# 002005206205
Unscheduled inspection
Start date: 2020-10-30, end date: 2020-11-27, duration: 20
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: to monitor compliance of the performed works with project documentation requirements for energy saving and energy efficiency in the reconstruction of capital construction object on the basis of a programme of inspections the purpose of this test is to verify compliance with the mandatory requirements of the legislation on town-planning including project documentation and requirements on energy saving and increase of energy efficiency in the construction of capital construction object developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer the focus of this test is to check the compliance of contractors and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with parts 15 of 152 and 153 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources used in accordance with the program of carrying out checks of the building permit compliance with the requirements of parts 2 3 and 31 St 52 of the town planning code of the Russian Federation
# 002004218376
Unscheduled inspection
Start date: 2020-01-20, end date: 2020-02-14, duration: —
Authority: Upravlenie Federalnoi sluzhby po akkreditacii po Privolzhskomu federalnomu okrugu
Purpose of inspection: in order to verify the Report of the Federal State Budgetary Educational Institution of Higher Education Tolyatti State University on the elimination of identified inconsistencies ex dated 18122019 18753 ex PFO3205 dated 19122019 and the documents attached to the report on the elimination of identified inconsistencies with the accreditation criteria specified in the Notification of the Office of the Federal Accreditation Service for the Volga Federal District dated 29102019 PFO2185IZ The objectives of this audit are to ensure compliance with the requirements of the legislation of the Russian Federation in the field of accreditation, including Federal Law No. 412 FZ dated 28122013 "On Accreditation in the National Accreditation System"Order of the Ministry of Economic Development of the Russian Federation No. 326 dated 30052014 "On approval of the criteria for accreditation of the list of documents confirming the applicant's compliance with the accredited person's accreditation criteria and the list of documents in the field of standardization, compliance with the requirements of which by applicants accredited persons ensures their compliance with the accreditation criteria"The subject of this audit is the observance of mandatory requirements or requirements established by municipal legal acts and the observance by an accredited person in the course of carrying out activities of the mandatory requirements of the legislation of the Russian Federation for the activities of accredited persons.
# 001904393126
Unscheduled inspection
Start date: 2019-12-16, end date: 2020-01-20, duration: —
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to monitor the compliance of completed works with design documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility based on the inspection program Case 2492 "TSU Indoor Swimming Pool" located at the address Samara region, Tolyatti Central District south of the building with the address 59 Ushakov Street, the objectives of this audit are to verify compliance with mandatory requirements of legislation on urban development including project documentation, as well as requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility by the developer, the technical customer, as well as the person carrying out the construction on the basis of a contract with the developer or the technical customer
# 632100298530
Unscheduled inspection
Start date: 2021-06-28, end date: —, duration: 10
Authority: Sredne-Povolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the design documentation, the requirements for energy conservation and energy efficiency improvement during the reconstruction of the capital construction facility, based on the inspection program (Case No. 2668) - "Reconstruction of the Tolyatti State University building Complex. TSU training and production workshops "Central district, Belorusskaya str., 14B", at the address: 445020, Russian Federation, Samara region, Tolyatti, Belorusskaya str., 14B;
The objectives of this audit are: to verify compliance with the mandatory requirements of legislation on urban development, including project documentation, as well as requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility, by the developer, the technical customer, as well as the person carrying out construction on the basis of a contract with the developer or technical customer
# 632100298612
Unscheduled inspection
Start date: 2021-06-23, end date: —, duration: 10
Authority: Sredne-Povolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to control the compliance of the completed works with the design documentation, requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility, based on the notice of completion of construction (Case No. 2492) - TSU Indoor Swimming Pool, located at the address: Samara region, Tolyatti, Central district, south of the building with the address Ushakov St., 59;
The objectives of this audit are: to verify compliance with the mandatory requirements of legislation on urban development, including design documentation, as well as requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility, by the developer, the technical customer, as well as the person carrying out construction on the basis of a contract with the developer or technical customer
# 632100105921
Unscheduled inspection
Start date: 2021-04-05, end date: 2021-04-30, duration: —
Authority: Gosudarstvennaya inspekciya truda v Samarskoi oblasti
Purpose of inspection: control over the execution by a legal entity or individual entrepreneur of a previously issued instruction on the elimination of an identified violation of mandatory labor requirements, the deadline for which has expired, ensuring compliance with labor legislation and protection of labor rights, compliance with the instructions of state control (supervision) bodies, municipal control bodies;
conducting events
# 632100158040
Unscheduled inspection
Start date: 2021-04-26, end date: 2021-05-11, duration: 10
Authority: Sredne-Povolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the design documentation, the requirements for energy conservation and energy efficiency improvement during the reconstruction of the capital construction facility, based on the inspection program "Reconstruction of the Tolyatti State University building complex. TSU training and production workshops "Central district, Belorusskaya str., 14B", at the address: 445020, Russian Federation, Samara region, Tolyatti, Belorusskaya str., 14B;
The objectives of this audit are: to verify compliance with the mandatory requirements of legislation on urban development, including project documentation, as well as requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility, by the developer, the technical customer, as well as the person carrying out construction on the basis of a contract with the developer or technical customer
# 632100083496
Unscheduled inspection
Start date: 2021-03-12, end date: 2021-03-18, duration: 5
Authority: Sredne-Povolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to verify the facts stated in the citizen's appeal (vh. No. 09-00-05/1229 dated 02/25/2021) and motivated submission dated 03/05/2021 No. 301-6592;
The objectives of this audit are: to verify compliance with the mandatory requirements of legislation on urban development, including project documentation, as well as requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility, by the developer, the technical customer, as well as the person carrying out construction on the basis of a contract with the developer or technical customer.
The subject of this check is:
verification of the facts stated in the citizen's appeal (vh. No.09-00-05/1229 dated 02/25/2021);
verification of the compliance of the work performed and the building materials used during the construction, reconstruction of a capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of the Urban Planning Code of the Civil Code of the Russian Federation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and equipment requirements for capital construction facilities accounting for the energy resources used; availability of a building permit; compliance with the requirements of parts 2, 3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.
# 632100051923
Unscheduled inspection
Start date: 2021-02-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002005206205
Unscheduled inspection
Start date: 2020-10-30, end date: 2020-11-27, duration: 20
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: to monitor compliance of the performed works with project documentation requirements for energy saving and energy efficiency in the reconstruction of capital construction object on the basis of a programme of inspections the purpose of this test is to verify compliance with the mandatory requirements of the legislation on town-planning including project documentation and requirements on energy saving and increase of energy efficiency in the construction of capital construction object developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer the focus of this test is to check the compliance of contractors and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with parts 15 of 152 and 153 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources used in accordance with the program of carrying out checks of the building permit compliance with the requirements of parts 2 3 and 31 St 52 of the town planning code of the Russian Federation
# 002004485664
Unscheduled inspection
Start date: 2020-08-13, end date: 2020-08-26, duration: 10
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: to monitor compliance of the performed works with project documentation requirements for energy saving and energy efficiency in the reconstruction of capital construction object on the basis of a programme of inspections the purpose of this test is to verify compliance with the mandatory requirements of the legislation on town-planning including project documentation and requirements on energy saving and increase of energy efficiency in the construction of capital construction object developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer the focus of this test is to check the compliance of contractors and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with parts 15 of 152 and 153 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources used in accordance with the program of carrying out checks of the building permit compliance with the requirements of parts 2 3 and 31 St 52 of the town planning code of the Russian Federation
# 002004433494
Unscheduled inspection
Start date: 2020-05-14, end date: 2020-06-10, duration: 20
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: to monitor compliance of the performed works with project documentation requirements for energy saving and energy efficiency in the reconstruction of capital construction object on the basis of a programme of inspections the purpose of this test is to verify compliance with the mandatory requirements of the legislation on town-planning including project documentation and requirements on energy saving and increase of energy efficiency in the construction of capital construction object developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer the focus of this test is to check the compliance of contractors and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with parts 15 of 152 and 153 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources used in accordance with the program of carrying out checks of the building permit compliance with the requirements of parts 2 3 and 31 St 52 of the town planning code of the Russian Federation
# 632004205942
Unscheduled inspection
Start date: 2020-01-27, end date: 2020-02-21, duration: —
Authority: Gosudarstvennaya inspekciya truda v Samarskoi oblasti
Purpose of inspection: implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms
# 002004218376
Unscheduled inspection
Start date: 2020-01-20, end date: 2020-02-14, duration: —
Authority: Upravlenie Federalnoi sluzhby po akkreditacii po Privolzhskomu federalnomu okrugu
Purpose of inspection: in order to verify the Report of the Federal State Budgetary Educational Institution of Higher Education Tolyatti State University on the elimination of identified inconsistencies ex dated 18122019 18753 ex PFO3205 dated 19122019 and the documents attached to the report on the elimination of identified inconsistencies with the accreditation criteria specified in the Notification of the Office of the Federal Accreditation Service for the Volga Federal District dated 29102019 PFO2185IZ The objectives of this audit are to ensure compliance with the requirements of the legislation of the Russian Federation in the field of accreditation, including Federal Law No. 412 FZ dated 28122013 "On Accreditation in the National Accreditation System"Order of the Ministry of Economic Development of the Russian Federation No. 326 dated 30052014 "On approval of the criteria for accreditation of the list of documents confirming the applicant's compliance with the accredited person's accreditation criteria and the list of documents in the field of standardization, compliance with the requirements of which by applicants accredited persons ensures their compliance with the accreditation criteria"The subject of this audit is the observance of mandatory requirements or requirements established by municipal legal acts and the observance by an accredited person in the course of carrying out activities of the mandatory requirements of the legislation of the Russian Federation for the activities of accredited persons.
# 001904393126
Unscheduled inspection
Start date: 2019-12-16, end date: 2020-01-20, duration: —
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to monitor the compliance of completed works with design documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility based on the inspection program Case 2492 "TSU Indoor Swimming Pool" located at the address Samara region, Tolyatti Central District south of the building with the address 59 Ushakov Street, the objectives of this audit are to verify compliance with mandatory requirements of legislation on urban development including project documentation, as well as requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility by the developer, the technical customer, as well as the person carrying out the construction on the basis of a contract with the developer or the technical customer
# 001904164499
Unscheduled inspection
Start date: 2019-09-16, end date: 2019-10-11, duration: —
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the mandatory requirements of the design documentation for energy conservation and energy efficiency improvement during the construction of a capital construction facility based on the inspection program Case 2492 "TSU Indoor Swimming Pool" located at the address Samara region, Tolyatti Central District south of the building with the address 59 Ushakov Street, the objectives of this inspection are to prevent identify and prevent the also, a person carrying out construction on the basis of a contract with a developer or customer for violations of legislation on urban planning activities, including design documentation, the subject of this audit is the compliance of the work performed and the materials used during the construction of the specified capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with energy metering devices resources in accordance with the program for conducting inspections of the availability of a construction permit and the availability of a construction permit to comply with the requirements of Parts 2 and 3 of Art 52 of the Urban Planning Code of the Russian Federation
# 631902963743
Unscheduled inspection
Start date: 2019-08-26, end date: 2019-09-20, duration: —
Authority: Gosudarstvennaya inspekciya truda v Samarskoi oblasti
Purpose of inspection: compliance with the requirements of labor legislation and other regulatory legal acts containing labor law norms
# 631902638371
Unscheduled inspection
Start date: 2019-04-10, end date: 2019-04-26, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Samarskoi oblasti
Purpose of inspection: execution of the order of the Deputy Chairman of the Government of the Russian Federation dated January 29, 2019 YUBP4628
# 001800392577
Unscheduled inspection
Start date: 2018-04-10, end date: 2018-04-12, duration: —
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the fulfillment of the prescription from 05032018g 104850318004P2
# 63170701534796
Unscheduled inspection
Start date: 2017-03-13, end date: 2017-04-14, duration: —
Authority: Glavnoe upravlenie Ministerstva vnutrennih del Rossiiskoi Federacii po Samarskoi oblasti
Purpose of inspection: control over the execution of traffic police regulations from 07022017 6541155
# 63160601762893
Unscheduled inspection
Start date: 2016-08-01, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya truda v Samarskoi oblasti
Purpose of inspection: compliance with labor laws
# 00150601413368
Unscheduled inspection
Start date: 2015-12-07, end date: 2015-12-11, duration: —
Authority: Federalnaya sluzhba po nadzoru v sfere obrazovaniya i nauki
Purpose of inspection: The purpose is to verify the information contained in the report on the monitoring of the higher education system approved by Deputy Head of Rosobrnadzor AYU Biserov 02112015the task is the implementation of federal state supervision in the field of education, the implementation of federal state quality control of education for educational programsaccidence by the licensee of the legislation of the Russian Federation in the field of education, assessment of the compliance of the content and quality of training of students in accordance with state-accredited educational programs federal state educational standards
# 63150601441080
Unscheduled inspection
Start date: 2015-10-30, end date: —, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Samarskoi oblasti
Purpose of inspection: Consideration of the application bx 51 dated 26102015 of the Tolyatti State University TSU for the reissue of the license for activities in the field of the use of ionizing radiation sources generating, except if these sources are used in medical activities, the storage of ionizing radiation sources for X-ray diffraction analysis of X-ray flaw detection