# 631903574326
Unscheduled inspection
Start date: 2019-09-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 631902966063
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-09-24, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631902897191
Unscheduled inspection
Start date: 2019-08-01, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection:
# 631902742789
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-06-28, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: The inspection program dated 30102017 Checks the compliance of the work performed and the building materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used
# 631902632245
Unscheduled inspection
Start date: 2019-04-12, end date: 2019-04-30, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631902537463
Unscheduled inspection
Start date: 2019-03-04, end date: 2019-03-22, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631802161165
Unscheduled inspection
Start date: 2018-12-10, end date: 2018-12-28, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631801777128
Unscheduled inspection
Start date: 2018-10-04, end date: 2018-10-26, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631800575701
Unscheduled inspection
Start date: 2018-08-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 631800091612
Unscheduled inspection
Start date: 2018-03-01, end date: 2018-03-27, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63180803025280
Unscheduled inspection
Start date: 2018-01-15, end date: 2018-01-31, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Inspection program dated 30102017 notification dated 19122017 5878 Verification of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 63170802937691
Unscheduled inspection
Start date: 2017-12-11, end date: 2017-12-27, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Inspection program dated 30102017 notification dated 29112017 5360 Verification of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 63170802821212
Unscheduled inspection
Start date: 2017-11-13, end date: 2017-11-30, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Inspection program dated 30102017 notification dated 31102017 4722 Verification of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 63170701845670
Unscheduled inspection
Start date: 2017-08-02, end date: 2017-08-03, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Inspection program dated 29/122014 notification dated 26072017 2952 Verification of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 63170701787907
Unscheduled inspection
Start date: 2017-07-17, end date: 2017-07-31, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Inspection program dated 29/122014 notification dated 05072017 2611 Verification of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 63170701686605
Unscheduled inspection
Start date: 2017-06-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 63170701549773
Unscheduled inspection
Start date: 2017-05-15, end date: 2017-05-31, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Inspection program dated 29/122014 notification dated 13042017 1318 Verification of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 63170701490074
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-21, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Inspection program dated 29/122014 notification dated 22032017 982 Verification of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 63170701282825
Unscheduled inspection
Start date: 2017-01-09, end date: 2017-01-25, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Inspection program dated 29/122014 notification dated 26/122016 7260 Verification of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 63160701092375
Unscheduled inspection
Start date: 2016-11-14, end date: 2016-11-30, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160700915032
Unscheduled inspection
Start date: 2016-10-10, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection:
# 63160601747511
Unscheduled inspection
Start date: 2016-08-04, end date: 2016-08-12, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160601792153
Unscheduled inspection
Start date: 2016-08-12, end date: 2016-08-12, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used