Found 95 inspections:

# 002004343512
Unscheduled inspection
Start date: 2020-03-05, end date: 2020-03-05, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the activities of a legal entity of an individual entrepreneur in connection with the expiration of the deadline for the execution of an order issued by the state supervisory authority on the elimination of identified violations of mandatory requirements 4512od159PR of 31.012020 the tasks of this audit are to monitor the measures taken by a legal entity of an individual entrepreneur to comply with the order prevention detection and suppression of violations of mandatory requirements established by federal laws and other regulatory acts of the Russian Federation in the field of industrial the adoption of measures provided for by the legislation of the Russian Federation to prevent and or eliminate the consequences of identified violations


# 002004369779
Unscheduled inspection
Start date: 2020-03-20, end date: 2020-04-02, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: to control the activities of legal licengineering entrepreneurs on compliance with legislation on town-planning of binding rules and regulations during the construction of the facility in connection with the notice of completion from 11032020 bn BX 2407104 from 11032020 Objectives of this review are to exercise control over the observance of legal entities, individual entrepreneurs of the requirements of the legislation on town-planning of binding rules and regulations warning detection and suppression of violations of legislation on town-planning including project documents the Subject of this review is to mark the right observance of obligatory requirements of the legislation on town-planning dejatelnostnyj works and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of this Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices used energy resourcevalue permission to stroitelstvoimoti persons engaged in the construction of the requirements of parts 2 and 3 of article 31 of 52 town planning code of Rivapalacio the requirements of state control surveillance


# 002004369733
Unscheduled inspection
Start date: 2020-03-20, end date: 2020-03-24, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal licindividual entrepreneurs in compliance with the requirements of legislation on urban planning mandatory norms and rules during the construction of a capital construction facility in order to verify the fulfillment of regulation 161321366379PR32 of 19022020 on notification of the elimination of violations of bn of 10032020 bx 2407103 of 11032020, the tasks of this audit are to monitor compliance by legal entities individual entrepreneurs with the requirements of legislation on urban development mandatory norms and rules prevention detection and suppression of violations of the legislation on urban planning activities, including project documentationthe subject of this audit is the fulfillment of the instructions of the state control and supervision bodies


# 002004234785
Unscheduled inspection
Start date: 2020-01-30, end date: —, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001903949191
Unscheduled inspection
Start date: 2019-11-12, end date: 2019-11-18, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: It is carried out in order to control the activities of legal licindividual entrepreneurs in compliance with the requirements of the legislation on urban development of mandatory norms and rules during the construction of a capital construction facility in order to verify the fulfillment of regulation 23128942552406PR298 of 11092019 on notification of the elimination of violations of 23102019 bn bx 1114280 of 28102019 The objectives of this audit are to monitor compliance by legal entities individual entrepreneurs with the requirements of legislation on urban development The purpose of this audit is to comply with the requirements of the state control and supervision bodies


# 001903946287
Unscheduled inspection
Start date: 2019-11-12, end date: 2019-11-29, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal licindividual entrepreneurs in compliance with the requirements of legislation on urban planning mandatory norms and rules during the construction of a capital construction facility in connection with the notification of bn dated 28102019 on the completion of construction of the facility bx 1114286 dated 28102019, the tasks of this audit are to monitor compliance by legal entities individual entrepreneurs with the requirements of legislation on urban planning mandatory norms and rules prevention detection and the suppression of violations of the legislation on urban planning activities, including design documentationthe subject of this audit is V compliance with the mandatory requirements of the legislation on urban planning activities V compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which the requirements energy efficiency does not apply to the requirements of equipping a capital construction facility with metering devices for used energy resources V availability of a construction permit v compliance by persons carrying out construction with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation V compliance with the instructions of state control and supervision bodies


# 001903853800
Unscheduled inspection
Start date: 2019-10-09, end date: —, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001903002498
Unscheduled inspection
Start date: 2019-09-05, end date: 2019-10-02, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal entities and individual entrepreneurs in compliance with the requirements of legislation on urban planning mandatory norms and rules during the construction of a capital construction facility in connection with the notice of completion of construction bn dated 16082019 bx 186257 dated 19082019, the tasks of this audit are to monitor compliance by legal entities and individual entrepreneurs with the requirements of legislation on urban planning mandatory norms and rules prevention detection and suppression of violations of legislation on urban development activities, including design documentationthe subject of this audit is V compliance with the mandatory requirements of legislation on urban development activities V compliance of work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction projects for which the requirements of energy efficiency efficiency does not apply to the requirements of equipping a capital construction facility with metering devices for used energy resources V availability of a construction permit v compliance by persons carrying out construction with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation V compliance with the instructions of state control and supervision bodies


# 001902903628
Unscheduled inspection
Start date: 2019-08-15, end date: —, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001902903447
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-14, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal licindividual entrepreneurs in compliance with the requirements of legislation on urban development mandatory norms and rules during the construction of a capital construction facility in order to verify the fulfillment of regulation 231151939584Pr38 of 15032019, the deadline for which has expired, except for paragraph 56, the objectives of this audit are to monitor compliance by legal entities individual entrepreneurs with the requirements of legislation on urban development mandatory norms and rules warning identification and suppression of violations of the legislation on urban planning activities, including project documentation, compliance with the instructions of state control and supervision bodies


# 00170802825039
Unscheduled inspection
Start date: 2017-10-30, end date: 2017-10-30, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the regulation of 29032017 3981pndsp1099PR


# 00170701708180
Unscheduled inspection
Start date: 2017-06-13, end date: —, duration:
Authority: SeveroZapadnoe territorialnoe upravlenie Federalnogo agentstva po rybolovstvu
Purpose of inspection:


# 00170701415476
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-03-23, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Novgorodskoi oblasti
Purpose of inspection: according to the consumer's complaint


# 00160701235054
Unscheduled inspection
Start date: 2016-12-30, end date: 2017-02-02, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the activities of legal entities and individual entrepreneurs in compliance with the requirements of legislation on urban development mandatory norms and rules during the construction of a capital construction facility the objectives of this audit are to monitor compliance by legal entities and individual entrepreneurs with the requirements of legislation on urban development mandatory norms and rules prevention detection and suppression of violations of legislation on urban development, including technical regulations and project documentation. The purpose of this check is to note the necessary compliance with the mandatory requirements of the legislation on urban planning activity, the compliance of the work and the construction materials used in the construction process of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, the execution by persons carrying out construction requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation compliance with the instructions of state control and supervision bodies


# 00160701140535
Unscheduled inspection
Start date: 2016-11-18, end date: —, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00160601732485
Unscheduled inspection
Start date: 2016-07-21, end date: —, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00160601703375
Unscheduled inspection
Start date: 2016-07-12, end date: 2016-08-08, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the activities of legal licindividual entrepreneurs in compliance with the requirements of the legislation on urban development, mandatory norms and rules during the construction of a capital construction facility


# 00160601513369
Unscheduled inspection
Start date: 2016-02-19, end date: —, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Novgorodskoi oblasti
Purpose of inspection: Renewal of the license


# 00150601428926
Unscheduled inspection
Start date: 2015-11-18, end date: —, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the activities of legal licindividual entrepreneurs in compliance with the requirements of the legislation on urban development, mandatory norms and rules during the construction of a capital construction facility


# 532101468207
Unscheduled inspection
Start date: 2021-12-15, end date: 2021-12-28, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novgorodskoi oblasti
Purpose of inspection: verification of the execution of the issued instruction on the elimination of the detected violation, verification of the execution of the issued instruction on the elimination of the detected violation, Regulation No. 27-21 of 10/22/2021


# 532101406462
Unscheduled inspection
Start date: 2021-11-15, end date: —, duration:
Authority:
Purpose of inspection:


# 532100401863
Unscheduled inspection
Start date: 2021-08-02, end date: 2021-08-13, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novgorodskoi oblasti
Purpose of inspection: verification of the works specified in the notification, determination of compliance of the completed stage of work with the requirements of design and working documentation, installation of technological pipelines, landscaping of the territory


# 532100327538
Unscheduled inspection
Start date: 2021-06-30, end date: —, duration: 1
Authority: Glavnoe upravlenie MCHS Rossii po Novgorodskoi oblasti
Purpose of inspection: this check is carried out for the purpose of: monitoring the execution of the previously issued to the person being checked order on the elimination of violations of fire safety requirements No. 32/1/1 dated 06/03/20210, the deadline for which was extended until 06/23/2021; The subject of this inspection is: the fulfillment of the previously issued to the person being checked order on the elimination of violations of fire safety requirements No. 32/1/1 dated 06/03/2021. The objectives of this audit are: control over the execution of the previously issued instruction to the person being checked on the elimination of violations of fire safety requirements No. 32/1/1 dated 06/03/2021.


# 782100349026
Unscheduled inspection
Start date: 2021-06-29, end date: —, duration: 9
Authority: Severo-Zapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring compliance with the requirements of legislation on urban development


# 782100327387
Unscheduled inspection
Start date: 2021-06-29, end date: —, duration: 2
Authority: Severo-Zapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the activities of a legal entity in connection with the expiration of the deadline for the execution of the order issued by the state supervisory authority on the elimination of identified violations of mandatory requirements dated 04/15/2021 No. 45-1302-843/pr; The objectives of this review are: - control over the measures taken by a legal entity (individual entrepreneur) to comply with the order; - prevention, detection and suppression of violations of mandatory requirements established by federal laws and other regulatory acts of the Russian Federation in the field of industrial safety (mandatory requirements); - taking measures provided for by the legislation of the Russian Federation to prevent and (or) eliminate the consequences of the violations identified; The subject is the fulfillment of the instructions of the state control (supervision) bodies, municipal control bodies


# 532100321679
Unscheduled inspection
Start date: 2021-06-28, end date: 2021-07-12, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novgorodskoi oblasti
Purpose of inspection: Compliance with the order of construction of the ACS, verification of completion of works provided for in the inspection program, Compliance with the order of construction of the ACS


# 532100245002
Unscheduled inspection
Start date: 2021-06-01, end date: —, duration:
Authority:
Purpose of inspection:


# 532105319787
Unscheduled inspection
Start date: 2021-01-25, end date: —, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Novgorodskoi oblasti
Purpose of inspection:


# 532105319846
Unscheduled inspection
Start date: 2021-01-25, end date: —, duration:
Authority:
Purpose of inspection:


# 532004453047
Unscheduled inspection
Start date: 2020-07-09, end date: 2020-08-05, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Novgorodskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with mandatory requirements of labor legislation and other normative legal acts containing norms of labor law Appeal 53791120OB from06072020


# 532004473704
Unscheduled inspection
Start date: 2020-07-14, end date: —, duration:
Authority:
Purpose of inspection:


# 002004343512
Unscheduled inspection
Start date: 2020-03-05, end date: 2020-03-05, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the activities of a legal entity of an individual entrepreneur in connection with the expiration of the deadline for the execution of an order issued by the state supervisory authority on the elimination of identified violations of mandatory requirements 4512od159PR of 31.012020 the tasks of this audit are to monitor the measures taken by a legal entity of an individual entrepreneur to comply with the order prevention detection and suppression of violations of mandatory requirements established by federal laws and other regulatory acts of the Russian Federation in the field of industrial the adoption of measures provided for by the legislation of the Russian Federation to prevent and or eliminate the consequences of identified violations


# 002004369779
Unscheduled inspection
Start date: 2020-03-20, end date: 2020-04-02, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: to control the activities of legal licengineering entrepreneurs on compliance with legislation on town-planning of binding rules and regulations during the construction of the facility in connection with the notice of completion from 11032020 bn BX 2407104 from 11032020 Objectives of this review are to exercise control over the observance of legal entities, individual entrepreneurs of the requirements of the legislation on town-planning of binding rules and regulations warning detection and suppression of violations of legislation on town-planning including project documents the Subject of this review is to mark the right observance of obligatory requirements of the legislation on town-planning dejatelnostnyj works and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of this Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices used energy resourcevalue permission to stroitelstvoimoti persons engaged in the construction of the requirements of parts 2 and 3 of article 31 of 52 town planning code of Rivapalacio the requirements of state control surveillance


# 002004369733
Unscheduled inspection
Start date: 2020-03-20, end date: 2020-03-24, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal licindividual entrepreneurs in compliance with the requirements of legislation on urban planning mandatory norms and rules during the construction of a capital construction facility in order to verify the fulfillment of regulation 161321366379PR32 of 19022020 on notification of the elimination of violations of bn of 10032020 bx 2407103 of 11032020, the tasks of this audit are to monitor compliance by legal entities individual entrepreneurs with the requirements of legislation on urban development mandatory norms and rules prevention detection and suppression of violations of the legislation on urban planning activities, including project documentationthe subject of this audit is the fulfillment of the instructions of the state control and supervision bodies


# 532004252256
Unscheduled inspection
Start date: 2020-01-29, end date: 2020-02-26, duration:
Authority: SeveroVostochnoe Mezhregionalnoe upravlenie gosudarstvennogo avtodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: the inspection is carried out in order to comply with the previously issued instruction dated 24/122019 7632, the deadline for which expired on 28.012019. The objectives of this inspection are to identify and suppress violations of regulatory legal normative technical acts standards and norms regulating the activities of the motor transport complex. The subject of this inspection is to comply with the instructions of state control and supervision bodies


# 002004234785
Unscheduled inspection
Start date: 2020-01-30, end date: 2020-02-19, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal entities and individual entrepreneurs in compliance with the requirements of legislation on urban development mandatory norms and rules during the construction of a capital construction facility in accordance with the inspection program dated 21102019, the objectives of this audit are to monitor compliance by legal entities and individual entrepreneurs with the requirements of legislation on urban development mandatory norms and rules prevention detection and suppression of violations of legislation on urban development The purpose of this audit is to note the necessary compliance with the mandatory requirements of legislation on urban planning activities, compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in in accordance with parts 38 and 39 of Article 49 of this Code and or an information model, if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used on construction fulfillment by persons carrying out construction of the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 532004259435
Unscheduled inspection
Start date: 2020-01-31, end date: 2020-02-27, duration:
Authority: Gosudarstvennaya inspekciya truda v Novgorodskoi oblasti
Purpose of inspection: Control over the execution by a legal entity or an individual entrepreneur of a previously issued order to eliminate an identified violation of mandatory labor requirements, the fulfillment of which has expired


# 001904088973
Unscheduled inspection
Start date: 2019-12-10, end date: 2019-12-12, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal licindividual entrepreneurs in compliance with the requirements of legislation on urban development mandatory norms and rules during the construction of a capital construction facility in order to verify the fulfillment of regulation 23128966123285PR472 of 29112019, the deadline for which has expired, the objectives of this audit are to monitor compliance by legal entities individual entrepreneurs with the requirements of legislation on urban development mandatory norms and rules prevention detection and suppression violations of the legislation on urban planning activities, including project documentation, the subject of this audit is the fulfillment of the instructions of the state control and supervision bodies


# 531904133188
Unscheduled inspection
Start date: 2019-12-12, end date: 2020-01-16, duration:
Authority: SeveroVostochnoe Mezhregionalnoe upravlenie gosudarstvennogo avtodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: the inspection is carried out in order to prevent possible harm to the life and health of citizens specified in the Submission dated 11122019 157 submitted by the Deputy head of the Territorial Department of the State Highway Supervision in the Novgorod region, Northeastern MUGADN Riskulov JUS Accident report dated 05122019 CUSP25757 The objectives of this inspection are to identify and suppress violations of regulatory legal normative technical acts standards and norms regulating the activities of the motor transport complex The subject of this inspection is compliance mandatory requirements established by legal acts


# 001903949191
Unscheduled inspection
Start date: 2019-11-12, end date: 2019-11-18, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: It is carried out in order to control the activities of legal licindividual entrepreneurs in compliance with the requirements of the legislation on urban development of mandatory norms and rules during the construction of a capital construction facility in order to verify the fulfillment of regulation 23128942552406PR298 of 11092019 on notification of the elimination of violations of 23102019 bn bx 1114280 of 28102019 The objectives of this audit are to monitor compliance by legal entities individual entrepreneurs with the requirements of legislation on urban development The purpose of this audit is to comply with the requirements of the state control and supervision bodies


# 001903946287
Unscheduled inspection
Start date: 2019-11-12, end date: 2019-11-29, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal licindividual entrepreneurs in compliance with the requirements of legislation on urban planning mandatory norms and rules during the construction of a capital construction facility in connection with the notification of bn dated 28102019 on the completion of construction of the facility bx 1114286 dated 28102019, the tasks of this audit are to monitor compliance by legal entities individual entrepreneurs with the requirements of legislation on urban planning mandatory norms and rules prevention detection and the suppression of violations of the legislation on urban planning activities, including design documentationthe subject of this audit is V compliance with the mandatory requirements of the legislation on urban planning activities V compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which the requirements energy efficiency does not apply to the requirements of equipping a capital construction facility with metering devices for used energy resources V availability of a construction permit v compliance by persons carrying out construction with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation V compliance with the instructions of state control and supervision bodies


# 001903853800
Unscheduled inspection
Start date: 2019-10-09, end date: 2019-10-10, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal licindividual entrepreneurs in compliance with the requirements of legislation on urban development mandatory norms and rules during the construction of a capital construction facility in order to verify the fulfillment of regulation 23128248882709PR336 dated 02102019, the deadline for which has expired, the objectives of this audit are to monitor compliance by legal entities individual entrepreneurs with the requirements of legislation on urban development mandatory norms and rules prevention detection and suppression violations of the legislation on urban planning activities, including project documentation, the subject of this audit is the fulfillment of the instructions of the state control and supervision bodies


# 531903826479
Unscheduled inspection
Start date: 2019-10-07, end date: 2019-11-01, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Novgorodskoi oblasti
Purpose of inspection: Verification of the information indicated in the appeal of residents of the d Vitka d Trubichino d Strelka of the Novgorod district as well as the Krechevitsy microdistrict of Veliky Novgorod letter ex dated 19092019 PR8311 and vh dated 25092019 107z the objectives of this audit are to prevent identify and suppress violations by a legal entity by its head and other officials of the requirements established in accordance with international treaties of the Russian Federation federal laws and adopted in in accordance with them, other regulatory legal acts of the Russian Federation in the field of environmental protection and nature management Comply with mandatory requirements and or requirements established by municipal legal acts to prevent harm to the life and health of citizens, harm to animals, plants and the environment


# 001903002498
Unscheduled inspection
Start date: 2019-09-05, end date: 2019-10-02, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal entities and individual entrepreneurs in compliance with the requirements of legislation on urban planning mandatory norms and rules during the construction of a capital construction facility in connection with the notice of completion of construction bn dated 16082019 bx 186257 dated 19082019, the tasks of this audit are to monitor compliance by legal entities and individual entrepreneurs with the requirements of legislation on urban planning mandatory norms and rules prevention detection and suppression of violations of legislation on urban development activities, including design documentationthe subject of this audit is V compliance with the mandatory requirements of legislation on urban development activities V compliance of work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction projects for which the requirements of energy efficiency efficiency does not apply to the requirements of equipping a capital construction facility with metering devices for used energy resources V availability of a construction permit v compliance by persons carrying out construction with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation V compliance with the instructions of state control and supervision bodies


# 531902935673
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-08-23, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Novgorodskoi oblasti
Purpose of inspection: prevention detection suppression of violations of the legislation of the Russian Federation in the field of ensuring sanitary and epidemiological welfare of the population consumer protection and compliance with mandatory requirements for goods works services


# 001902903628
Unscheduled inspection
Start date: 2019-08-15, end date: 2019-09-11, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal entities and individual entrepreneurs in compliance with the requirements of legislation on urban development mandatory norms and rules during the construction of a capital construction facility in connection with the inspection program from 28052019 bn, the objectives of this audit are to monitor compliance by legal entities and individual entrepreneurs with the requirements of legislation on urban development mandatory norms and rules prevention detection and suppression of violations of legislation on urban development The subject of this audit is compliance with the mandatory requirements of the legislation on urban development activities, compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements of equipment of the facility capital construction with metering devices for energy resources used


# 531902984449
Unscheduled inspection
Start date: 2019-08-19, end date: 2019-08-29, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Novgorodskoi oblasti
Purpose of inspection: implementation of subparagraph 71 of paragraph 7 of the protocol of the operational meeting of the Security Council of the Russian Federation dated 300-52019 approved by the President of the Russian Federation 06062019


# 001902903447
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-14, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal licindividual entrepreneurs in compliance with the requirements of legislation on urban development mandatory norms and rules during the construction of a capital construction facility in order to verify the fulfillment of regulation 231151939584Pr38 of 15032019, the deadline for which has expired, except for paragraph 56, the objectives of this audit are to monitor compliance by legal entities individual entrepreneurs with the requirements of legislation on urban development mandatory norms and rules warning identification and suppression of violations of the legislation on urban planning activities, including project documentation, compliance with the instructions of state control and supervision bodies


# 531902945733
Unscheduled inspection
Start date: 2019-08-08, end date: 2019-08-16, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Novgorodskoi oblasti
Purpose of inspection: This audit is carried out in order to fulfill the order of the Government of the Russian Federation dated July 30, 2019 YBP46516THE tasks of this audit are to assess the compliance of activities carried out by a legal entity, an individual entrepreneur, or actions of inaction with mandatory fire safety requirements. The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts


# 531902879761
Unscheduled inspection
Start date: 2019-07-12, end date: 2019-07-26, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novgorodskoi oblasti
Purpose of inspection: The subject of this audit is the fulfillment of the instruction of the inspection of the state construction supervision of the Novgorod region 1119 of 15052019 The purpose of checking the verification of the elimination of violations of mandatory requirements specified in the notice of the person carrying out construction on the elimination of identified violations UA428B of 01072019 UA450B of 10072019the tasks of this audit are the prevention detection and suppression of violations of the legislation on urban development by the developer, the technical customer and the person carrying out construction, including technical regulations and project documentation


# 531902879753
Unscheduled inspection
Start date: 2019-07-12, end date: 2019-07-26, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novgorodskoi oblasti
Purpose of inspection: The subject of the audit is the fulfillment of the instruction of the inspection of the State construction supervision of the Novgorod Region 1219 of 20052019the tasks of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer and the person carrying out the construction, verification of the elimination of violations of mandatory requirements specified in the notice of the person carrying out the construction on the elimination of violations identified UA441B from 08072019


# 531902812686
Unscheduled inspection
Start date: 2019-06-19, end date: —, duration:
Authority: Gosudarstvennaya inspekciya truda v Novgorodskoi oblasti
Purpose of inspection:


# 531902759397
Unscheduled inspection
Start date: 2019-05-29, end date: 2019-05-31, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novgorodskoi oblasti
Purpose of inspection: verification of the execution of the issued instruction on the elimination of the identified violation 0719 of 13032019the tasks of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer and the person carrying out the construction


# 531902639834
Unscheduled inspection
Start date: 2019-04-05, end date: 2019-05-07, duration:
Authority: SeveroVostochnoe Mezhregionalnoe upravlenie gosudarstvennogo avtodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: the audit is carried out in order to verify the compliance of the information contained in the application and documents of a legal entity or individual entrepreneur for the provision of a special permit license issuance of a permit approval with the mandatory requirements of the application dated 01042019 5312lits the objectives of this audit are to identify and suppress violations of regulatory legal normative technical acts standards and norms regulating the activities of the motor transport complex 7 The subject of this audit is the compliance of the information contained in the the application and documents of a legal entity or individual entrepreneur for granting the legal status of a special permit license for the right to carry out certain types of activities or permit approval for other legally significant actions if the conduct of an appropriate unscheduled inspection of a legal entity individual entrepreneur is provided for by the rules for granting the legal status of a special permit license issuance of a permit approval of mandatory requirements as well as data on these legal entities and individual entrepreneurs contained in the unified state register of legal entities the unified state register of individual entrepreneurs and other federal information resources


# 001902567069
Unscheduled inspection
Start date: 2019-03-19, end date: 2019-04-15, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal entities and individual entrepreneurs in compliance with the requirements of legislation on urban development mandatory norms and rules during the construction of a capital construction facility in accordance with the inspection program from 11022019 bn, the objectives of this audit are to monitor compliance by legal entities and individual entrepreneurs with the requirements of legislation on urban development mandatory norms and rules prevention detection and suppression of violations of legislation on urban development The subject of this audit is compliance with the mandatory requirements of the legislation on urban planning activities compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements of design documentation including energy efficiency requirements with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements of equipment of the capital construction facility with metering devices for energy resources used availability of a construction permit compliance by persons carrying out construction with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 531902588626
Unscheduled inspection
Start date: 2019-03-21, end date: 2019-04-17, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Novgorodskoi oblasti
Purpose of inspection: control of elimination of violations of fire safety requirements specified in the regulation on elimination of identified violations of fire safety requirements specified in paragraphs 1 2 3 of the regulation on elimination of violations of fire safety requirements dated 27052016 9611 identification suppression and prevention of possible violations of fire safety requirements systematic monitoring of compliance with fire safety requirements compliance with regulations of state control supervision of municipal control bodies


# 531902520260
Unscheduled inspection
Start date: 2019-02-18, end date: —, duration:
Authority:
Purpose of inspection:


# 531902520190
Unscheduled inspection
Start date: 2019-02-18, end date: —, duration:
Authority:
Purpose of inspection:


# 531902552787
Unscheduled inspection
Start date: 2019-02-21, end date: 2019-03-21, duration:
Authority: Gosudarstvennaya inspekciya truda v Novgorodskoi oblasti
Purpose of inspection: implementation of state control over compliance with labor legislation


# 531902526991
Unscheduled inspection
Start date: 2019-02-21, end date: 2019-03-21, duration:
Authority: Gosudarstvennaya inspekciya truda v Novgorodskoi oblasti
Purpose of inspection: implementation of state control over compliance with labor legislation


# 531802157129
Unscheduled inspection
Start date: 2018-12-04, end date: 2018-12-24, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Novgorodskoi oblasti
Purpose of inspection: The purpose of checking the fulfillment of the instruction on the elimination of violations of the legislation of the Russian Federation in the field of nature management and environmental protection identified as a result of the audit 27 dated 29062018 with a deadline of 20112018 The objectives of this audit are to comply with the requirements of the environmental legislation of the Russian Federation in the use of the Volkhov river water body Subject to compliance with the instructions of state control supervision bodies of municipal control bodies


# 531802326798
Unscheduled inspection
Start date: 2018-12-18, end date: 2018-12-21, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Novgorodskoi oblasti
Purpose of inspection: this inspection is carried out in order to fulfill the Order of the Government of the Russian Federation dated 16112018 g YUBP47987. The objectives of this inspection are to identify, suppress and prevent possible violations of fire safety requirements and carry out systematic monitoring of compliance with fire safety requirements


# 531802172653
Unscheduled inspection
Start date: 2018-11-22, end date: —, duration:
Authority:
Purpose of inspection:


# 531801009697
Unscheduled inspection
Start date: 2018-09-11, end date: 2018-09-17, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Novgorodskoi oblasti
Purpose of inspection: Objectives verification of compliance with the regulation dated 06042018 13 on the elimination of violations of the environmental legislation of the Russian Federation identified as a result of the audit Tasks verification of the elimination of violations of the environmental legislation of the Russian Federation in the field of waste management expressed in the fact that Public Joint Stock Company "Akron" hereinafter PJSC "Akron" Company in the performance of work on the disposal of waste "il excess biological treatment facilities and mixed wastewater" hazard class IV code according to FCKO 7 22 220 013 94, which was formed at biological treatment facilities in Veliky Novgorod, does not observe a time interval of no more than 7 days between its spreading and embedding in the soil on land plot A of a land plot with cadastral number 531119004027 located at the address having address landmarks Novgorod region Novgorod district Trubichinskoye rural settlement in the central part of the cadastral quarter Subject to compliance with the instructions of the state control bodies supervision of municipal control bodies


# 531801008756
Unscheduled inspection
Start date: 2018-09-04, end date: —, duration:
Authority:
Purpose of inspection:


# 531800651148
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-09-03, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Novgorodskoi oblasti
Purpose of inspection: the inspection is carried out in order to comply with subparagraph 51 of paragraph 5 of the protocol of the operational meeting of the Security Council of the Russian Federation of 19072018 approved by the President of the Russian Federation 28072018. The objectives of this inspection are to identify, suppress and prevent possible violations of fire safety requirements________________________________________________________________________ implementation of systematic monitoring of compliance with fire safety requirements_


# 531800422855
Unscheduled inspection
Start date: 2018-05-29, end date: 2018-06-20, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Novgorodskoi oblasti
Purpose of inspection: The real test is conducted to check the feasibility to license requirements and conditions for the implementation of activities for the collection transport treatment disposal disposal disposal of waste I IV hazard classes through the collection of waste of hazard class waste collection IV class of danger transportation of waste I hazard class II waste transport hazard class transportation of waste of hazard class of waste transport hazard class of waste of hazard class IV waste class II hazard waste hazard class waste disposal III hazard class waste disposal hazard class on the basis of statements of Public joint stock company "Akron" incoming 2188 from 14052018 "For renewal of license" The objectives of this review are to verify compliance with the legislation of the Russian Federation in the field of licensing of the Subject of this review is compliance with the compliance of the information contained in the statement and the documents of the legal entity or the individual entrepreneur on the legal status of a special permit of license to conduct certain types of activities or resolution of approval for the implementation of other legal actions if the conducting unscheduled inspections of the legal entity the individual entrepreneur provided the rules for the provision of the legal status of a special permit a license authorizing approval of the mandatory requirements as well as data about the specified legal entities and individual entrepreneurs contained in the unified state register of legal entities and the unified state register of individual entrepreneurs and other Federal information resources


# 001800277216
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-04-27, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the activities of legal entities and individual entrepreneurs in compliance with the requirements of legislation on urban development of mandatory norms and rules during the construction of a capital construction facility in accordance with the audit program dated 26012018 bn agreed with PJSC ACRON, the objectives of this audit are to monitor compliance by legal entities and individual entrepreneurs with the requirements of legislation on urban development of mandatory norms and rules prevention detection and suppression violations of legislation on urban planning activities, including technical regulations and design documentation compliance with mandatory requirements of legislation on urban planning activities compliance of work and construction materials used during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of design documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices used energy resources availability of a building permit compliance by persons carrying out construction with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 531800194043
Unscheduled inspection
Start date: 2018-03-12, end date: —, duration:
Authority:
Purpose of inspection:


# 531800190331
Unscheduled inspection
Start date: 2018-03-12, end date: 2018-03-23, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Novgorodskoi oblasti
Purpose of inspection: the audit is carried out in order to monitor the implementation of the previously issued instruction dated May 27, 2016 on the 16th to eliminate violations of established requirements in the field of civil defense The objectives of this audit are to identify, suppress and prevent possible violations of requirements in the field of civil defense, carry out systematic monitoring of compliance with requirements in the field of civil defense, the subject of the audit is compliance with the instructions of state control bodies, supervision of municipal bodies control


# 531800190304
Unscheduled inspection
Start date: 2018-03-12, end date: 2018-03-23, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Novgorodskoi oblasti
Purpose of inspection: this audit is carried out in order to control the elimination of violations of fire safety requirements specified in the regulation on the elimination of violations of fire safety requirements dated 27052016 9411, the deadline for which expired on December 31, 2017, paragraphs 105 155 156 170 171 220 231 the objectives of this audit are to identify, suppress and prevent possible violations of fire safety requirements, carry out systematic monitoring of compliance with fire safety requirements the subject of the inspection is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies


# 00170802825039
Unscheduled inspection
Start date: 2017-10-30, end date: 2017-10-30, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the regulation of 29032017 3981pndsp1099PR


# 53170701798046
Unscheduled inspection
Start date: 2017-07-10, end date: 2017-08-04, duration:
Authority: Gosudarstvennaya inspekciya truda v Novgorodskoi oblasti
Purpose of inspection: protection of the rights and interests of employees in connection with the consideration of the appeal of 22062017 760017OB On violation of labor rights Supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms


# 53170701816911
Unscheduled inspection
Start date: 2017-07-07, end date: 2017-08-03, duration:
Authority: Gosudarstvennaya inspekciya truda v Novgorodskoi oblasti
Purpose of inspection: implementation of federal state supervision over the employer's compliance with labor legislation and other regulatory legal acts containing labor law norms in accordance with the consideration of the Rostrud Order of 19052017 364


# 53170701752817
Unscheduled inspection
Start date: 2017-07-03, end date: 2017-07-28, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Novgorodskoi oblasti
Purpose of inspection: This audit is conducted in order to control the elimination of violations of fire safety requirements specified in the regulation on the elimination of violations of fire safety requirements dated 27052016 9811, the deadline for which expired on June 01, 2017The objectives of this audit are to identify, suppress and prevent possible violations of fire safety requirements, carry out systematic monitoring of compliance with fire safety requirements. The subject of this audit is to comply with the instructions of state control bodies supervision bodies municipal control


# 53170701752778
Unscheduled inspection
Start date: 2017-07-03, end date: 2017-07-28, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Novgorodskoi oblasti
Purpose of inspection: This audit is conducted in order to control the elimination of violations of fire safety requirements specified in the regulation on the elimination of violations of fire safety requirements dated 27052016 9411, the deadline for which expired on June 01, 2017The objectives of this audit are to identify, suppress and prevent possible violations of fire safety requirements, carry out systematic monitoring of compliance with fire safety requirements. The subject of this audit is to comply with the instructions of state control bodies, supervision bodies municipal control


# 00170701708180
Unscheduled inspection
Start date: 2017-06-13, end date: 2017-06-19, duration:
Authority: SeveroZapadnoe territorialnoe upravlenie Federalnogo agentstva po rybolovstvu
Purpose of inspection: compliance with the instructions of the state control bodies, supervision of municipal control bodies in order to verify the implementation of regulation 12 of 14062016 on the elimination of identified violations issued by the Municipal Unitary Enterprise Novgorodsky Vodokanal by an official of the Northwestern Territorial Administration of the Federal Agency for Fisheries, the deadline for which expired on 01062017


# 53170701586122
Unscheduled inspection
Start date: 2017-05-17, end date: 2017-05-30, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Novgorodskoi oblasti
Purpose of inspection: The purpose of the audit is to verify the implementation of the regulation of 14112016 93 on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements The objectives of this audit are to verify the elimination of violations of environmental legislation of the Russian Federation in the field of waste management expressed in the placement of waste at operated facilities not included in the list of the main purpose of this audit is to comply with the instructions of state control bodies supervision of municipal control bodies


# 00170701503265
Unscheduled inspection
Start date: 2017-04-06, end date: 2017-05-04, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the activities of legal entities and individual entrepreneurs in compliance with the requirements of legislation on urban development mandatory norms and rules during the construction of a capital construction facility in accordance with the notice of completion of construction dated 27032017 17 vx 124517 dated 28032017, the objectives of this audit are to monitor compliance by legal entities and individual entrepreneurs with the requirements of legislation on urban development mandatory norms and rules prevention detection and suppression of violations of legislation on urban development activities, including technical regulations and project documentation 7 The subject of this audit is to note the necessary compliance with the mandatory requirements of legislation on urban development activities, compliance of work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements the equipment of the capital construction facility with metering devices for the energy resources used, the presence of a construction permit by persons carrying out construction of the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation, Compliance with the instructions of state control and supervision bodies


# 00170701415476
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-03-23, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Novgorodskoi oblasti
Purpose of inspection: according to the consumer's complaint


# 00160701235054
Unscheduled inspection
Start date: 2016-12-30, end date: 2017-02-02, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the activities of legal entities and individual entrepreneurs in compliance with the requirements of legislation on urban development mandatory norms and rules during the construction of a capital construction facility the objectives of this audit are to monitor compliance by legal entities and individual entrepreneurs with the requirements of legislation on urban development mandatory norms and rules prevention detection and suppression of violations of legislation on urban development, including technical regulations and project documentation. The purpose of this check is to note the necessary compliance with the mandatory requirements of the legislation on urban planning activity, the compliance of the work and the construction materials used in the construction process of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, the execution by persons carrying out construction requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation compliance with the instructions of state control and supervision bodies


# 00160701140535
Unscheduled inspection
Start date: 2016-11-18, end date: 2016-12-15, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The objectives of this audit are to monitor compliance by legal entities and individual entrepreneurs with the requirements of legislation on urban development and mandatory norms and rules to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation The subject of this audit is to note the necessary compliance with the requirements of state control and supervision bodies


# 53160701071334
Unscheduled inspection
Start date: 2016-11-08, end date: —, duration:
Authority:
Purpose of inspection:


# 53160601792813
Unscheduled inspection
Start date: 2016-08-08, end date: 2016-09-02, duration:
Authority: Gosudarstvennaya inspekciya truda v Novgorodskoi oblasti
Purpose of inspection: implementation of the instructions of the Deputy Chairman of the Government of the Russian Federation OYU Golodets dated July 18, 2016 OGP124289


# 53160700590714
Unscheduled inspection
Start date: 2016-08-18, end date: 2016-08-26, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Novgorodskoi oblasti
Purpose of inspection: prevention detection suppression of violations of the legislation of the Russian Federation in the field of ensuring sanitary and epidemiological welfare of the population consumer protection and compliance with mandatory requirements for goods works services


# 53160700432133
Unscheduled inspection
Start date: 2016-07-27, end date: 2016-08-15, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Novgorodskoi oblasti
Purpose of inspection: prevention detection suppression of violations of the legislation of the Russian Federation in the field of ensuring sanitary and epidemiological welfare of the population consumer protection and compliance with mandatory requirements for goods works services


# 00160601732485
Unscheduled inspection
Start date: 2016-07-21, end date: 2016-08-17, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the activities of legal licindividual entrepreneurs in compliance with the requirements of the legislation on urban development, mandatory norms and rules during the construction of a capital construction facility


# 00160601703375
Unscheduled inspection
Start date: 2016-07-12, end date: 2016-08-08, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the activities of legal licindividual entrepreneurs in compliance with the requirements of the legislation on urban development, mandatory norms and rules during the construction of a capital construction facility


# 00160601703282
Unscheduled inspection
Start date: 2016-07-19, end date: 2016-08-15, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the activities of legal licindividual entrepreneurs in compliance with the requirements of the legislation on urban development, mandatory norms and rules during the construction of a capital construction facility


# 00160601613247
Unscheduled inspection
Start date: 2016-05-18, end date: 2016-06-15, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the activities of legal licindividual entrepreneurs in compliance with the requirements of the legislation on urban development, mandatory norms and rules during the construction of a capital construction facility


# 53160601542657
Unscheduled inspection
Start date: 2016-04-04, end date: —, duration:
Authority:
Purpose of inspection:


# 00160601513369
Unscheduled inspection
Start date: 2016-02-19, end date: —, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Novgorodskoi oblasti
Purpose of inspection: Renewal of the license


# 00150601428926
Unscheduled inspection
Start date: 2015-11-18, end date: —, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the activities of legal licindividual entrepreneurs in compliance with the requirements of the legislation on urban development, mandatory norms and rules during the construction of a capital construction facility


# 53150600014098
Unscheduled inspection
Start date: 2015-07-06, end date: —, duration:
Authority:
Purpose of inspection:


# 53150600020876
Unscheduled inspection
Start date: 2015-07-30, end date: 2015-08-10, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Novgorodskoi oblasti
Purpose of inspection: ensuring sanitary and epidemiological well-being of a person, consumer protection and compliance with mandatory requirements for goods, works and services


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.