# 77190803394354
Unscheduled inspection
Start date: 2019-04-12, end date: 2019-04-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803370449
Unscheduled inspection
Start date: 2019-03-14, end date: 2019-03-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803081312
Unscheduled inspection
Start date: 2018-02-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803075180
Unscheduled inspection
Start date: 2018-02-01, end date: 2018-02-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 771800175937
Unscheduled inspection
Start date: 2018-02-26, end date: 2018-03-17, duration: —
Authority: Upravlenie po voprosam migracii Glavnogo upravleniya Ministerstva vnutrennih del Rossiiskoi Federacii po gorodu Moskve
Purpose of inspection: identification of violations of the provisions of federal laws of 25072002 115 FZ "On the legal status of foreign citizens in the Russian Federation" of 15081996 114 FZ "On the procedure for leaving the Russian Federation and entering the Russian Federation" of 18072006 109 FZ "On migration registration of foreign citizens and stateless persons in the Russian Federation" suppression of administrative offenses responsibility for committing which are provided for in Chapters 18-19 of the Special Part of the Code of the Russian Federation on Migration compliance by a legal entity or an individual entrepreneur with the mandatory requirements of current legislation in the field of migration
# 77170802379450
Unscheduled inspection
Start date: 2017-09-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 50170701855655
Unscheduled inspection
Start date: 2017-06-19, end date: 2017-06-22, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: proverki ispolneniya predpisaniya ot 04052017 0908068400504 so srokom vypolneniya do 05062017 ocenka sootvetstviya vypolnyaemyh rabot trebovaniyam tehnicheskih reglamentov i proektnoi dokumentacii na obekte kapitalnogo stroitelstva Stadion Meteor Krytyi futbolnyi manezh po adresu Moskovskaya oblast g Balashiha ul Pobedy vladenie 1
# 77170701368736
Unscheduled inspection
Start date: 2017-02-13, end date: 2017-03-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77160700973924
Unscheduled inspection
Start date: 2016-10-04, end date: 2016-10-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: proverka provoditsya s celyu ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narusheniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 947516 ot 19092016
# 77160700142623
Unscheduled inspection
Start date: 2016-09-07, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: