Found 39 inspections:

# 77180803276129
Unscheduled inspection
Start date: 2018-11-14, end date: 2018-11-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803223323
Unscheduled inspection
Start date: 2018-09-10, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803200668
Unscheduled inspection
Start date: 2018-08-10, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803193833
Unscheduled inspection
Start date: 2018-08-02, end date: 2018-08-10, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803172852
Unscheduled inspection
Start date: 2018-07-03, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803172105
Unscheduled inspection
Start date: 2018-07-03, end date: 2018-07-06, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803176090
Unscheduled inspection
Start date: 2018-06-29, end date: 2018-07-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803170980
Unscheduled inspection
Start date: 2018-06-29, end date: 2018-07-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803154135
Unscheduled inspection
Start date: 2018-06-04, end date: 2018-06-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803152498
Unscheduled inspection
Start date: 2018-06-04, end date: 2018-07-02, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803143733
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-05-25, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803144200
Unscheduled inspection
Start date: 2018-05-21, end date: 2018-05-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803106756
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-27, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803103822
Unscheduled inspection
Start date: 2018-03-19, end date: 2018-03-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803102047
Unscheduled inspection
Start date: 2018-03-16, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803097619
Unscheduled inspection
Start date: 2018-03-07, end date: 2018-03-07, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803086637
Unscheduled inspection
Start date: 2018-02-20, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803079176
Unscheduled inspection
Start date: 2018-01-18, end date: 2018-01-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803064455
Unscheduled inspection
Start date: 2018-01-18, end date: 2018-01-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170803039424
Unscheduled inspection
Start date: 2017-12-29, end date: —, duration:
Authority:
Purpose of inspection:


# 77170802923909
Unscheduled inspection
Start date: 2017-12-18, end date: 2017-12-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170802815594
Unscheduled inspection
Start date: 2017-11-07, end date: 2017-12-04, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170802884423
Unscheduled inspection
Start date: 2017-11-22, end date: 2017-11-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170802645965
Unscheduled inspection
Start date: 2017-10-02, end date: 2017-10-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170802562703
Unscheduled inspection
Start date: 2017-09-21, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701889892
Unscheduled inspection
Start date: 2017-08-28, end date: 2017-09-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170801929512
Unscheduled inspection
Start date: 2017-08-21, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77170701841764
Unscheduled inspection
Start date: 2017-07-31, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701671996
Unscheduled inspection
Start date: 2017-06-19, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701635329
Unscheduled inspection
Start date: 2017-05-23, end date: 2017-06-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701632153
Unscheduled inspection
Start date: 2017-05-22, end date: 2017-06-02, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701516097
Unscheduled inspection
Start date: 2017-04-05, end date: 2017-04-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701509494
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701467994
Unscheduled inspection
Start date: 2017-03-28, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701473832
Unscheduled inspection
Start date: 2017-03-27, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701403584
Unscheduled inspection
Start date: 2017-02-21, end date: 2017-03-10, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701403837
Unscheduled inspection
Start date: 2017-02-21, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701330488
Unscheduled inspection
Start date: 2017-01-25, end date: 2017-02-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77160601719186
Unscheduled inspection
Start date: 2016-07-19, end date: 2016-07-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the audit is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of an approved verification program. The objectives of this audit are to prevent, identify and suppress violations of technical regulations and design documentation committed by the person being audited. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation, including requirements for energy efficiency and requirements for the equipment of the capital construction facility with metering devices for energy resources used


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.