Found 15 inspections:

# 772100272968
Unscheduled inspection
Start date: 2021-06-07, end date: 2021-06-09, duration: 3
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 772100144577
Unscheduled inspection
Start date: 2021-04-14, end date: 2021-05-13, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772005171631
Unscheduled inspection
Start date: 2020-10-06, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772004216452
Unscheduled inspection
Start date: 2020-02-03, end date: 2020-02-28, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, the subject of verification is the fulfillment by the person carrying out the construction of the requirements of part 3 of Article 52 of the Urban Planning Code compliance with the performance of works and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such works with the requirements of design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used


# 772004225063
Unscheduled inspection
Start date: 2020-01-27, end date: —, duration:
Authority:
Purpose of inspection:


# 771903937091
Unscheduled inspection
Start date: 2019-11-08, end date: —, duration:
Authority:
Purpose of inspection:


# 771903645953
Unscheduled inspection
Start date: 2019-09-24, end date: 2019-09-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with checking the fulfillment of the prescriptionthe tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development activity by the audited person. The purpose of the audit is to verify the elimination of violations specified in the prescription issued by Mosgosstroynadzor


# 77190803490317
Unscheduled inspection
Start date: 2019-09-02, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803477311
Unscheduled inspection
Start date: 2019-08-14, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803249583
Unscheduled inspection
Start date: 2018-10-15, end date: 2018-10-19, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803215966
Unscheduled inspection
Start date: 2018-08-31, end date: 2018-09-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803136176
Unscheduled inspection
Start date: 2018-05-10, end date: 2018-05-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803107534
Unscheduled inspection
Start date: 2018-03-23, end date: —, duration:
Authority:
Purpose of inspection:


# 77170803026404
Unscheduled inspection
Start date: 2017-12-28, end date: —, duration:
Authority:
Purpose of inspection:


# 77170802870067
Unscheduled inspection
Start date: 2017-11-17, end date: 2017-11-21, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.