Found 3 inspections:

# 631903483468
Unscheduled inspection
Start date: 2019-09-20, end date: 2019-10-17, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 631902951617
Unscheduled inspection
Start date: 2019-08-19, end date: 2019-09-13, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Vypolnenie ranee vydannogo predpisaniya 01050804591 ot 21062019 izveschenie 3454 ot 06082019


# 631902784849
Unscheduled inspection
Start date: 2019-06-13, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.