, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 03072020 case 190420190028 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004475975
Unscheduled inspection
Start date: 2020-08-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004475972
Unscheduled inspection
Start date: 2020-08-10, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004444551
Unscheduled inspection
Start date: 2020-07-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004444541
Unscheduled inspection
Start date: 2020-07-06, end date: 2020-07-17, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipment of capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 13082019 case 190420190040 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004446450
Unscheduled inspection
Start date: 2020-07-08, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004457576
Unscheduled inspection
Start date: 2020-07-20, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004461381
Unscheduled inspection
Start date: 2020-07-22, end date: 2020-08-05, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 31.012020 case 190420190059 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004461379
Unscheduled inspection
Start date: 2020-07-22, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004446373
Unscheduled inspection
Start date: 2020-07-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004444538
Unscheduled inspection
Start date: 2020-07-13, end date: 2020-07-17, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 06092019 case 190420190020 The objectives of this inspection are to prevent, identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer with the requirements of the mandatory requirements and or requirements established by the municipal legal acts
# 162004444544
Unscheduled inspection
Start date: 2020-07-15, end date: 2020-07-17, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 270-52020 case 190420190054 The objectives of this inspection are to prevent, identify and suppress violations of compliance with the requirements of technical regulations other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of the work performed during the construction of the capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation The subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004423782
Unscheduled inspection
Start date: 2020-06-04, end date: 2020-06-16, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 270-52020 case 190420190054 The objectives of this inspection are to prevent, identify and suppress violations of compliance with the requirements of technical regulations other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of the work performed during the construction of the capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation The subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004423778
Unscheduled inspection
Start date: 2020-06-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004436205
Unscheduled inspection
Start date: 2020-06-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004436171
Unscheduled inspection
Start date: 2020-06-22, end date: 2020-06-30, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 13082019 case 190420190039 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004435954
Unscheduled inspection
Start date: 2020-06-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004436060
Unscheduled inspection
Start date: 2020-06-22, end date: 2020-06-26, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 20042020 case 190420190046 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004421138
Unscheduled inspection
Start date: 2020-06-01, end date: 2020-06-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 26022020 case 190420200005 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004442376
Unscheduled inspection
Start date: 2020-06-30, end date: 2020-07-15, duration: 11
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 28042020 case 190420190028 The objectives of this inspection are to prevent, identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer with the requirements of the mandatory requirements and or requirements established by the municipal legal acts
# 162004429062
Unscheduled inspection
Start date: 2020-06-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004429053
Unscheduled inspection
Start date: 2020-06-15, end date: 2020-06-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipment of capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 13082019 case 190420190040 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004429052
Unscheduled inspection
Start date: 2020-06-15, end date: 2020-06-30, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipment of capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 07052020 case 190420190044 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004428968
Unscheduled inspection
Start date: 2020-06-15, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004428986
Unscheduled inspection
Start date: 2020-06-15, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004403690
Unscheduled inspection
Start date: 2020-05-07, end date: 2020-05-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 20042020 case 190420190046 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004411307
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-06-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such works, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 13042020 case 190420200013 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004410154
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-05-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 02042020 case 190420200011 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004407611
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-06-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such works, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 24042020 case 190420200015 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004407609
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-06-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections from 14042020 case 190420190048 The objectives of this audit are to prevent, identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer with the requirements of mandatory requirements and or requirements established by the municipal legal acts
# 162004407604
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-06-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 21042020 case 190420190047 The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004407602
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-06-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 28042020 case 190420190028 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004410076
Unscheduled inspection
Start date: 2020-05-22, end date: 2020-05-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 13042020 case 190420200012 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004404313
Unscheduled inspection
Start date: 2020-05-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004403706
Unscheduled inspection
Start date: 2020-05-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004410148
Unscheduled inspection
Start date: 2020-05-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004410123
Unscheduled inspection
Start date: 2020-05-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004411306
Unscheduled inspection
Start date: 2020-05-20, end date: 2020-06-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 31.012020 case 190420190059 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004279444
Unscheduled inspection
Start date: 2020-02-17, end date: 2020-02-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 20012020 case 190420190031 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 161904036658
Unscheduled inspection
Start date: 2019-12-04, end date: 2019-12-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 13082019 case 190420190039the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out reconstruction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161904036506
Unscheduled inspection
Start date: 2019-12-04, end date: 2019-12-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 08112019 case 190420190031 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161904090896
Unscheduled inspection
Start date: 2019-12-12, end date: 2019-12-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 08112019 case 190420190059 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161904086011
Unscheduled inspection
Start date: 2019-12-16, end date: 2020-01-20, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms reasoned representation of an official of the State Labor Inspectorate 16367719PV dated 15112019
# 161903994027
Unscheduled inspection
Start date: 2019-11-22, end date: 2019-12-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such works, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 13082019 case 190420190040 The tasks of this audit are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this audit is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161903919893
Unscheduled inspection
Start date: 2019-11-07, end date: 2019-11-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 06092019 case 190420190020the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 161903932699
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 03092019 case 190420190046the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 161903931570
Unscheduled inspection
Start date: 2019-11-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903920294
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 04102019 case 190420190054 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161903949190
Unscheduled inspection
Start date: 2019-11-18, end date: 2019-11-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such works, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program of 21082019 case 190420190044 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161903853724
Unscheduled inspection
Start date: 2019-10-21, end date: 2019-11-01, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the order dated 19072019 1912009801, the deadline for which expired on 07102019, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations and other regulatory documents performed during the construction of a capital construction facility. The subject of this audit is to select the necessary compliance with the mandatory requirements and or requirements established by municipal legal acts, compliance with the instructions of state control bodies, supervision bodies of municipal control
# 161903871701
Unscheduled inspection
Start date: 2019-10-22, end date: 2019-11-01, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program of 26072019 case 190420190034 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 161903774981
Unscheduled inspection
Start date: 2019-10-04, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161903705601
Unscheduled inspection
Start date: 2019-10-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903893131
Unscheduled inspection
Start date: 2019-10-30, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161903866896
Unscheduled inspection
Start date: 2019-10-31, end date: 2019-10-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the order dated 20092019 1912017601, the deadline for which expired on 18102019, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations of compliance by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations and other regulatory documents performed during the construction of a capital construction facility. legal acts and project documentation
# 161903816181
Unscheduled inspection
Start date: 2019-10-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903705465
Unscheduled inspection
Start date: 2019-10-14, end date: 2019-10-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 28082019 case 190420190047 The tasks of this audit are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this audit is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161903705258
Unscheduled inspection
Start date: 2019-10-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903847803
Unscheduled inspection
Start date: 2019-10-15, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161903847557
Unscheduled inspection
Start date: 2019-10-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903847192
Unscheduled inspection
Start date: 2019-10-15, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161903841679
Unscheduled inspection
Start date: 2019-10-15, end date: 2019-10-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 04102019 case 190420190054 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161903327938
Unscheduled inspection
Start date: 2019-09-11, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161903328607
Unscheduled inspection
Start date: 2019-09-11, end date: 2019-09-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipment of capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 22072019 case 190420190033 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161903323247
Unscheduled inspection
Start date: 2019-09-11, end date: 2019-09-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 24042019 case 190420190006the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161902951439
Unscheduled inspection
Start date: 2019-09-16, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161902951609
Unscheduled inspection
Start date: 2019-09-16, end date: 2019-09-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 15072019 case 190420190031 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation
# 161903527400
Unscheduled inspection
Start date: 2019-09-16, end date: 2019-09-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 28082019 case 190420190047 The tasks of this audit are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this audit is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161903524353
Unscheduled inspection
Start date: 2019-09-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903523436
Unscheduled inspection
Start date: 2019-09-16, end date: 2019-09-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 02082019 case 191120180016the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation7 carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation7the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161903463889
Unscheduled inspection
Start date: 2019-09-16, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161903560999
Unscheduled inspection
Start date: 2019-09-17, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161903544295
Unscheduled inspection
Start date: 2019-09-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903621160
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-10-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 03092019 case 190420190046the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 161903591349
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-09-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 13082019 case 190420190039the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out reconstruction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161903092080
Unscheduled inspection
Start date: 2019-09-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903591341
Unscheduled inspection
Start date: 2019-09-23, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161903532638
Unscheduled inspection
Start date: 2019-09-23, end date: 2019-10-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 02092019 case 190420190048the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out the reconstruction on the basis of a contract with the developer or the customer. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161903629632
Unscheduled inspection
Start date: 2019-09-24, end date: 2019-09-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such works, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 13082019 case 190420190040 The tasks of this audit are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this audit is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161903629462
Unscheduled inspection
Start date: 2019-09-24, end date: 2019-09-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 26072019 case 190420190034the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 161903276950
Unscheduled inspection
Start date: 2019-09-06, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161903313502
Unscheduled inspection
Start date: 2019-09-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903313333
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-09-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 28082019 case 190420190047 The tasks of this audit are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this audit is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161903208564
Unscheduled inspection
Start date: 2019-09-09, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161903208142
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-09-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 31072019 case 190420190004the tasks of this audit are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this audit is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161903208382
Unscheduled inspection
Start date: 2019-09-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903207923
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-09-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules for determining the fact of execution of the order, as well as for the purpose of drawing up an act on the elimination of violations of the order based on the notice received by the Inspectorate from 23082019 7704 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which were ordered to be eliminated within the time limit set by the order from 02082019 1912011001 to 26082019 and the expiration of the order from 02082019 1912011001, the deadline for which expired on 26082019the objectives of this audit are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and design documentation. Documentationthe subject of this audit is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts, compliance with the instructions of state control bodies, supervision bodies of municipal control
# 161902965690
Unscheduled inspection
Start date: 2019-08-19, end date: 2019-08-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 22072019 case 190420190033 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902965639
Unscheduled inspection
Start date: 2019-08-20, end date: 2019-08-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 05082019 case 191120180031 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161902965195
Unscheduled inspection
Start date: 2019-08-20, end date: 2019-08-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The program of inspections dated 23052019 case 190420190020the objectives of this audit are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility. The subject of this audit is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 161902964930
Unscheduled inspection
Start date: 2019-08-20, end date: 2019-09-03, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such works, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 06052019 case 190420190015 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161902979066
Unscheduled inspection
Start date: 2019-08-26, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161902979216
Unscheduled inspection
Start date: 2019-08-26, end date: 2019-09-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 13082019 case 190420190040the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 161902865845
Unscheduled inspection
Start date: 2019-08-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902915447
Unscheduled inspection
Start date: 2019-08-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902915498
Unscheduled inspection
Start date: 2019-08-07, end date: 2019-08-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the Inspection notice dated 26072019 6474 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the regulation from 18072019 1912009501 to 19082019 The objectives of this audit are to prevent as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this audit is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts. regulations of state control bodies, supervision of municipal control bodies
# 161902757895
Unscheduled inspection
Start date: 2019-07-31, end date: 2019-08-02, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 24042019 case 190420190012the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161902838650
Unscheduled inspection
Start date: 2019-07-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902837578
Unscheduled inspection
Start date: 2019-07-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902863310
Unscheduled inspection
Start date: 2019-07-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902863255
Unscheduled inspection
Start date: 2019-07-15, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161902839868
Unscheduled inspection
Start date: 2019-07-15, end date: 2019-07-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 17052019 case 190420190016the objectives of this audit are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility, the subject of this audit is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902847166
Unscheduled inspection
Start date: 2019-07-23, end date: 2019-07-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 03092018 case 191120180029the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation
# 161902825981
Unscheduled inspection
Start date: 2019-07-01, end date: 2019-07-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 24052019 case 191120180043the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer.
# 161902885061
Unscheduled inspection
Start date: 2019-07-24, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161902836638
Unscheduled inspection
Start date: 2019-07-02, end date: 2019-07-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipment of capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 08052019 case 191120180040 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161902835133
Unscheduled inspection
Start date: 2019-07-02, end date: 2019-07-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 08052019 case 191120180031the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 161902864842
Unscheduled inspection
Start date: 2019-07-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902848942
Unscheduled inspection
Start date: 2019-07-09, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161902837661
Unscheduled inspection
Start date: 2019-07-08, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161902837085
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-07-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections from 10062019 case 190420190010 The tasks of this audit are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this audit is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902836420
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-07-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 03062019 case 191120180033the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902759821
Unscheduled inspection
Start date: 2019-06-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902757765
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 04102018 case 191120180033the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of a capital construction facility. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902746566
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program of 26092018 case 191120180016 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation
# 161902790135
Unscheduled inspection
Start date: 2019-06-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902764113
Unscheduled inspection
Start date: 2019-06-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902757962
Unscheduled inspection
Start date: 2019-06-17, end date: 2019-06-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 23052019 case 190420190004the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 161902789798
Unscheduled inspection
Start date: 2019-06-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902757844
Unscheduled inspection
Start date: 2019-06-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902757632
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-07-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 17052019 case 190420190016the objectives of this inspection are to prevent, identify and prevent violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer with the requirements of technical regulations and other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts. acts
# 161902759198
Unscheduled inspection
Start date: 2019-06-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902746461
Unscheduled inspection
Start date: 2019-06-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902789958
Unscheduled inspection
Start date: 2019-06-27, end date: 2019-07-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 06052019 case 190420190015 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161902689246
Unscheduled inspection
Start date: 2019-05-15, end date: 2019-06-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 24042019 case 190420190006 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161902698268
Unscheduled inspection
Start date: 2019-05-13, end date: 2019-05-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 22042019 case 190420190004 The objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out the reconstruction on the basis of a contract with the developer or the customer of the work performed during the construction of the capital construction facility. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902698163
Unscheduled inspection
Start date: 2019-05-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902698382
Unscheduled inspection
Start date: 2019-05-20, end date: 2019-05-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such works, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 22042019 case 190420190004 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902698088
Unscheduled inspection
Start date: 2019-05-20, end date: 2019-05-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 04102018 case 191120180033 The objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, carried out during the construction of the capital construction facility. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902709668
Unscheduled inspection
Start date: 2019-05-23, end date: 2019-05-29, duration: —
Authority: Glavnoe upravlenie veterinarii Kabineta Ministrov Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to carry out the function of control in the field of veterinary medicine and comply with regulation 13040003 of 22042019, which expires on 22052019. The objectives of this inspection are to comply with the requirements of veterinary legislation and to prevent violations of legislation in the field of veterinary medicine
# 161902721710
Unscheduled inspection
Start date: 2019-05-27, end date: 2019-06-11, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 08052019 case 191120180040the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 161902721535
Unscheduled inspection
Start date: 2019-05-27, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161802332398
Unscheduled inspection
Start date: 2018-12-24, end date: 2018-12-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 11122018 case 191120180043
# 161802138964
Unscheduled inspection
Start date: 2018-11-21, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161802150343
Unscheduled inspection
Start date: 2018-11-28, end date: 2018-11-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 13112018 case 191120180043
# 161802047791
Unscheduled inspection
Start date: 2018-11-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161802050399
Unscheduled inspection
Start date: 2018-11-08, end date: 2018-11-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules for determining the fact of execution of the order, as well as for the purpose of drawing up an act on the elimination of violations of the order based on the notice received by the Inspectorate from 18102018 7822 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by by the order from 23082018 1919013901 to 31102018 and the expiration of the period of execution of the order from 23082018 1919013902, the period of execution of which expired on 31102018
# 161802095512
Unscheduled inspection
Start date: 2018-11-30, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161802050204
Unscheduled inspection
Start date: 2018-11-14, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161801944063
Unscheduled inspection
Start date: 2018-10-22, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161801944009
Unscheduled inspection
Start date: 2018-10-22, end date: 2018-10-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 04102018 case 191120180033, the objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is to select the necessary compliance with mandatory requirements and or the requirements established by municipal legal acts
# 161801915986
Unscheduled inspection
Start date: 2018-10-22, end date: 2018-10-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 27072018 case 191120180031, the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161801753212
Unscheduled inspection
Start date: 2018-10-01, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161801750846
Unscheduled inspection
Start date: 2018-10-01, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161801750286
Unscheduled inspection
Start date: 2018-10-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161801715407
Unscheduled inspection
Start date: 2018-10-01, end date: 2018-10-11, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 11092018 case 191120180021
# 161801715350
Unscheduled inspection
Start date: 2018-10-01, end date: 2018-10-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 22082018 case 191120180014
# 161801880595
Unscheduled inspection
Start date: 2018-10-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161801881284
Unscheduled inspection
Start date: 2018-10-08, end date: 2018-10-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 17052018 case 191120180017the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out reconstruction on the basis of a contract with the developer or the customer. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161801879141
Unscheduled inspection
Start date: 2018-10-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161802002422
Unscheduled inspection
Start date: 2018-10-31, end date: 2018-11-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 03092018 case 191120180029
# 161801880806
Unscheduled inspection
Start date: 2018-10-15, end date: 2018-10-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 12092018 case 191120180040, the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 161801914989
Unscheduled inspection
Start date: 2018-10-16, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161801559889
Unscheduled inspection
Start date: 2018-09-19, end date: 2018-09-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 25072018 case 191120180010, the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161801123350
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-09-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 31082018 case 191120180037, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer. The subject of this inspection is to select the necessary compliance with mandatory requirements and or the requirements established by municipal legal acts
# 161801595684
Unscheduled inspection
Start date: 2018-09-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161801587858
Unscheduled inspection
Start date: 2018-09-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161801588244
Unscheduled inspection
Start date: 2018-09-24, end date: 2018-09-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 31082018 case 191120180037, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer. The subject of this inspection is to select the necessary compliance with mandatory requirements and or the requirements established by municipal legal acts
# 161801660877
Unscheduled inspection
Start date: 2018-09-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161801082862
Unscheduled inspection
Start date: 2018-09-06, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161801076200
Unscheduled inspection
Start date: 2018-09-06, end date: 2018-09-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 11052018 case 191120180008, the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161801559561
Unscheduled inspection
Start date: 2018-09-20, end date: 2018-09-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 25072018 case 191120180030the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161801558915
Unscheduled inspection
Start date: 2018-09-20, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161801558502
Unscheduled inspection
Start date: 2018-09-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161800638736
Unscheduled inspection
Start date: 2018-08-27, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161800621048
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-08-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 23072018 case 191120180021
# 161800604078
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 17052018 case 191120180016
# 161800599110
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 13072018 case 191120180029
# 161800577687
Unscheduled inspection
Start date: 2018-08-07, end date: 2018-08-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 10052018 case 191120170035, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161800639091
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-08-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 17052018 case 191120180017, the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 161800639172
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-08-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 25072018 case 191120180010, the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161800639018
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-08-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 14052018 case 191120180011, the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 161800638929
Unscheduled inspection
Start date: 2018-08-20, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161800638872
Unscheduled inspection
Start date: 2018-08-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161800621126
Unscheduled inspection
Start date: 2018-08-21, end date: 2018-08-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the inspection program from 14062018 case 191120180014
# 161800646552
Unscheduled inspection
Start date: 2018-08-22, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161800542880
Unscheduled inspection
Start date: 2018-07-16, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161800542641
Unscheduled inspection
Start date: 2018-07-16, end date: 2018-07-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 10052018 case 191120170035, the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 161800543038
Unscheduled inspection
Start date: 2018-07-18, end date: 2018-07-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 16052018 case 191120180013, the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 161800579199
Unscheduled inspection
Start date: 2018-07-30, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161800577842
Unscheduled inspection
Start date: 2018-07-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161800577438
Unscheduled inspection
Start date: 2018-07-30, end date: 2018-08-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the order dated 20062018 1919006201, the deadline for which expired on 13072018, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations and other regulations performed during the construction of a capital construction facility. regulatory legal acts and project documentation The subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 161800507877
Unscheduled inspection
Start date: 2018-07-04, end date: 2018-07-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 17052018 case 191120180017, the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 161800508000
Unscheduled inspection
Start date: 2018-07-05, end date: 2018-07-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 17052018 case 191120180016
# 161800514109
Unscheduled inspection
Start date: 2018-07-06, end date: 2018-07-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 26062018 case 191120180021
# 161800564322
Unscheduled inspection
Start date: 2018-07-23, end date: 2018-07-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the inspection program from 14062018 case 191120180014
# 161800508077
Unscheduled inspection
Start date: 2018-07-02, end date: 2018-07-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 14052018 case 191120180010, the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 161800577212
Unscheduled inspection
Start date: 2018-07-25, end date: 2018-08-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 23052018 case 191120180020, the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800459327
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-06-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 10052018 case 191120170035, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161800414612
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-06-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 23052018 case 191120180021
# 161800406007
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-06-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 17052018 case 191120180016
# 161800406074
Unscheduled inspection
Start date: 2018-06-19, end date: 2018-06-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such works, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 17052018 case 191120180015
# 161800424156
Unscheduled inspection
Start date: 2018-06-11, end date: 2018-06-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 14052018 case 191120180011, the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161800424278
Unscheduled inspection
Start date: 2018-06-11, end date: 2018-06-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 14052018 case 191120180010, the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 161800435474
Unscheduled inspection
Start date: 2018-06-06, end date: 2018-06-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 23052018 case 191120180019, the objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800435382
Unscheduled inspection
Start date: 2018-06-06, end date: 2018-06-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 11052018 case 191120180008, the objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800432764
Unscheduled inspection
Start date: 2018-06-06, end date: 2018-06-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 23052018 case 191120180020, the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800406136
Unscheduled inspection
Start date: 2018-06-08, end date: 2018-06-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such works, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 17052018 case 191120180015
# 161800478512
Unscheduled inspection
Start date: 2018-06-25, end date: 2018-06-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 16052018 case 191120180013, the objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800406270
Unscheduled inspection
Start date: 2018-06-25, end date: 2018-06-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 17052018 case 191120180014
# 161800380491
Unscheduled inspection
Start date: 2018-05-17, end date: 2018-05-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 10052018 case 191120170035, the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 161802717944
Unscheduled inspection
Start date: 2018-05-28, end date: 2018-05-28, duration: —
Authority: Ministerstvo vnutrennih del po Respublike Tatarstan
Purpose of inspection: expiration of the deadline for the execution by a legal entity, an individual entrepreneur, of an order issued by the state supervisory authority to eliminate identified violations of the mandatory requirements of the Traffic Police Department of the Ministry of Internal Affairs of the Russian Federation in the Nizhnekamsk region, order 11 of 16052018
# 161800406937
Unscheduled inspection
Start date: 2018-05-29, end date: 2018-05-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 16052018 case 191120180013, the objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800391275
Unscheduled inspection
Start date: 2018-05-22, end date: 2018-05-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 14052018 case 191120180011, the objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800391203
Unscheduled inspection
Start date: 2018-05-22, end date: 2018-05-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 14052018 case 191120180010, the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161800264672
Unscheduled inspection
Start date: 2018-04-03, end date: 2018-04-27, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Respublike Tatarstan
Purpose of inspection: For compliance with fire safety requirements at the supervision facility
# 16170802882632
Unscheduled inspection
Start date: 2017-11-27, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170802802271
Unscheduled inspection
Start date: 2017-11-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170802882549
Unscheduled inspection
Start date: 2017-11-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170802797077
Unscheduled inspection
Start date: 2017-10-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170802681707
Unscheduled inspection
Start date: 2017-10-06, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170802681779
Unscheduled inspection
Start date: 2017-10-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170802741378
Unscheduled inspection
Start date: 2017-10-23, end date: 2017-10-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program from 18072017 case 191120170021
# 16170802706575
Unscheduled inspection
Start date: 2017-10-23, end date: 2017-10-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with According to the inspection program dated 07092017 case 191120170029, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out reconstruction on the basis of a contract with the developer or the customer. The purpose of this inspection is to ensure that the information contained in the notice of commencement of implementation mandatory requirements for certain types of business activities
# 16170802682482
Unscheduled inspection
Start date: 2017-10-23, end date: 2017-10-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer of the compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and design documentationcompliance with mandatory requirements and or requirements established by municipal legal acts
# 16170802682336
Unscheduled inspection
Start date: 2017-10-23, end date: 2017-10-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer of the compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and design documentationcompliance with mandatory requirements and or requirements established by municipal legal acts
# 16170802741225
Unscheduled inspection
Start date: 2017-10-19, end date: 2017-10-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the verification program dated 24082017 case 191120170004
# 16170802713310
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-10-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 04102017 case 191120170035the objectives of this inspection are to prevent, as well as identify and prevent violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The purpose of this inspection is to comply with mandatory requirements and or requirements established by municipal legal acts. acts
# 16170802681785
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-10-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of an agreement with the developer or the customer of the compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and design documentationcompliance with mandatory requirements and or requirements established by municipal legal acts
# 16170802695962
Unscheduled inspection
Start date: 2017-10-10, end date: 2017-10-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 14092017 case 191120170018, the objectives of this inspection are to prevent, identify and prevent violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 16170802695810
Unscheduled inspection
Start date: 2017-10-10, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170802693046
Unscheduled inspection
Start date: 2017-10-10, end date: 2017-10-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with According to the inspection program from 18052017 case 191120170015, the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The purpose of this inspection is to comply with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 16170802693115
Unscheduled inspection
Start date: 2017-10-10, end date: 2017-10-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 18052017 case 191120170008, the objectives of this inspection are to prevent, identify and prevent violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 16170802692951
Unscheduled inspection
Start date: 2017-10-10, end date: 2017-10-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 18052017 case 191120170011, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out reconstruction on the basis of a contract with the developer or the customer. The purpose of this inspection is to comply with mandatory requirements and or requirements established by municipal authorities. legal acts
# 16170802786006
Unscheduled inspection
Start date: 2017-10-30, end date: 2017-10-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations design documentation other regulations norms and rules, as well as to draw up an act on the elimination of violations based on the notice received by the Inspectorate from 11102017 8208 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time period established by the regulation from 26072017 1919011401 to 10102017
# 16170801936016
Unscheduled inspection
Start date: 2017-09-18, end date: 2017-09-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. also, the identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer of the compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, and compliance with mandatory requirements and or requirements established by municipal legal acts
# 16170802506595
Unscheduled inspection
Start date: 2017-09-18, end date: 2017-09-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. according to the inspection program dated 24082017 case 191120170009
# 16170802507095
Unscheduled inspection
Start date: 2017-09-18, end date: 2017-09-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program of 18072017 case 191120170014
# 16170802507766
Unscheduled inspection
Start date: 2017-09-18, end date: 2017-09-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program of 18072017 case 191120170021
# 16170802449240
Unscheduled inspection
Start date: 2017-09-18, end date: 2017-09-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program dated 07092017 case 191120170029, the tasks of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 16170802533999
Unscheduled inspection
Start date: 2017-09-13, end date: 2017-09-29, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: in order to protect the rights and interests of employees, the objectives of this audit are supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms. The subject of this audit is to note the necessary compliance with mandatory requirements or requirements established by municipal legal acts to prevent harm to the life and health of citizens, harm to animals, plants and the environment
# 16170802292328
Unscheduled inspection
Start date: 2017-09-11, end date: 2017-09-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in according to the inspection program from 03072017 case 191120170006
# 16170802290814
Unscheduled inspection
Start date: 2017-09-11, end date: 2017-09-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. according to the inspection program dated 24082017 case 191120170004
# 16170802008161
Unscheduled inspection
Start date: 2017-09-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170802008711
Unscheduled inspection
Start date: 2017-09-05, end date: 2017-09-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program from 18052017 case 191120170011the objectives of this inspection are to prevent, as well as identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out the reconstruction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 16170802009104
Unscheduled inspection
Start date: 2017-09-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170802008395
Unscheduled inspection
Start date: 2017-09-05, end date: 2017-09-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program from 18052017 case 191120170015the tasks of this inspection are to prevent, as well as identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 16170802602358
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 26062017 case 191120170024the tasks of this inspection are to prevent, as well as identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 16170802602298
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 26062017 case 191120170025the tasks of this inspection are to prevent, as well as identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 16170802599073
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program from 19052017 case 191120170020the objectives of this inspection are to prevent, as well as identify and prevent violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The purpose of this inspection is to comply with mandatory requirements and or requirements established by municipal authorities. legal acts
# 16170802529815
Unscheduled inspection
Start date: 2017-09-21, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170801923158
Unscheduled inspection
Start date: 2017-08-18, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection:
# 16170701879737
Unscheduled inspection
Start date: 2017-08-18, end date: 2017-08-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program dated 17052017 case 191120170009
# 16170701891432
Unscheduled inspection
Start date: 2017-08-15, end date: 2017-08-18, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. also, the identification and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer of the compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, and compliance with mandatory requirements and or requirements established by municipal legal acts
# 16170701887069
Unscheduled inspection
Start date: 2017-08-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170701887182
Unscheduled inspection
Start date: 2017-08-14, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170701859480
Unscheduled inspection
Start date: 2017-08-07, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170701859389
Unscheduled inspection
Start date: 2017-08-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170801922217
Unscheduled inspection
Start date: 2017-08-22, end date: 2017-08-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program from 19052017 case 191120170020, the tasks of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation
# 16170801922304
Unscheduled inspection
Start date: 2017-08-22, end date: 2017-08-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 26062017 case 191120170024, the objectives of this inspection are to prevent, as well as identify and prevent violations of compliance by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The purpose of this inspection is to comply with mandatory requirements and or requirements established by municipal authorities. legal acts
# 16170801922294
Unscheduled inspection
Start date: 2017-08-22, end date: 2017-08-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 26062017 case 191120170025the objectives of this inspection are to prevent, as well as identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out the reconstruction on the basis of a contract with the developer or the customer, performed during the construction of a capital construction facility. The purpose of this inspection is to comply with mandatory requirements and or requirements established by municipal authorities. legal acts
# 16170701891605
Unscheduled inspection
Start date: 2017-08-23, end date: 2017-08-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. also, the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, and compliance with mandatory requirements and or requirements established by municipal legal acts
# 16170802624718
Unscheduled inspection
Start date: 2017-08-21, end date: 2017-09-18, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: The objectives of this audit are to ensure that the labor rights and freedoms of citizens are respected and protected, and to ensure that the employer complies with labor laws and other regulatory legal acts containing labor law norms.The purpose of this audit is to comply with mandatory requirements and or requirements established by municipal legal acts to protect the rights and interests of employees by memo
# 16170701891956
Unscheduled inspection
Start date: 2017-08-21, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170701879917
Unscheduled inspection
Start date: 2017-08-21, end date: 2017-08-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program of 18072017 case 191120170021
# 16170701879847
Unscheduled inspection
Start date: 2017-08-21, end date: 2017-08-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program of 18072017 case 191120170014
# 16170701814652
Unscheduled inspection
Start date: 2017-07-18, end date: 2017-08-14, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: protection of the rights and interests of employees
# 16170701804305
Unscheduled inspection
Start date: 2017-07-18, end date: 2017-07-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 26062017 case 191120170024, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer.
# 16170701804151
Unscheduled inspection
Start date: 2017-07-18, end date: 2017-07-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 26062017 case 191120170025the tasks of this inspection are to prevent, as well as identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer.
# 16170701802721
Unscheduled inspection
Start date: 2017-07-18, end date: 2017-07-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program from 19052017 case 191120170020, the tasks of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation
# 16170701802465
Unscheduled inspection
Start date: 2017-07-18, end date: 2017-07-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 06072016 case 191120160032the tasks of this inspection are to prevent, as well as identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer.
# 16170701801180
Unscheduled inspection
Start date: 2017-07-19, end date: 2017-07-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: compliance with mandatory requirements and or requirements established by municipal legal acts, prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility
# 16170701801135
Unscheduled inspection
Start date: 2017-07-19, end date: 2017-07-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: compliance with mandatory requirements and or requirements established by municipal legal acts, prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility
# 16170701801093
Unscheduled inspection
Start date: 2017-07-19, end date: 2017-07-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: compliance with mandatory requirements and or requirements established by municipal legal acts, prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer
# 16170701798229
Unscheduled inspection
Start date: 2017-07-19, end date: 2017-07-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in according to the inspection program from 07072017 case 191120170004
# 16170701793682
Unscheduled inspection
Start date: 2017-07-19, end date: 2017-07-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in according to the inspection program from 03072017 case 191120170006
# 16170701786271
Unscheduled inspection
Start date: 2017-07-17, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170701786158
Unscheduled inspection
Start date: 2017-07-17, end date: 2017-07-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program from 15052017 case 191120160028, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 16170701766478
Unscheduled inspection
Start date: 2017-07-05, end date: 2017-07-11, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program from 18052017 case 191120170018the objectives of this inspection are to prevent, as well as identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 16170701766632
Unscheduled inspection
Start date: 2017-07-06, end date: 2017-07-18, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program from 18052017 case 191120170011the tasks of this inspection are to prevent, as well as identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 16170701807824
Unscheduled inspection
Start date: 2017-07-25, end date: 2017-07-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: compliance with mandatory requirements and or requirements established by municipal legal acts, prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer
# 16170701751993
Unscheduled inspection
Start date: 2017-07-03, end date: 2017-07-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in according to the inspection program from 03052017 case 191120170006
# 16170701751830
Unscheduled inspection
Start date: 2017-07-03, end date: 2017-07-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in according to the inspection program from 03052017 case 191120170004
# 16170701806237
Unscheduled inspection
Start date: 2017-07-21, end date: 2017-07-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program of 21062017 case 191120170021
# 16170701805314
Unscheduled inspection
Start date: 2017-07-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170701703937
Unscheduled inspection
Start date: 2017-06-19, end date: 2017-07-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 19052017 case 191120170020, the tasks of this inspection are to prevent, as well as to identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation
# 16170701702952
Unscheduled inspection
Start date: 2017-06-19, end date: 2017-06-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program from 06072016 case 191120160032, the tasks of this inspection are to prevent, as well as to identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation
# 16170701703731
Unscheduled inspection
Start date: 2017-06-15, end date: 2017-06-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the inspection program from 15052017 case 191120160028the objectives of this inspection are to prevent, as well as identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this inspection is to comply with mandatory requirements
# 16170701703967
Unscheduled inspection
Start date: 2017-06-13, end date: 2017-06-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program from 18052017 case 191120170015the objectives of this inspection are to prevent, as well as identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this inspection is to comply with mandatory requirements
# 16170701703852
Unscheduled inspection
Start date: 2017-06-13, end date: 2017-06-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program from 18052017 case 191120170011the tasks of this inspection are to prevent, as well as identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer. The subject of this inspection is compliance with mandatory requirements
# 16170701668921
Unscheduled inspection
Start date: 2017-06-13, end date: 2017-06-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program from 03052017 case 191120170004, a warning as well as the detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
# 16170701723834
Unscheduled inspection
Start date: 2017-06-26, end date: 2017-06-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program dated 17052017 case 191120170009
# 16170701674653
Unscheduled inspection
Start date: 2017-06-26, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170701669938
Unscheduled inspection
Start date: 2017-06-26, end date: 2017-06-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: To establish that this inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction and reconstruction of the capital construction facility, and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code In accordance with the inspection program of 17052017 case 191120170019, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this inspection is to comply with mandatory requirements
# 16170701668966
Unscheduled inspection
Start date: 2017-06-05, end date: 2017-06-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. according to the inspection program from 22052017 case 191120170021
# 16170701653551
Unscheduled inspection
Start date: 2017-06-05, end date: 2017-06-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program from 17052017 case 191120170014the objectives of this inspection are to prevent, as well as identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements
# 16170701673993
Unscheduled inspection
Start date: 2017-06-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170701725492
Unscheduled inspection
Start date: 2017-06-20, end date: 2017-06-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program dated 18052017 case 191120170008, the tasks of this inspection are to prevent, as well as to identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The purpose of this inspection is to select the necessary compliance with mandatory requirements
# 16170701725632
Unscheduled inspection
Start date: 2017-06-20, end date: 2017-06-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program from 18052017 case 191120170013the objectives of this inspection are to prevent, as well as identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements
# 16170701648425
Unscheduled inspection
Start date: 2017-05-30, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170701648595
Unscheduled inspection
Start date: 2017-05-31, end date: 2017-06-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program dated 17052017 case 191120170009
# 16170701656772
Unscheduled inspection
Start date: 2017-05-29, end date: 2017-05-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used during the construction and reconstruction of the capital construction facility comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program from 17052017 case 191120170010, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this inspection is to comply with mandatory requirements
# 16170701634187
Unscheduled inspection
Start date: 2017-05-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170701634312
Unscheduled inspection
Start date: 2017-05-29, end date: 2017-06-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in according to the inspection program from 03052017 case 191120170006
# 00170701565985
Unscheduled inspection
Start date: 2017-04-17, end date: 2017-04-21, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control and supervision of the execution of the previously issued regulation 4321201218122830475996110128135141 dated 01062016
# 001702410392
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-04-03, duration: —
Authority: Privolzhskoe mezhregionalnoe territorialnoe upravlenie Federalnogo agentstva po tehnicheskomu regulirovaniyu i metrologii
Purpose of inspection: In order to assess the fulfillment of the previously issued instruction No. 54m dated May 26, 2016, due to the expiration of its execution on March 01, 2017, the objectives of this audit are to assess the compliance of measurements performed in the field of state regulation to ensure the uniformity of measurements with established requirements. The subject of this audit is the fulfillment of the instructions of the state control and supervision bodies
# 00170701438206
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-04-03, duration: —
Authority: Privolzhskoe mezhregionalnoe territorialnoe upravlenie Federalnogo agentstva po tehnicheskomu regulirovaniyu i metrologii
Purpose of inspection: assessment of the fulfillment of the previously issued order dated May 26, 2016 54m in connection with the expiration of its execution on March 01, 2017
# 16170701420981
Unscheduled inspection
Start date: 2017-03-01, end date: 2017-03-29, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: the details of the order previously issued to the person being checked on the elimination of the detected violation, the deadline for which has expired, the details of appeals and applications from citizens, legal entities and individual entrepreneurs submitted to the state control and supervision bodies, the municipal control bodies, the details of the order of the head of the state control and supervision body issued in accordance with the instructions of the President of the Russian Federation, the Government of the Russian Federation, the details of the prosecutor's request for an unscheduled inspection in as part of the supervision of the implementation of laws and the details of the materials and appeals attached to the request
# 00160701260724
Unscheduled inspection
Start date: 2016-12-15, end date: 2017-01-18, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Respublike Tatarstan
Purpose of inspection: confirmation of the fulfillment of regulation 3673 dated 06062016 issued following the results of an audit of JSC Tatavtodor conducted in compliance with the orders of Farit Yusupovich Khairutdinov, Head of the Federal Service for Supervision of Natural Resources in the Republic of Tatarstan, 393 dated 29042015, acting Head of the Rosprirodnadzor Department for the Republic of Tatarstan, Lilia Akhatovna Gainutdinova 429 dated 13052016 to the act of inspection by the state control authority for the supervision of a legal entity persons 367 from 06062016
# 16160701102592
Unscheduled inspection
Start date: 2016-11-18, end date: 2016-11-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program dated 28072016 case 191120160038 warning, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility
# 16160701101239
Unscheduled inspection
Start date: 2016-11-18, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16160701078880
Unscheduled inspection
Start date: 2016-11-15, end date: 2016-11-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used during the construction and reconstruction of the capital construction facility comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program dated 12052016 case 191120160008, the prevention, as well as the detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation with mandatory requirements performed during the construction of a capital construction facility.
# 16160701078831
Unscheduled inspection
Start date: 2016-11-15, end date: 2016-11-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used during the construction and reconstruction of the capital construction facility comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program from 08062016 case 191120160018, the prevention as well as the detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation, with mandatory requirements.
# 16160701144856
Unscheduled inspection
Start date: 2016-11-30, end date: 2016-12-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction and reconstruction of the capital construction facility, and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and the requirements for equipping capital construction facilities with metering devices for energy resources used, based on the notice received by the Inspection dated 10102016 8930 on the completion dates that are subject to verification at the capital construction facility, the objectives of this audit are to prevent, as well as to identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 16160701106457
Unscheduled inspection
Start date: 2016-11-11, end date: 2016-11-18, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program from 06052016 case 191120160005the tasks of this inspection are to prevent, as well as identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer. The subject of this inspection is compliance with mandatory requirements
# 16160701077408
Unscheduled inspection
Start date: 2016-11-07, end date: 2016-11-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: The inspection is carried out in order to determine the compliance of the completed works and applied building materials during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer customer carrying out construction on the basis of a contract with the developer or the customer of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations of other regulatory legal acts and design documentationthe subject of this audit is Compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations of other regulatory legal acts and project documentation
# 16160701073691
Unscheduled inspection
Start date: 2016-11-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160701078255
Unscheduled inspection
Start date: 2016-11-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160701054915
Unscheduled inspection
Start date: 2016-11-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160701135898
Unscheduled inspection
Start date: 2016-11-21, end date: 2016-11-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program dated 24052016 case 191120160012the tasks of this inspection are to prevent, as well as identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is to select the necessary compliance with mandatory requirements
# 16160701135860
Unscheduled inspection
Start date: 2016-11-21, end date: 2016-11-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program dated 24052016 case 191120160012the tasks of this inspection are to prevent, as well as identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is to select the necessary compliance with mandatory requirements
# 16160701034195
Unscheduled inspection
Start date: 2016-10-17, end date: 2016-10-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used based on the notice received by the Inspectorate dated 03102016 8638 on the completion dates that are subject to verification At the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The subject of this audit is compliance with mandatory requirements
# 16160701034134
Unscheduled inspection
Start date: 2016-10-17, end date: 2016-10-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used based on the notice received by the Inspection dated 05092016 7669 20092016 8185 on the completion dates that are subject to inspection at the capital construction facility. The objectives of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is the observance of mandatory requirements
# 16160700972773
Unscheduled inspection
Start date: 2016-10-13, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16160700972797
Unscheduled inspection
Start date: 2016-10-13, end date: 2016-10-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation for the work performed during the construction of the capital construction facility. Compliance with mandatory requirements
# 16160700972744
Unscheduled inspection
Start date: 2016-10-13, end date: 2016-10-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer
# 16160700979816
Unscheduled inspection
Start date: 2016-10-14, end date: 2016-10-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of the fulfillment of the order dated 05082016 1619039001, the deadline for which expired on 03102016, and to draw up an act based on the results of the inspection, to prevent, as well as to identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, violations of the compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations and other regulatory legal acts. project documentation compliance with Inspection regulations
# 16160701017478
Unscheduled inspection
Start date: 2016-10-14, end date: 2016-10-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used based on the notice received by the Inspectorate dated 10102016 8910 on the completion dates that are subject to verification at the capital construction facility, the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation, performed during the construction of the capital construction facility. compliance with mandatory requirements
# 16160701017464
Unscheduled inspection
Start date: 2016-10-14, end date: 2016-10-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used based on the notice received by the Inspectorate dated 10102016 8911 on the completion dates that are subject to verification at the capital construction facility, the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation, performed during the construction of the capital construction facility. compliance with mandatory requirements
# 16160701016663
Unscheduled inspection
Start date: 2016-10-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160700992960
Unscheduled inspection
Start date: 2016-10-10, end date: 2016-10-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used, based on the notice received by the Inspectorate from 05092016 7685 on the completion dates that are subject to verification at the capital construction facility, the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation, performed during the construction of the capital construction facility. compliance with mandatory requirements
# 16160700992929
Unscheduled inspection
Start date: 2016-10-10, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16160700984674
Unscheduled inspection
Start date: 2016-10-10, end date: 2016-10-11, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notice dated 27092016 8416 on the completion dates that are subject to verification. at the capital construction facility, the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation, performed during the construction of the capital construction facility. compliance with mandatory requirements
# 16160701045912
Unscheduled inspection
Start date: 2016-10-12, end date: 2016-10-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: The inspection is carried out in order to determine the compliance of the completed works and applied building materials during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer customer carrying out construction on the basis of a contract with the developer or the customer of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations of other regulatory legal acts and design documentationthe subject of this audit is Compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations of other regulatory legal acts and project documentation
# 16160701046258
Unscheduled inspection
Start date: 2016-10-12, end date: 2016-10-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: The inspection is carried out in order to determine the compliance of the completed works and applied building materials during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer customer carrying out construction on the basis of a contract with the developer or the customer of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations of other regulatory legal acts and design documentationthe subject of this audit is Compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations of other regulatory legal acts and project documentation
# 16160700962686
Unscheduled inspection
Start date: 2016-10-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160701022354
Unscheduled inspection
Start date: 2016-10-24, end date: 2016-10-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used during the construction and reconstruction of the capital construction facility comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 06072016 case 191120160032, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160701037935
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-10-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the notice received by the Inspectorate from 17102016 9195 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the regulation from 19072016 1619035001 to 18102016 prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, while eliminating previously identified violations, compliance with Inspection instructions
# 00160701032149
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used based on the Inspection notice dated 04102016 8703 on the completion dates that are subject to verification at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 00160701032121
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used based on the Inspection notice dated 04102016 8707 on the completion dates that are subject to verification at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 00160701032105
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notice dated 04102016 8705 on the completion dates that are subject to verification. at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 00160701032085
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notice dated 04102016 8705 on the completion dates that are subject to verification. at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 00160701032057
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notice dated 04102016 8704 on the completion dates that are subject to verification. at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 16160700919825
Unscheduled inspection
Start date: 2016-10-03, end date: 2016-10-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used, based on the notice received by the Inspectorate from 05092016 7670 on the completion dates that are subject to verification At the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160700919942
Unscheduled inspection
Start date: 2016-10-03, end date: 2016-10-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used based on the notice received by the Inspectorate from 05092016 7674 on the completion dates of the work that is subject to verification At the capital construction facility, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160700919848
Unscheduled inspection
Start date: 2016-10-03, end date: 2016-10-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used, based on the notice received by the Inspection from 05092016 7673 on the completion dates that are subject to verification At the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160700919573
Unscheduled inspection
Start date: 2016-10-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160701051954
Unscheduled inspection
Start date: 2016-10-26, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notice dated 06102016 8837 on the completion dates that are subject to verification. At the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this audit is to comply with mandatory requirements
# 00160701051828
Unscheduled inspection
Start date: 2016-10-26, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used based on the notice received by the Inspectorate dated 17102016 9209 on the completion dates that are subject to verification at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 00160701051908
Unscheduled inspection
Start date: 2016-10-26, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used based on the notice received by the Inspectorate dated 06102016 8836 on the completion dates that are subject to verification at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 00160701051871
Unscheduled inspection
Start date: 2016-10-26, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the notice received by the Inspectorate dated 17102016 9206 on the completion dates that are subject to verification At the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this audit is to comply with mandatory requirements
# 00160700937926
Unscheduled inspection
Start date: 2016-10-04, end date: 2016-10-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notice dated 22092016 8278 on the completion dates that are subject to verification. at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 16160700981711
Unscheduled inspection
Start date: 2016-10-05, end date: 2016-10-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the notice received by the Inspectorate dated 14092016 8007 on the completion dates that are subject to verification at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 16160700973603
Unscheduled inspection
Start date: 2016-10-05, end date: 2016-10-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used based on the notice received by the Inspectorate from 20092016 8210 on the completion dates that are subject to verification at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 16160700973527
Unscheduled inspection
Start date: 2016-10-05, end date: 2016-10-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used based on the notice received by the Inspectorate from 20092016 8211 on the completion dates that are subject to verification at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 16160701046424
Unscheduled inspection
Start date: 2016-10-20, end date: 2016-10-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: The inspection is carried out in order to determine the compliance of the completed works and applied building materials during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer customer carrying out construction on the basis of a contract with the developer or the customer of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations of other regulatory legal acts and design documentationthe subject of this audit is Compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations of other regulatory legal acts and project documentation
# 16160700887769
Unscheduled inspection
Start date: 2016-09-22, end date: 2016-09-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentationcompliance with mandatory requirements or requirements established by municipal legal acts
# 16160700846035
Unscheduled inspection
Start date: 2016-09-22, end date: 2016-09-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used during the construction and reconstruction of the capital construction facility comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 31052016 case 191120160013, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160700846266
Unscheduled inspection
Start date: 2016-09-22, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16160700846245
Unscheduled inspection
Start date: 2016-09-22, end date: 2016-09-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used during the construction and reconstruction of the capital construction facility comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 28072016 case 191120160038, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160700846239
Unscheduled inspection
Start date: 2016-09-22, end date: 2016-09-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used during the construction and reconstruction of the capital construction facility comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 22062016 case 191120160026, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160700846233
Unscheduled inspection
Start date: 2016-09-22, end date: 2016-09-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used during the construction and reconstruction of the capital construction facility comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 14062016 case 191120160023, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160700845382
Unscheduled inspection
Start date: 2016-09-22, end date: 2016-09-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used during the construction and reconstruction of the capital construction facility comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 06052016 case 191120160004the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160700721587
Unscheduled inspection
Start date: 2016-09-22, end date: 2016-09-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentationcompliance with mandatory requirements or requirements established by municipal legal acts
# 00160700412785
Unscheduled inspection
Start date: 2016-09-08, end date: 2016-10-05, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Respublike Tatarstan
Purpose of inspection: verification of compliance with regulations 3671 3672 dated 06062016
# 16160700844675
Unscheduled inspection
Start date: 2016-09-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160700863240
Unscheduled inspection
Start date: 2016-09-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160700863315
Unscheduled inspection
Start date: 2016-09-26, end date: 2016-09-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used based on the notice received by the Inspection dated 24082016 7296 31082016 7510 01082016 6345 on the completion dates The objectives of this audit are to prevent as well as identify and suppress violations of compliance of works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and design documentationthe subject of this audit is to comply with mandatory requirements.
# 16160700863165
Unscheduled inspection
Start date: 2016-09-26, end date: 2016-09-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the construction materials used in the construction and reconstruction of the capital construction facility with the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used based on the notice received by the Inspection dated 27072016 6173 27072016 6179 27072016 6180 27072016 6181 01082016 6343 on the completion dates of works that are subject to verification at the capital construction facility The objectives of this audit are to prevent, identify and prevent violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentationthe subject of this audit is compliance with mandatory requirements
# 16160700863284
Unscheduled inspection
Start date: 2016-09-26, end date: 2016-09-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used during the construction and reconstruction of the capital construction facility comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program from 30062016 case 191120160028, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this inspection is to comply with mandatory requirements
# 16160700863125
Unscheduled inspection
Start date: 2016-09-26, end date: 2016-09-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used based on the notice received by the Inspectorate from 19082016 7112 19082016 7113 19082016 7114 on the completion dates The objectives of this audit are to prevent as well as identify and suppress violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility by the developer, the customer, or the person carrying out the construction on the basis of a contract with the developer or the customer. The purpose of this audit is to comply with mandatory requirements
# 16160700948858
Unscheduled inspection
Start date: 2016-09-29, end date: 2016-09-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notice dated 13092016 7969 on the completion dates that are subject to verification. At the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160700938651
Unscheduled inspection
Start date: 2016-09-29, end date: 2016-09-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used based on the Inspection notification dated 13092016 7968 on the completion dates that are subject to verification At the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160700870463
Unscheduled inspection
Start date: 2016-09-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160700841315
Unscheduled inspection
Start date: 2016-09-13, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16160700841147
Unscheduled inspection
Start date: 2016-09-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160700840927
Unscheduled inspection
Start date: 2016-09-13, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16160700840713
Unscheduled inspection
Start date: 2016-09-13, end date: 2016-09-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used based on the notice received by the Inspection from 05092016 7686 05092016 7665 on the completion dates that subject to inspection at the capital construction facility
# 16160700444026
Unscheduled inspection
Start date: 2016-09-13, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16160700439373
Unscheduled inspection
Start date: 2016-09-13, end date: 2016-09-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer
# 16160700440604
Unscheduled inspection
Start date: 2016-09-13, end date: 2016-09-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer
# 16160700915130
Unscheduled inspection
Start date: 2016-09-30, end date: 2016-10-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notice dated 13092016 7971 on the completion dates that are subject to verification. at the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation6 committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements
# 16160601751388
Unscheduled inspection
Start date: 2016-08-02, end date: 2016-08-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the process of construction reconstruction of the capital construction facility, the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used on the basis of the notification received by the Inspection from 11072016 5609 on the completion dates of works that are subject to verification at the capital construction facility, the objectives of this audit are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentationthe subject of this audit is compliance with mandatory requirements or requirements established by municipal legal acts
# 16160601751266
Unscheduled inspection
Start date: 2016-08-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160601782479
Unscheduled inspection
Start date: 2016-08-01, end date: 2016-08-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notification dated 26072016 6134 on the completion dates that are subject to verification. At the capital construction facility, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160601759433
Unscheduled inspection
Start date: 2016-08-01, end date: 2016-08-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notification dated 26072016 6134 on the completion dates that are subject to verification. at a capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation6 committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation6 The subject of this audit is compliance with mandatory requirements or requirements established by municipal legal acts
# 16160601724260
Unscheduled inspection
Start date: 2016-08-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160601778371
Unscheduled inspection
Start date: 2016-08-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160601750727
Unscheduled inspection
Start date: 2016-08-03, end date: 2016-08-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the notice received by the Inspectorate from 07072016 5525 07072016 5523 on the completion dates that are subject to verification for the prevention of capital construction, as well as the detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, compliance with mandatory requirements or requirements established by municipal legal acts
# 16160601731021
Unscheduled inspection
Start date: 2016-08-22, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16160601731005
Unscheduled inspection
Start date: 2016-08-22, end date: 2016-08-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works applied during the construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program from 02062016 case 191120160014, the objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility. The subject of this inspection is compliance with mandatory requirements or requirements established by municipal authorities. legal acts
# 16160601730949
Unscheduled inspection
Start date: 2016-08-22, end date: 2016-08-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works applied during the construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program from 02062016 case 191120160014, the objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility. The subject of this inspection is compliance with mandatory requirements or requirements established by municipal authorities. legal acts
# 16160601729439
Unscheduled inspection
Start date: 2016-08-09, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16160601724242
Unscheduled inspection
Start date: 2016-08-29, end date: 2016-09-02, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works applied during the construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program dated 17052016 case 191120160011, the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentationthe subject of this inspection is compliance with mandatory requirements or requirements established by municipal authorities. legal acts
# 16160601730924
Unscheduled inspection
Start date: 2016-08-15, end date: 2016-08-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works applied during the construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program from 02062016 case 191120160014, the objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility. The subject of this inspection is compliance with mandatory requirements or requirements established by municipal authorities. legal acts
# 16160601772259
Unscheduled inspection
Start date: 2016-08-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160601732425
Unscheduled inspection
Start date: 2016-08-10, end date: 2016-08-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works applied during the construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program from 20012016 case 193320130052, the tasks of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is the compliance of the information contained in the notification of the beginning implementation of certain types of entrepreneurial activity by mandatory requirements compliance with mandatory requirements or requirements established by municipal legal acts
# 16160700040140
Unscheduled inspection
Start date: 2016-08-17, end date: 2016-08-18, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used based on the notice received by the Inspectorate from 05082016 6592 on the completion dates that are subject to verification at the capital construction facility, prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation and compliance with mandatory requirements or requirements established by municipal legal acts
# 16160601801595
Unscheduled inspection
Start date: 2016-08-17, end date: 2016-08-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used during the construction and reconstruction of the capital construction facility comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 22062016 case 191120160026, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160601801369
Unscheduled inspection
Start date: 2016-08-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160601800768
Unscheduled inspection
Start date: 2016-08-17, end date: 2016-08-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the Inspection notice dated 01082016 6406 on the completion dates that are subject to verification. At the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160601800878
Unscheduled inspection
Start date: 2016-08-17, end date: 2016-08-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used during the construction and reconstruction of the capital construction facility comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 31052016 case 191120160013, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160601800831
Unscheduled inspection
Start date: 2016-08-17, end date: 2016-08-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used based on the notice received by the Inspectorate dated 29072016 6308 29072016 6312 29072016 6310 on the completion dates The tasks of this inspection are to prevent as well as identify and prevent violations of compliance of works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160601801537
Unscheduled inspection
Start date: 2016-08-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160601801428
Unscheduled inspection
Start date: 2016-08-18, end date: 2016-08-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the notice received by the Inspectorate from 03082016 6499 on the completion dates that are subject to verification At the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160601736829
Unscheduled inspection
Start date: 2016-07-27, end date: 2016-07-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: in order to determine the compliance of the work performed with the construction materials used in the process of construction reconstruction of the capital construction facility, the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used on the basis of the notification received by the Inspection from 06072016 5456 on the completion dates of works that are subject to verification at the capital construction facility construction prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and design documentationcompliance with mandatory requirements or requirements established by municipal legal acts
# 16160601725097
Unscheduled inspection
Start date: 2016-07-21, end date: 2016-07-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works applied during the construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program of 12052016 case 191120160007, the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentationthe subject of this inspection is compliance with mandatory requirements or requirements established by municipal authorities. legal acts
# 16160601725038
Unscheduled inspection
Start date: 2016-07-21, end date: 2016-07-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the order dated 02062016 1919003101, the deadline for which expired on 20072016, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations and other regulatory documents. legal acts and project documentation The subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 16160601724199
Unscheduled inspection
Start date: 2016-07-20, end date: 2016-07-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works applied during the construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program of 12052016 case 191120160009, the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements or requirements established by the municipal legal acts
# 16160601724131
Unscheduled inspection
Start date: 2016-07-20, end date: 2016-07-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and equipment requirements for capital construction facilities with metering devices for energy resources used based on the Inspection notice dated 11072016 5610 on the completion dates that are subject to verification At the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The purpose of this audit is to comply with mandatory requirements or requirements established by municipal legal acts
# 16160601718535
Unscheduled inspection
Start date: 2016-07-01, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16160601729037
Unscheduled inspection
Start date: 2016-07-22, end date: 2016-07-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the notice received by the Inspectorate dated 13072016 5705 on the completion dates that are subject to verification At the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160601729102
Unscheduled inspection
Start date: 2016-07-22, end date: 2016-07-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, based on the notice received by the Inspectorate dated 13072016 5702 on the completion dates that are subject to verification At the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer.
# 16160601736797
Unscheduled inspection
Start date: 2016-07-18, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 00150600583528
Unscheduled inspection
Start date: 2015-09-10, end date: 2015-09-23, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Respublike Tatarstan
Purpose of inspection: monitoring the implementation of the regulation GPN 111149 of 10102014 on the elimination of identified violations as a result of surveillance measures