# 562005146059
Unscheduled inspection
Start date: 2020-09-30, end date: 2020-10-01, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision on the basis of regulation 4107033525067p dated 25082020. The objectives of this inspection are to identify and prevent violations of the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources legislation on urban development h 2 art 51 h 2 3 31 6 art 52 Of the Urban Planning Code of the Russian Federation, the subject of this audit is compliance with the mandatory requirements of urban planning legislation, compliance of the work performed and the building materials used during the reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with Parts 38 and 39 Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources. implementation of measures according to regulation 4107033525067p of 25082020
# 002004301999
Unscheduled inspection
Start date: 2020-02-25, end date: 2020-02-26, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation of regulation 35180rp6 dated 29012020 issued by the West Ural Rostechnadzor Department of Orenburg Minerals JSC, the deadline for which has expired 14022019the task is to assess the compliance of activities or actions of omissions carried out by Orenburg Minerals JSC with the requirements established by federal laws and regulatory legal acts of the Russian Federation in the field of industrial safety adopted in accordance with them, Subject to verification of compliance with the regulations of state control and supervision bodies
# 002005228458
Unscheduled inspection
Start date: 2020-02-03, end date: 2020-02-05, duration: 3
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the fulfillment of a previously issued prescription
# 002004278291
Unscheduled inspection
Start date: 2020-02-03, end date: 2020-02-05, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking a previously issued prescription
# 002004225653
Unscheduled inspection
Start date: 2020-01-27, end date: 2020-01-29, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation of paragraphs 32 34 35 36 37 38 39 of Regulation 33GN4891rp163 dated 18102019, the deadline for which expired on 18112019 and paragraph 33 of Regulation 33GN4891rp163 dated 18102019 issued by the West Ural Rostechnadzor Department of Orenburg Minerals JSC, the deadline for which expired on 18122019the task is to assess the compliance of activities or actions omissions carried out by Orenburg Minerals JSC with the requirements established by federal laws and adopted in accordance with them, the regulatory legal acts of the Russian Federation in the field of industrial safety are subject to verification of compliance with the instructions of the state control and supervision authorities.
# 002004212620
Unscheduled inspection
Start date: 2020-01-27, end date: 2020-01-29, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation of paragraphs 32 34 35 36 37 38 39 of Regulation 33GN4891rp163 dated 18102019, the deadline for which expired on 18112019 and paragraph 33 of Regulation 33GN4891rp163 dated 18102019 issued by the West Ural Rostechnadzor Department of Orenburg Minerals JSC, the deadline for which expired on 18122019the task is to assess the compliance of activities or actions omissions carried out by Orenburg Minerals JSC with the requirements established by federal laws and adopted in accordance with them, the regulatory legal acts of the Russian Federation in the field of industrial safety are subject to verification of compliance with the instructions of the state control and supervision authorities.
# 002004202172
Unscheduled inspection
Start date: 2020-01-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001903924620
Unscheduled inspection
Start date: 2019-11-01, end date: —, duration: —
Authority: Uralskoe upravlenie gosudarstvennogo zheleznodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection:
# 00160701258051
Unscheduled inspection
Start date: 2016-11-21, end date: 2016-12-29, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the implementation of the previously issued regulation 33GN171836rpo0802016 dated 04072016, the deadline for the execution of paragraphs 84 85 of which has expired
# 00160701028184
Unscheduled inspection
Start date: 2016-10-12, end date: 2016-10-12, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: ETL registration
# 00160700867866
Unscheduled inspection
Start date: 2016-08-10, end date: 2016-08-11, duration: —
Authority: Uralskoe upravlenie gosudarstvennogo zheleznodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: control
# 00160601601120
Unscheduled inspection
Start date: 2016-04-04, end date: 2016-04-15, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the implementation of a previously issued prescription
# 00160601505715
Unscheduled inspection
Start date: 2016-02-08, end date: 2016-02-10, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the fulfillment of the prescription
# 00150601278961
Unscheduled inspection
Start date: 2015-09-24, end date: 2015-10-06, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: determining the readiness of an enterprise to carry out a licensed type of activity
# 00150601265028
Unscheduled inspection
Start date: 2015-09-24, end date: 2015-10-06, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to verify the licensee's compliance with the licensing requirements for the operation of explosion- and fire-hazardous and chemically hazardous production facilities of hazard classes I II and III established by Federal Laws No. 04052011 99FZ "On licensing of certain types of activities" n 5 "Regulations on licensing the operation of explosion- and fire-hazardous and chemically hazardous production facilities of hazard classes I II and III" approved by decree of the Government of the Russian Federation Russian Federation No. 492 dated June 10, 2013
# 00150601265013
Unscheduled inspection
Start date: 2015-09-24, end date: 2015-10-06, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the completeness and reliability of the information contained in the application ex 01314057 dated 07092015 ex 0715739 dated 09092015 and the licensed materials and the compliance of the licensee of JSC Orenburg Minerals for the operation of explosive and fire hazardous and chemically hazardous production facilities of hazard classes I II and III with the licensing requirements established by Article 8 of the Federal Law of 04052011 99FZ "On Licensing Certain Types of Activities"
# 562101510199
Unscheduled inspection
Start date: 2021-12-27, end date: 2021-12-29, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: implementation of regional state construction supervision on the basis of the notice of the beginning of construction dated 12/14/2021 No. 14-04/21-STPRKP, vh. dated 12/20/2021 No. 40/07-09-123 , identification and suppression of violations of the requirements of the project documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources, legislation on 51, Parts 2, 3, 3.1, 6, Article 52 of the Urban Planning Code of the Russian Federation), The subject of this audit is: compliance with the mandatory requirements of urban planning legislation; compliance of the work and construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation of the project documentation (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of the Urban Planning Code of the Russian Federation), including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, the notice of the start of construction dated 12/14/2021 No. 14-04/21-STPRKP, ex. dated 12/20/2021 No. 40/07-09-123
# 562101397259
Unscheduled inspection
Start date: 2021-12-01, end date: —, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: implementation of regional state construction supervision on the basis of the inspection program dated 09/25/2021;
- the objectives of this audit are: prevention, identification and suppression of violations of the legislation on urban planning activities committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, project documentation (code 121.0.00-01 LLC "Design Bureau "Gorod"), approved in accordance with part h. 15, 15.2 and 15.3 of Articles 48 of the Urban Planning Code of the Russian Federation (including taking into account the changes made to the working documentation and which, in accordance with Part 1.3 of Article 52 of the Code, are part of such project documentation) (hereinafter referred to as project documentation).
compliance of the work performed and the construction materials and products used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the approved project documentation, the requirement for a construction permit;
requirements established by Parts 2 and 3.1 of art. 52 of this Code;
requirements to the procedure for carrying out construction control established by this Code and other regulatory legal acts.
inspection programs.
# 562101227357
Unscheduled inspection
Start date: 2021-10-21, end date: —, duration: 7
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: implementation of regional state construction supervision on the basis of the inspection program;
- the objectives of this audit are: prevention, detection and suppression of violations of legislation on urban planning activities committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, project documentation (code 121.0.00-01 LLC Design Bureau Gorod), approved in accordance with Part 15, 15.2 and 15.3 of Articles 48 of the Urban Planning Code of the Russian Federation (including taking into account the changes made to the working documentation and which, in accordance with Part 1.3 of Article 52 of the Code, are part of such project documentation) (hereinafter referred to as project documentation).
- the subject of this audit is compliance with:
1) compliance of the work performed and the construction materials and products used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the approved design documentation
2) building permit requirements;
3) the requirements established by Parts 2 and 3.1 of art. 52 of this Code;
4) requirements to the procedure for carrying out construction control, established by this Code and other regulatory legal acts.
5) Inspection programs.
# 562100631474
Unscheduled inspection
Start date: 2021-09-15, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection:
# 562100423249
Unscheduled inspection
Start date: 2021-08-18, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: - this inspection is carried out for the purpose of: implementing regional state construction supervision on the basis of the developer's notice dated 08/02/2021 No. 1 on the completion of the construction of the capital construction facility;
- the objectives of this audit are: to identify and prevent violations of the requirements of the legislation on urban planning (Part 2 of art. 51, Part 2, 3.1, 6 of art. 52, Part 2, 4 of art. 53 of the Urban Planning Code of the Russian Federation).
-the subject of this audit is: assessment of the conformity of completed works and applied building materials and products in the process the construction of a capital construction facility, as well as the results of such work, meet the requirements of the project documentation approved in accordance with parts 15,15.2 and 15.3 of Article 48 of this Code, cipher: 10.19-0.00-00 (positive expert opinion No. 56-2-1-2-013643-2020 dated 04/22/2020); (including taking into account the changes made to the working documentation and which, in accordance with Part 1.3 of Article 52 of this Code, are part of such project documentation) and (or) the information model (in the event that the formation and maintenance of information models are mandatory in accordance with the requirements of this Code); requirements for a construction permit; requirements established by Parts 2 and 3.1 of art. 52 of this Code; requirements for the procedure for carrying out construction control established by this Code and other regulatory legal acts; elimination of violations identified in the course of construction control and regional state construction supervision; registration and submission of executive documentation.
# 562100397246
Unscheduled inspection
Start date: 2021-07-29, end date: —, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: implementation of regional state construction supervision in accordance with the inspection program.
- the objectives of this audit are: to identify and prevent violations of the legislation on urban construction activities, project documentation, including the requirements for equipping a capital construction facility with metering devices for used energy resources.
7. The subject of this audit is to verify the compliance of the work performed and the construction materials and products used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the approved design documentation (including taking into account the changes made to the working documentation and which, in accordance with Part 1.3 of Article 52 of this Urban Planning Code, are part of such project documentation); compliance with the requirements of Parts 2, 3, 3.1 of art. 52 of the Urban Planning Code of the Russian Federation, elimination of violations detected during the implementation of construction control and state construction supervision, registration and submission of executive documentation, inspection programs.
# 562100280523
Unscheduled inspection
Start date: 2021-06-16, end date: —, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: - this inspection is carried out for the purpose of: implementing regional state construction supervision based on the inspection program approved on 09/18/2020.
- The objectives of this inspection are: to identify and prevent violations of the requirements of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources, legislation on urban development (part 51, part 2, 3, 3.1, 6, Article 52, Part 2, 4, Article 53 of the Urban Planning Code of the Russian Federation).
-the subject of this audit is: compliance with the mandatory requirements of urban planning legislation; compliance of the work performed and the building materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of art. 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the project documentation in accordance with Parts 3.8 and 3.9 of Articles 49 of the Urban Planning Code of the Russian Federation), including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources (item No. 2 of the inspection program dated 09/18/2020 - landscaping).
# 562105286050
Unscheduled inspection
Start date: 2021-01-15, end date: 2021-02-11, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms
Ensuring the observance and protection of citizens' labor rights and freedoms, including the right to safe working conditions
, compliance with mandatory requirements and (or) requirements established
by municipal legal acts
# 562005346434
Unscheduled inspection
Start date: 2020-11-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 562005150300
Unscheduled inspection
Start date: 2020-10-01, end date: 2020-10-08, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of completion of the capital construction facility dated 23092020 3 The objectives of this inspection are to identify and prevent violations of the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used legislation on urban development h 2 art 51 h 2 3 31 6 Art 52 h 2 4 7 Art 53 of the Urban Planning Code of the Russian Federation The subject of this audit is compliance with the mandatory requirements of urban planning legislation, compliance of the work and construction materials used during the reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, as amended included in the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used in the notice of completion of construction of the capital construction facility dated 23092020 3
# 562005150324
Unscheduled inspection
Start date: 2020-10-01, end date: 2020-10-08, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of completion of the capital construction facility dated 23092020 4 The objectives of this inspection are to identify and prevent violations of the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used legislation on urban development h 2 art 51 h 2 3 31 6 Art 52 h 2 4 7 Art 53 of the Urban Planning Code of the Russian Federation The subject of this audit is compliance with the mandatory requirements of urban planning legislation, compliance of work performed and construction materials used during the reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, as amended included in the design documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used in the notice of completion of construction of the capital construction facility dated 23092020 4
# 562004489479
Unscheduled inspection
Start date: 2020-08-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 562004489452
Unscheduled inspection
Start date: 2020-08-17, end date: 2020-08-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program dated 01062020. The objectives of this inspection are to identify and prevent violations of the requirements of the project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources legislation on urban development h 2 art 51 h 2 3 31 6 art 52 The Urban Planning Code of the Russian Federation
# 562004427283
Unscheduled inspection
Start date: 2020-06-09, end date: 2020-06-11, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision on the basis of the developer's notification dated 11052020 1 on the start of construction of a capital construction facility. The objectives of this inspection are to identify and suppress violations of the requirements of legislation on urban development h 2 art 51 h 2 3 31 5 6 art 52 h 2 4 Art 53 h 2 Art 55 of the Urban Planning Code The subject of this audit is compliance with the deadlines for the developer to send a notice of the start of construction of a capital construction facility compliance with urban planning legislation h 2 art 51 h 2 3 31 5 6 Art 52 h 2 4 Art 53 h 2 Art 55 of the Urban Planning Code of the Russian Federation
# 562004422575
Unscheduled inspection
Start date: 2020-05-28, end date: 2020-06-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: the implementation of regional state construction supervision on the basis of the notice of the beginning of construction dated 19052020 BN BX dated 19052020 7701the objectives of this audit are to identify and prevent violations of the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used legislation on urban development h 2 art 51 h 2 3 31 6 art 52 of the Urban Planning Code of the Russian Federation The subject of this audit is compliance with the mandatory requirements of urban planning legislation, compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 Articles 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for energy resources used notice of the start of construction dated 1905-2020 bn
# 562004422521
Unscheduled inspection
Start date: 2020-05-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002004301999
Unscheduled inspection
Start date: 2020-02-25, end date: 2020-02-26, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation of regulation 35180rp6 dated 29012020 issued by the West Ural Rostechnadzor Department of Orenburg Minerals JSC, the deadline for which has expired 14022019the task is to assess the compliance of activities or actions of omissions carried out by Orenburg Minerals JSC with the requirements established by federal laws and regulatory legal acts of the Russian Federation in the field of industrial safety adopted in accordance with them, Subject to verification of compliance with the regulations of state control and supervision bodies
# 002005228458
Unscheduled inspection
Start date: 2020-02-03, end date: 2020-02-05, duration: 3
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the fulfillment of a previously issued prescription
# 002004278291
Unscheduled inspection
Start date: 2020-02-03, end date: 2020-02-05, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking a previously issued prescription
# 002004225653
Unscheduled inspection
Start date: 2020-01-27, end date: 2020-01-29, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation of paragraphs 32 34 35 36 37 38 39 of Regulation 33GN4891rp163 dated 18102019, the deadline for which expired on 18112019 and paragraph 33 of Regulation 33GN4891rp163 dated 18102019 issued by the West Ural Rostechnadzor Department of Orenburg Minerals JSC, the deadline for which expired on 18122019the task is to assess the compliance of activities or actions omissions carried out by Orenburg Minerals JSC with the requirements established by federal laws and adopted in accordance with them, the regulatory legal acts of the Russian Federation in the field of industrial safety are subject to verification of compliance with the instructions of the state control and supervision authorities.
# 002004212620
Unscheduled inspection
Start date: 2020-01-27, end date: 2020-01-29, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation of paragraphs 32 34 35 36 37 38 39 of Regulation 33GN4891rp163 dated 18102019, the deadline for which expired on 18112019 and paragraph 33 of Regulation 33GN4891rp163 dated 18102019 issued by the West Ural Rostechnadzor Department of Orenburg Minerals JSC, the deadline for which expired on 18122019the task is to assess the compliance of activities or actions omissions carried out by Orenburg Minerals JSC with the requirements established by federal laws and adopted in accordance with them, the regulatory legal acts of the Russian Federation in the field of industrial safety are subject to verification of compliance with the instructions of the state control and supervision authorities.
# 002004202172
Unscheduled inspection
Start date: 2020-01-27, end date: 2020-01-31, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the implementation of the regulations issued earlier by Orenburg Minerals JSC dated 18102019 33GN4891rp163 items 21 33 for execution on 15122019
# 562004240486
Unscheduled inspection
Start date: 2020-01-24, end date: 2020-02-20, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms Accident Notice 566820IZ dated 21012020
# 001903924620
Unscheduled inspection
Start date: 2019-11-01, end date: 2019-11-29, duration: —
Authority: Uralskoe upravlenie gosudarstvennogo zheleznodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: regarding the implementation of the previously issued DB 561519 dated 24092019 upon expiration, the registration number of the function of the Federal Republic of Germany is 100014425 59
# 561903959067
Unscheduled inspection
Start date: 2019-11-14, end date: 2019-11-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: implementation of regional state construction supervision in accordance with the program of inspections, the objectives of this audit are to identify and suppress violations of the legislation on urban planning and project documentation committed by the developer, including the requirements for equipping the capital construction facility with metering devices for energy resources used. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility and also, the results of such work meet the requirements of project documentation, including the requirements of energy efficiency and the requirements of equipping a capital construction facility with metering devices for energy resources used, meeting the requirements of Parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation elimination of violations identified in the process of construction control and state construction supervision, registration and submission of executive documentation
# 561903979298
Unscheduled inspection
Start date: 2019-11-19, end date: 2019-11-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: implementation of regional state construction supervision on the basis of a notice of completion of construction the objectives of this audit are to identify and prevent violations of the requirements of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources legislation on urban development h 2 art 51 h 2 3 31 6 Art 52 of the Urban Planning Code of the Russian Federation the subject of this The verification is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with urban planning legislation h 2 art 51 h 2 3 31 6 Art 52 of the Urban Planning Code of the Russian Federation
# 561903973059
Unscheduled inspection
Start date: 2019-11-18, end date: 2019-12-05, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Orenburgskoi oblasti
Purpose of inspection: Compliance with the regulation dated 25102018 NNE2271
# 561903862043
Unscheduled inspection
Start date: 2019-10-25, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection:
# 561903517932
Unscheduled inspection
Start date: 2019-09-16, end date: 2019-10-03, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Orenburgskoi oblasti
Purpose of inspection: This audit is conducted in order to monitor the implementation of the order of the State Tax Service on the elimination of violations of fire safety requirements on the implementation of measures to ensure fire safety at protection facilities and to prevent the threat of fire from 05102018 2011the objectives of this audit are to verify compliance by organizations and citizens with fire safety requirements The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts and compliance with the regulations of state control bodies, supervision bodies of municipal control
# 561903483486
Unscheduled inspection
Start date: 2019-09-16, end date: 2019-09-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Orenburgskoi oblasti
Purpose of inspection: implementation of regional state construction supervision in accordance with the inspection program approved in 17052019 on the basis of the supervision order 210 dated 15052019. The objectives of this inspection are to identify and prevent violations of legislation on urban development activities by the developer, to perform work in accordance with the design documentation, including the requirements for equipping the capital construction facility with metering devices for energy resources used
# 561903372108
Unscheduled inspection
Start date: 2019-09-17, end date: 2019-09-30, duration: —
Authority: Gosudarstvennaya inspekciya truda v Orenburgskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms identifier of the state function 1001244260
# 001903384174
Unscheduled inspection
Start date: 2019-08-19, end date: 2019-08-27, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: organization of operation of electrical networks and installations
# 001802178728
Unscheduled inspection
Start date: 2018-12-12, end date: 2019-01-16, duration: —
Authority: Privolzhskoe mezhregionalnoe territorialnoe upravlenie Federalnogo agentstva po tehnicheskomu regulirovaniyu i metrologii
Purpose of inspection: Assessment of the fulfillment of the Prescription from 10102018 106 in connection with the expiration of the Task assessment of the conformity of measurements with established requirements Subject to verification compliance with mandatory requirements compliance with regulations
# 561801694326
Unscheduled inspection
Start date: 2018-09-25, end date: 2018-10-19, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Orenburgskoi oblasti
Purpose of inspection: monitoring the implementation of previously issued instructions to eliminate violations of mandatory requirements in the field of protection of the population and territories from emergency situations dated 11082017 11H
# 561801694324
Unscheduled inspection
Start date: 2018-09-25, end date: 2018-10-19, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Orenburgskoi oblasti
Purpose of inspection: control over the execution of the regulation on the elimination of violations of mandatory requirements in the field of civil defense dated 11082017 11th
# 561801694321
Unscheduled inspection
Start date: 2018-09-25, end date: 2018-10-19, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Orenburgskoi oblasti
Purpose of inspection: control over the execution of the GPN regulation on the elimination of violations of fire safety requirements on the implementation of measures to ensure fire safety at protection facilities and to prevent the threat of fire from 11082017 1911
# 561800200789
Unscheduled inspection
Start date: 2018-03-19, end date: 2018-04-13, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Orenburgskoi oblasti
Purpose of inspection: objectives execution of the order of the Federal Service for Supervision of Consumer Rights Protection and Human Well-being dated 15012018 10 "On conducting unscheduled on-site inspections of children's recreation and health improvement organizations in 2018" in order to implement the instructions of the Government of the Russian Federation dated 27122017 OGP128751 Tasks supervision and control over the implementation of mandatory requirements of the legislation of the Russian Federation in the field of sanitary and epidemiological The welfare of the population is the subject of compliance with mandatory requirements
# 56170802994394
Unscheduled inspection
Start date: 2017-10-23, end date: 2017-11-20, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Orenburgskoi oblasti
Purpose of inspection: This inspection is carried out in order to prevent damage to the rights legitimate interests of the life or health of citizens, the environment, cultural heritage sites, historical and cultural monuments of the peoples of the Russian Federation, and the defense and security of the state, the possibility of which is associated with the implementation by legal entities of activities related to the installation maintenance and repair of fire safety equipment for buildings and structures. The objectives of this inspection are to prevent identify and suppress violations a legal entity, its head and other officials, its authorized representatives of the requirements established by Federal Law No. 99 FZ dated 04052011 "On Licensing Certain Types of Activities" and Decree of the Government of the Russian Federation No. 30122011 1225 "On Licensing activities related to the installation, Maintenance and Repair of Fire Safety Equipment for Buildings and Structures"The subject of this audit is the compliance of the license applicant by the licensee with the licensing requirements when carrying out activities related to the installation maintenance and repair of fire safety equipment for buildings and structures
# 56170701826105
Unscheduled inspection
Start date: 2017-07-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 56170701826138
Unscheduled inspection
Start date: 2017-07-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 56170701826123
Unscheduled inspection
Start date: 2017-07-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160701258051
Unscheduled inspection
Start date: 2016-11-21, end date: 2016-12-29, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the implementation of the previously issued regulation 33GN171836rpo0802016 dated 04072016, the deadline for the execution of paragraphs 84 85 of which has expired
# 00160701028184
Unscheduled inspection
Start date: 2016-10-12, end date: 2016-10-12, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: ETL registration
# 00160700867866
Unscheduled inspection
Start date: 2016-08-10, end date: 2016-08-11, duration: —
Authority: Uralskoe upravlenie gosudarstvennogo zheleznodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: control
# 56160601784588
Unscheduled inspection
Start date: 2016-06-08, end date: 2016-06-28, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Orenburgskoi oblasti
Purpose of inspection: execution of the Order of the Federal Service for Supervision of Consumer Rights Protection and Human Welfare dated 19082014 876 "On measures to implement Decree of the President of the Russian Federation dated 06082014 560" issued in order to implement the instruction of the Government of the Russian Federation dated 08082014 ISHP1186PR Order of the Federal Service for Supervision of Consumer Rights Protection and Human Welfare dated 30062015 568 "On the extension of actions of the Rospotrebnadzor Order No. 876 dated 19082014" Order of the Federal Service for Supervision of Consumer Rights Protection and Human Welfare No. 222 dated 29032016 "On inspections of milk and dairy products" issued in order to implement the instructions of the Government of the Russian Federation, paragraph 3 of Part 1 of the minutes of the meeting of the Government Commission for Monitoring and Prompt Response to Changes in Food Market Conditions dated 1 March 2016 1 in accordance with p3 ch2 ct10 of the Federal Law of the Russian Federation dated 26122008g 294 FZ "On the Protection of the Rights of Legal Entities and Individual Entrepreneurs in the implementation of state control supervision of municipal control"
# 00160601601120
Unscheduled inspection
Start date: 2016-04-04, end date: 2016-04-15, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the implementation of a previously issued prescription
# 00160601505715
Unscheduled inspection
Start date: 2016-02-08, end date: 2016-02-10, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the fulfillment of the prescription
# 00150601278961
Unscheduled inspection
Start date: 2015-09-24, end date: 2015-10-06, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: determining the readiness of an enterprise to carry out a licensed type of activity
# 00150601265028
Unscheduled inspection
Start date: 2015-09-24, end date: 2015-10-06, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to verify the licensee's compliance with the licensing requirements for the operation of explosion- and fire-hazardous and chemically hazardous production facilities of hazard classes I II and III established by Federal Laws No. 04052011 99FZ "On licensing of certain types of activities" n 5 "Regulations on licensing the operation of explosion- and fire-hazardous and chemically hazardous production facilities of hazard classes I II and III" approved by decree of the Government of the Russian Federation Russian Federation No. 492 dated June 10, 2013
# 00150601265013
Unscheduled inspection
Start date: 2015-09-24, end date: 2015-10-06, duration: —
Authority: ZapadnoUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the completeness and reliability of the information contained in the application ex 01314057 dated 07092015 ex 0715739 dated 09092015 and the licensed materials and the compliance of the licensee of JSC Orenburg Minerals for the operation of explosive and fire hazardous and chemically hazardous production facilities of hazard classes I II and III with the licensing requirements established by Article 8 of the Federal Law of 04052011 99FZ "On Licensing Certain Types of Activities"