# 631800619394
Unscheduled inspection
Start date: 2018-08-13, end date: 2018-08-24, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Vypolnenie ranee vydannogo predpisaniya 01050805301 ot 15062018
# 631800380220
Unscheduled inspection
Start date: 2018-05-30, end date: 2018-06-15, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63170701832287
Unscheduled inspection
Start date: 2017-07-31, end date: 2017-08-04, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Predpisanie ot 10042017 02231341 Proverka ranee vydannogo predpisaniya
# 63170701495069
Unscheduled inspection
Start date: 2017-04-04, end date: —, duration: —
Authority: —
Purpose of inspection: