# 632100188083
Unscheduled inspection
Start date: 2021-05-11, end date: 2021-05-14, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used.
# 632100069459
Unscheduled inspection
Start date: 2021-03-18, end date: 2021-03-26, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used.
# 631904121908
Unscheduled inspection
Start date: 2019-12-20, end date: 2019-12-23, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631904125588
Unscheduled inspection
Start date: 2019-12-23, end date: 2019-12-24, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631904068894
Unscheduled inspection
Start date: 2019-12-09, end date: 2019-12-11, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631903986062
Unscheduled inspection
Start date: 2019-11-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 631903898731
Unscheduled inspection
Start date: 2019-10-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 631903853493
Unscheduled inspection
Start date: 2019-10-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 631903641989
Unscheduled inspection
Start date: 2019-09-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 631800635286
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-08-31, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631800580079
Unscheduled inspection
Start date: 2018-07-27, end date: 2018-08-03, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63170802859595
Unscheduled inspection
Start date: 2017-11-17, end date: 2017-11-24, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Programma provedeniya proverok ot 06102017 izveschenie ot 09112017 4903 Proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov
# 63170802777564
Unscheduled inspection
Start date: 2017-10-30, end date: 2017-11-03, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Programma provedeniya proverok ot 06102017 izveschenie ot 19102017 4493 Proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov
# 63170701661062
Unscheduled inspection
Start date: 2017-05-24, end date: 2017-06-21, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya Samarskoi oblasti
Purpose of inspection: proverki svedenii izlozhennyh v obraschenii vh 10053c ot 26042017