# 002005201303
Unscheduled inspection
Start date: 2020-11-02, end date: 2020-12-09, duration: 27
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to comply with the order of the head of the Federal Service for Environmental Technological and Nuclear Supervision dated 29092020 379 issued in pursuance of the order of the Government of the Russian Federation dated 22092020 YUBP911478 of the order of the head of the Far Eastern Department of the Federal Service for Environmental Technological and Nuclear Supervision dated 06102020 PR372406 The tasks of this inspection are the prevention detection and suppression of violations by legal entities engaged in industrial safety activities their managers and other officials of the requirements in the field of industrial safety for taking measures provided for by the legislation of the Russian Federation to suppress prevent and or eliminate identified violations, the subject of this audit is compliance by a legal entity in the course of carrying out activities with mandatory requirements in the field of industrial safety as well as compliance with the specified requirements of used buildings premises structures technical devices equipment and materials of ongoing technological processes
# 001902758381
Unscheduled inspection
Start date: 2019-06-03, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001902550546
Unscheduled inspection
Start date: 2019-03-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001902443074
Unscheduled inspection
Start date: 2019-02-19, end date: 2019-02-20, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the implementation of the previously issued instruction on the elimination of identified violations from 13092018 PA71965 paragraphs 1, the deadline for which expires on 01022019 2, the deadline for which expired on 01012019
# 00170801950087
Unscheduled inspection
Start date: 2017-09-01, end date: 2017-09-15, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution of JSC "Urgalugol" previously issued by the Far Eastern Department of Rostechnadzor regulation PA71474 dated June 27, 2017 item 11, the deadline for which expired on July 10, 2017 items 1 3 4 10, the deadline for which expired on July 25, 2017 item 2, the deadline for which expired on August 1, 2017 items 5 8 9, the deadline for the execution of which expires on September 1, 2017, the objectives of this audit are to monitor the measures taken by the legal entity to comply with the order
# 00170701775043
Unscheduled inspection
Start date: 2017-07-10, end date: 2017-07-21, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution of JSC "Urgalugol" previously issued by the Far Eastern Department of Rostechnadzor regulations dated April 27, 2017 PA71291 dated April 27, 2017 dated February 26, 2017 PA7195
# 00170701775042
Unscheduled inspection
Start date: 2017-07-10, end date: 2017-07-21, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution of JSC "Urgalugol" previously issued by the Far Eastern Department of Rostechnadzor regulations dated April 27, 2017 PA71291 dated April 27, 2017 dated February 26, 2017 PA7195
# 00170701413912
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-03-22, duration: —
Authority: Departament Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Dalnevostochnomu federalnomu okrugu
Purpose of inspection: execution by a legal entity of JSC "Urgalugol" issued by the Department of Rosprirodnadzor for the Far Eastern Federal District of the order on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements dated July 25, 2016 08407202016
# 00160700175661
Unscheduled inspection
Start date: 2016-09-02, end date: 2016-09-29, duration: —
Authority: Departament Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Dalnevostochnomu federalnomu okrugu
Purpose of inspection: Objectives verification of the fulfillment by JSC Urgalugol of the instruction on the elimination of violations of the conditions of use of a water body identified as a result of verification issued by the Department of Rosprirodnadzor for the Far Eastern Federal District based on the results of a planned on-site inspection 08307202016 of 25072016 "To develop an action plan to ensure wastewater discharges, including drainage waters, into the Ruchbolyshye Satanki water body Verkhnebureinsky district Khabarovsk Territory in accordance with the requirement The Water Code of the Russian Federation from 03062006 74FZ deadline for execution 31082016 Tasks identification suppression prevention of violations of mandatory requirements of environmental legislation of the Russian Federation Subject to verification information contained in the documents of JSC "Urgalugol" related to the execution of the instruction on the elimination of violations of the conditions of use of a water body identified as a result of verification from 25072016 08307202016
# 00160700175611
Unscheduled inspection
Start date: 2016-09-02, end date: 2016-09-29, duration: —
Authority: Departament Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Dalnevostochnomu federalnomu okrugu
Purpose of inspection: Objectives verification of the fulfillment by the legal entity of JSC Urgalugol of the instruction on the elimination of violations of the conditions of use of a water body identified as a result of the inspection issued by the Department of Rosprirodnadzor for the Far Eastern Federal District based on the results of a planned on-site inspection 08207202016 of 25072016 "To develop an action plan to achieve standards for the volume of discharge and content of pollutants in wastewater discharged into the water body Ruchbolyshye Satanki Verkhnebureinsky District Khabarovsk Territory including drainage waters in accordance with pp9 10 p23 of the Decision on the provision of a water body for use from 30032015 27200305001RRSBHS20150116600" deadline 31082016 Tasks identification suppression prevention of violations of mandatory requirements of environmental legislation of the Russian Federation Subject to verification contained in the documents of JSC "Urgalugol" information related to the execution of the order on the elimination of violations of the conditions of use of a water body identified as a result of verification from 25072016 08207202016
# 00160700049014
Unscheduled inspection
Start date: 2016-09-02, end date: 2016-09-21, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: objectives control of the execution of the previously issued by the Far Eastern Department of Rostechnadzor of the order dated June 14, 2016 PA71387 in terms of points 1 2 3 4 5 6 7 10 11 14 15 the deadline for the execution of which has expired is the implementation of control over the measures taken by the legal entity to comply with the prescriptionsubject verification compliance with the instructions of the state control supervision body
# 00150600497178
Unscheduled inspection
Start date: 2015-09-10, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution of a previously issued prescription
# 00150600040605
Unscheduled inspection
Start date: 2015-07-13, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of the execution of the previously issued prescription from 31032015 g PA71203PGV
# 00150600040509
Unscheduled inspection
Start date: 2015-07-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272101297514
Unscheduled inspection
Start date: 2021-11-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272101278103
Unscheduled inspection
Start date: 2021-11-15, end date: 2021-12-10, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of JSC "Urgalugol" on the completion of the construction of the capital construction facility dated 10/21/2021 No. 3 (ex. No. 4763 dated 10/21/2021), the objectives of this inspection are: prevention, detection, suppression of violations of current legislation on urban development and project documentation., The subject of the audit is to verify the compliance of the work performed and the construction materials and products used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the approved design documentation.
# 272101297456
Unscheduled inspection
Start date: 2021-11-15, end date: 2021-12-10, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of JSC "Urgalugol" on the completion of the construction of the capital construction facility dated 10/21/2021 No. 1 (ex. No. 4763 dated 10/21/2021)., The objectives of this inspection are: prevention, detection, suppression of violations of current legislation on urban development and project documentation. The subject of the audit is to verify the compliance of the work performed and the construction materials and products used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the approved design documentation.
# 272101302336
Unscheduled inspection
Start date: 2021-11-15, end date: 2021-12-10, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of JSC "Urgalugol" on the completion of the construction of the capital construction facility dated 10/21/2021 No. 2 (ex. No. 4763 dated 10/21/2021)., The objectives of this inspection are: prevention, detection, suppression of violations of current legislation on urban development and project documentation, The subject of the audit is to verify the compliance of the work performed and the construction materials and products used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the approved design documentation.
# 272100636782
Unscheduled inspection
Start date: 2021-09-15, end date: 2021-09-24, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program dated 02/13/2019, The subject of the inspection is to verify the compliance of the work performed and the construction materials and products used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of approved design documentation
# 272100475244
Unscheduled inspection
Start date: 2021-08-24, end date: 2021-09-20, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program dated 03/27/2020.. . The subject of the inspection is to verify the compliance of the work performed and the construction materials and products used during construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of approved design documentation.
# 272100302336
Unscheduled inspection
Start date: 2021-06-21, end date: —, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Habarovskom krae
Purpose of inspection: Purpose: protection of the rights and interests of the employee; Tasks: supervision and control over compliance with labor legislation and other normative legal acts containing norms of labor law; Subject of verification: compliance with mandatory requirements established by municipal legal acts
# 272100253993
Unscheduled inspection
Start date: 2021-05-31, end date: 2021-06-28, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of a notice on the completion dates of works subject to inspection dated 05/19/2021 No. 03/1065 (vx. 2160 dated 05/27/2021), The objectives of this inspection are: prevention, detection, suppression of violations of current legislation on urban development and project documentation., The subject of the inspection is verification compliance of the work performed and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements (with the exception of capital construction facilities, to which energy efficiency requirements do not apply) and the requirements of equipping the capital construction facility with metering devices for energy resources used.
# 272100238906
Unscheduled inspection
Start date: 2021-05-31, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272100226922
Unscheduled inspection
Start date: 2021-05-24, end date: —, duration: —
Authority: Amurskoe territorialnoe upravlenie Federalnogo agentstva po rybolovstvu
Purpose of inspection:
# 272100150379
Unscheduled inspection
Start date: 2021-04-20, end date: 2021-05-07, duration: 7
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 5.1 of Article 6 of the Urban Planning Code of the Russian Federation, based on the inspection program, which should be notified to the head of JSC "Urgalugol" within 24 hours before the start of the inspection in accordance with the established procedure.
The objectives of this audit are:
prevention, detection and suppression of violations of legislation on urban development, including technical regulations, and project documentation committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or technical customer (hereinafter referred to as the contractor).
7. The subject of this audit is:
a) compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of the Urban Planning Code The Code of the Russian Federation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation), including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements of equipping the capital construction facility with metering devices used energy resources;
b) availability of a building permit;
c) fulfillment of the requirements established by parts 2, 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 272100150381
Unscheduled inspection
Start date: 2021-04-20, end date: 2021-05-07, duration: 8
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 5.1 of Article 6 of the Urban Planning Code of the Russian Federation, based on the inspection program, which should be notified to the head of JSC "Urgalugol" within 24 hours before the start of the inspection in accordance with the established procedure.
The objectives of this audit are:
prevention, detection and suppression of violations of legislation on urban development, including technical regulations, and project documentation committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or technical customer (hereinafter referred to as the contractor).
7. The subject of this audit is:
a) compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of the Urban Planning Code The Code of the Russian Federation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation), including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements of equipping the capital construction facility with metering devices used energy resources;
b) availability of a building permit;
c) fulfillment of the requirements established by parts 2, 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 272100131940
Unscheduled inspection
Start date: 2021-04-12, end date: 2021-05-11, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Habarovskom krae
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms, Appeal no.27/7-922-21- ABOUT from 03/24/2021
Ensuring the observance and protection of the labor rights and freedoms of citizens, including the right to safe working conditions
, compliance with mandatory requirements and (or) requirements established
by municipal legal acts;
# 272100178340
Unscheduled inspection
Start date: 2021-04-28, end date: —, duration: 20
Authority: Amurskoe territorialnoe upravlenie Federalnogo agentstva po rybolovstvu
Purpose of inspection: this audit is carried out in order to:
monitor compliance by a legal entity with the mandatory requirements of environmental legislation, establish violations of legislation in the field of protection of VBR and their habitat
the objectives of this audit are:
prevention of harm to the environment, prevention of man-made emergencies
subject: carrying out measures:
to prevent harm to life, health of citizens, harm animals, plants, the environment, objects of cultural heritage (historical and cultural monuments) of the peoples of the Russian Federation, museum objects and museum collections included in the Museum Fund of the Russian Federation, especially valuable, including unique, documents of the Archival Fund of the Russian Federation, documents of special historical, scientific, cultural significance, included part of the National Library Fund
# 272100044205
Unscheduled inspection
Start date: 2021-03-04, end date: 2021-04-01, duration: 20
Authority: Priamurskoe mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya
Purpose of inspection: Verification of the fulfillment by a legal entity — JSC "Urgalugol" of the regulation dated 11/25/2019 No. 08-023/2019-1 on the elimination of identified violations of mandatory requirements.
The order was issued on the basis of the inspection act dated 11/25/2019 No. 08-023/201
# 272005243035
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-12-18, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of a notice on the completion dates of works subject to inspection dated 18112020 1 The objectives of this inspection are to prevent identify suppress violations of current legislation on urban development and project documentationthe subject of the inspection is to verify the compliance of the work and the construction materials used in the construction process reconstruction of a capital construction facility as well as the results of such the requirements of the project documentation, including the requirements of energy efficiency, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used
# 272005243034
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-12-18, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 13022019the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and design documentationthe subject of the inspection is to verify the compliance of the work and the construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements of design documentation in including the requirements of energy efficiency, with the exception of capital construction projects to which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used
# 272005243033
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-12-18, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision in connection with the expiration of the deadline for the execution of the order dated January 14, 2020 C02032020 on the elimination of violations during the construction of a capital construction facility issued by the state construction supervision authority, the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentationthe subject of this inspection is to verify the execution of the Order
# 272005243032
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-12-18, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision in connection with the expiration of the deadline for the execution of the order dated January 14, 2020 C01032020 on the elimination of violations during the construction of a capital construction facility issued by the state construction supervision authority, the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentationthe subject of this inspection is to verify the execution of the Order
# 002005201303
Unscheduled inspection
Start date: 2020-11-02, end date: 2020-12-09, duration: 27
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to comply with the order of the head of the Federal Service for Environmental Technological and Nuclear Supervision dated 29092020 379 issued in pursuance of the order of the Government of the Russian Federation dated 22092020 YUBP911478 of the order of the head of the Far Eastern Department of the Federal Service for Environmental Technological and Nuclear Supervision dated 06102020 PR372406 The tasks of this inspection are the prevention detection and suppression of violations by legal entities engaged in industrial safety activities their managers and other officials of the requirements in the field of industrial safety for taking measures provided for by the legislation of the Russian Federation to suppress prevent and or eliminate identified violations, the subject of this audit is compliance by a legal entity in the course of carrying out activities with mandatory requirements in the field of industrial safety as well as compliance with the specified requirements of used buildings premises structures technical devices equipment and materials of ongoing technological processes
# 752005171849
Unscheduled inspection
Start date: 2020-08-27, end date: 2020-09-23, duration: 20
Authority: Priamurskoe mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya
Purpose of inspection: verification of the fulfillment by the business entity of JSC "Urgalugol" p1 of regulation 0802320191 of 25112019 on the elimination of identified violations of mandatory requirements issued by the Amur Interregional Department of Rosprirodnadzor based on the results of a planned on-site inspection Deadline for the execution of the regulation 03082020
# 272004473742
Unscheduled inspection
Start date: 2020-07-27, end date: 2020-08-21, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Habarovskom krae
Purpose of inspection: protection of the rights and interests of an employee Tasks supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms The subject of verification is compliance with mandatory requirements established by municipal legal acts
# 272004444408
Unscheduled inspection
Start date: 2020-06-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272004437221
Unscheduled inspection
Start date: 2020-06-22, end date: 2020-07-17, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 27032020the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation7 The subject of the inspection is to verify the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements of project documentation including the requirements of energy efficiency, with the exception of capital construction projects to which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used
# 272004405643
Unscheduled inspection
Start date: 2020-04-27, end date: 2020-05-27, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Habarovskomu krayu
Purpose of inspection: this check is carried out in order to establish compliance with the non-compliance of the object with the mandatory requirements of sanitary and epidemiological legislation, consideration of the appeal of a citizen of vh 140285 from 31032020 redirected by the Government of the Khabarovsk Territory to the Prosecutor's Office of the Verkhnebureinsky district about the need to take measures to clean up smoke by boiler houses in Chegdomyn
# 272004389791
Unscheduled inspection
Start date: 2020-04-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272004364954
Unscheduled inspection
Start date: 2020-03-06, end date: 2020-04-03, duration: —
Authority: Gosudarstvennaya inspekciya truda v Habarovskom krae
Purpose of inspection: The purpose is to protect the rights and interests of the employee Tasks supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms The subject of verification is compliance with mandatory requirements established by municipal legal acts
# 272004364950
Unscheduled inspection
Start date: 2020-03-06, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya truda v Habarovskom krae
Purpose of inspection:
# 272004364957
Unscheduled inspection
Start date: 2020-03-06, end date: 2020-04-03, duration: —
Authority: Gosudarstvennaya inspekciya truda v Habarovskom krae
Purpose of inspection: The purpose is to protect the rights and interests of the employee Tasks supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms The subject of verification is compliance with mandatory requirements established by municipal legal acts
# 272004379573
Unscheduled inspection
Start date: 2020-03-30, end date: 2020-04-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program dated 18102019 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and project documentation The subject of this inspection is to verify the compliance of work and the use of building materials during the construction of the Facility as well as the results of such inspections works according to the requirements of the technical regulations of the project documentation
# 001904041161
Unscheduled inspection
Start date: 2019-12-02, end date: 2019-12-24, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to control the execution of JSC "Urgalugol" previously issued by the Federal Service for Environmental Technological and Nuclear Supervision of the order on the elimination of identified violations from 07092018 442P2018 p 47The purpose of this inspection is to monitor the measures taken by JSC "Urgalugol" to comply with the order of the Far Eastern Directorate of Rostechnadzor from 07092018 442P2018 p 47The subject of this inspection is the implementation of JSC "Urgalugol" regulations of the Far Eastern Department of Rostechnadzor dated 07092018 442P2018 p 47The implementation of measures to prevent harm to the life and health of citizens, harm to animals, plants, the environment, and the prevention of natural and man-made emergencies
# 271904168510
Unscheduled inspection
Start date: 2019-12-31, end date: 2020-01-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision in connection with the expiration of the deadline for the execution of the order dated May 31, 2019 C04032019 on the elimination of violations during the construction of a capital construction facility issued by the state construction supervision authority, the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentationthe subject of this inspection is to verify the execution of the Order
# 271904168503
Unscheduled inspection
Start date: 2019-12-31, end date: 2020-01-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision in connection with the expiration of the deadline for the execution of the order dated May 31, 2019 C05032019 on the elimination of violations during the construction of a capital construction facility issued by the state construction supervision authority, the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentationthe subject of this inspection is to verify the execution of the Order
# 271904168414
Unscheduled inspection
Start date: 2019-12-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 271903943251
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-12-05, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Habarovskomu krayu
Purpose of inspection: Control over the execution of a previously issued order on the elimination of identified violations of mandatory requirements of sanitary and epidemiological legislation 1071 dated 04102018 with a deadline of 04112019
# 271903943223
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-12-03, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Habarovskomu krayu
Purpose of inspection: Control over the execution of a previously issued order on the elimination of identified violations of mandatory requirements of sanitary and epidemiological legislation 1090 dated 04102018 with a deadline of 04112019
# 001903730079
Unscheduled inspection
Start date: 2019-10-01, end date: 2019-10-29, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to control the execution of JSC "Urgalugol" previously issued by the Federal Service for Environmental Technological and Nuclear Supervision of the order on the elimination of identified violations from 07092018 442P2018 p 30 61 The task of this inspection is to monitor the measures taken by JSC "Urgalugol" to comply with the order of the Far Eastern Directorate of Rostechnadzor from 07092018 442P2018 p 30 61 The subject of this inspection is the implementation of JSC "Urgalugol" regulations of the Far Eastern Department of Rostechnadzor dated 07092018 442P2018 p 30 61
# 271903060608
Unscheduled inspection
Start date: 2019-08-30, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection:
# 271903060809
Unscheduled inspection
Start date: 2019-08-30, end date: 2019-09-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 13022019the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and design documentationthe subject of the inspection is to verify the compliance of the work and the construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements of design documentation in including the requirements of energy efficiency, with the exception of capital construction projects to which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used
# 271903710114
Unscheduled inspection
Start date: 2019-08-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001902758381
Unscheduled inspection
Start date: 2019-06-03, end date: 2019-07-15, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of this audit is to monitor the measures taken by JSC Urgalugol to comply with the order of the Far Eastern Directorate of Rostechnadzor from 21032019 PA71182. The verification is carried out in order to control the execution of JSC Urgalugol previously issued by the Far Eastern Directorate of Rostechnadzor of the order from 21032019 PA71182 on the elimination of identified violations. The subject of this audit is the fulfillment by JSC Urgalugol of the order of the Far Eastern Directorate of Rostechnadzor from 21032019 PA71182. measures to prevent harm to life to the health of citizens, harm to animals, plants, the environment, and the prevention of emergency situations of a natural and man-made nature
# 001902715888
Unscheduled inspection
Start date: 2019-05-17, end date: 2019-05-30, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to control the execution of JSC "Urgalugol" previously issued by the Federal Service for Environmental Technological and Nuclear Supervision of the order on the elimination of identified violations from 07092018 442P2018 n 29 30 38 39 47 59 61 67 The task of this inspection is to monitor the measures taken by JSC "Urgalugol" to comply with the order of the Far Eastern Department of Rostechnadzor from 07092018 442P2018 by the subject of this inspection is the fulfillment by JSC "Urgalugol" of the regulations of the Far Eastern Department of Rostechnadzor dated 07092018 442P2018
# 271902674454
Unscheduled inspection
Start date: 2019-04-29, end date: 2019-05-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 15032019 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation 7 The subject of the inspection is to verify the compliance of the work and the construction materials used in the construction reconstruction of the capital construction facility as well as the results of such work with the requirements design documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used
# 271902674470
Unscheduled inspection
Start date: 2019-04-29, end date: 2019-05-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 15032019 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation The subject of the inspection is to verify the compliance of the work and the construction materials used in the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used
# 271902673057
Unscheduled inspection
Start date: 2019-04-29, end date: 2019-05-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 13022019 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation The subject of the inspection is to verify the compliance of the work and the construction materials used in the construction process reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used
# 271902672936
Unscheduled inspection
Start date: 2019-04-29, end date: 2019-05-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 15032019 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation The subject of the inspection is to verify the compliance of the work and the construction materials used in the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used
# 001902550546
Unscheduled inspection
Start date: 2019-03-04, end date: 2019-03-21, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The implementation of Federal state supervision in the field of industrial safety, which should be notified to a legal entity no later than 24 hours before the start of its conduct in accordance with the procedure established by law, the objectives of this audit are to prevent the occurrence of a threat of harm to the life and health of citizens, as well as the threat of natural and man-made emergencies, to identify and suppress violations of mandatory industrial safety requirements during operation hazardous production facilities The Bureinsky coal mine of hazard class II reg A71006820003 The Pravoberezhny coal mine of hazard class II reg A71006820023 The subject of this inspection is the information set out in the appeal of citizen Akhmetyanov AA bx 33OG dated 21022019 on illegal actions of JSC Urgalugol during blasting operations in the immediate vicinity of residential buildings of the village of Sredny Urgal that pose a threat to the life and health of residents of the above-mentioned in the part related to the competence of Rostechnadzor, compliance with mandatory industrial safety requirements established by regulatory legal acts
# 001902443074
Unscheduled inspection
Start date: 2019-02-19, end date: 2019-02-20, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the implementation of the previously issued instruction on the elimination of identified violations from 13092018 PA71965 paragraphs 1, the deadline for which expires on 01022019 2, the deadline for which expired on 01012019
# 271902528054
Unscheduled inspection
Start date: 2019-02-26, end date: 2019-03-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 08022018 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and design documentation The subject of this inspection is to verify the compliance of work and the use of building materials during the construction of the Facility as well as the results of such inspections works according to the requirements of the technical regulations of the project documentation
# 271802419484
Unscheduled inspection
Start date: 2018-12-27, end date: 2019-01-31, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Habarovskomu krayu
Purpose of inspection: To establish compliance with the non-compliance of the object with the mandatory requirements of sanitary and epidemiological legislation, to consider a written request from a citizen of vh1401214 dated 21122018 on atmospheric air pollution by boiler room emissions 2
# 271802190784
Unscheduled inspection
Start date: 2018-12-10, end date: 2019-01-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 13092017 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation The subject of the inspection is to verify the compliance of the work and construction materials used in the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used
# 271802190780
Unscheduled inspection
Start date: 2018-12-10, end date: 2019-01-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of a notice on the completion dates of works subject to inspection dated November 23, 2018, vx 5876 of 26112018, the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation The subject of the inspection is to verify the compliance of the work and the construction materials used in the process construction reconstruction of the capital construction facility as well as the results of such work to the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used
# 271802208754
Unscheduled inspection
Start date: 2018-12-12, end date: 2019-01-16, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of completion of the construction of the facility dated November 28, 2018, vx 5937 of 28112018, the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation The subject of the inspection is to verify the compliance of completed works and applied building materials during construction reconstruction the capital construction facility as well as the results of such work meet the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used
# 271802089105
Unscheduled inspection
Start date: 2018-11-14, end date: 2018-12-11, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program dated 08112018 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation The subject of the inspection is to verify the compliance of the work and construction materials used in the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used
# 271801990187
Unscheduled inspection
Start date: 2018-10-26, end date: 2018-11-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 23032018 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation The subject of the inspection is to verify the compliance of the work and the construction materials used in the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used
# 271801609712
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-10-05, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Habarovskomu krayu
Purpose of inspection: Control over the execution of previously issued orders on the elimination of identified violations of mandatory requirements of sanitary and epidemiological legislation 1220 dated 22112017 with a deadline of 04092018 and 443 dated 03052018 with a deadline of 04092018
# 271800582571
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-10, duration: —
Authority: Upravlenie lesami Pravitelstva Habarovskogo kraya
Purpose of inspection: Verification of the execution of the previously issued order dated 29.012018 515118 On the elimination of deficiencies and Violations Identified as a result of Federal State Forest Supervision and Federal State Fire Supervision in Forests for Compliance with the Requirements of forest Legislation the deadline for eliminating the identified violations expires 01082018
# 271800663431
Unscheduled inspection
Start date: 2018-08-23, end date: 2018-09-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 08022018 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and design documentation The subject of this inspection is to verify the compliance of work and the use of building materials during the construction of the Facility as well as the results of such inspections works according to the requirements of the technical regulations of the project documentation
# 271800571698
Unscheduled inspection
Start date: 2018-07-31, end date: 2018-08-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of JSC Urgalugol on the completion of the construction of a capital construction facility dated 11072018 bn bx 3367 dated 12072018 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities including technical regulations and design documentationthe subject of this inspection is to verify the compliance of work and application construction materials during the construction of the Facility as well as the results of such work meet the requirements of technical regulations and project documentation
# 271800545406
Unscheduled inspection
Start date: 2018-07-27, end date: 2018-08-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of a notice on the completion dates of works subject to inspection dated July 04, 2018 vx 3232 dated July 05, 2018 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities including technical regulations and project documentation The subject of this inspection is to verify compliance performance of works and application of building materials during the construction of the Facility as well as the results of such work to the requirements of technical regulations of the project documentation
# 271800412388
Unscheduled inspection
Start date: 2018-05-31, end date: 2018-06-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 23032018 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and project documentation The subject of this inspection is to verify the compliance of work and the use of building materials during the construction of the Facility as well as the results of such inspections works according to the requirements of the technical regulations of the project documentation
# 271800310198
Unscheduled inspection
Start date: 2018-05-16, end date: 2018-06-13, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 08022018 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and design documentation The subject of this inspection is to verify the compliance of work and the use of building materials during the construction of the Facility as well as the results of such inspections works according to the requirements of the technical regulations of the project documentation
# 271800297488
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-05-16, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of a notice from JSC Urgalugol on the execution of an order dated April 10, 2018 on the elimination of violations during the construction of a capital construction facility issued by the state construction supervision authority, the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban planning activities, including technical regulations and project documentation. The purpose of this check is to verify the fulfillment of the Regulation from 16032018 C02032018
# 271800298039
Unscheduled inspection
Start date: 2018-04-17, end date: 2018-05-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of JSC Urgalugol on the completion of the construction of a capital construction facility dated 11042018 bn bx 1648 dated 12042018 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities including technical regulations and project documentation The subject of this inspection is to verify the compliance of work and the use of building materials during the construction of the Facility as well as the results of such work to the requirements of the technical regulations of the project documentation
# 001800331815
Unscheduled inspection
Start date: 2018-04-20, end date: 2018-05-22, duration: —
Authority: Departament Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Dalnevostochnomu federalnomu okrugu
Purpose of inspection: verification of the fulfillment by the economic entity of JSC "Urgalugol" of the instruction dated 28122017 07371 on the elimination of violations of legislation in the field of subsoil use and protection of subsoil allowed during the use of subsoil in the license area provided for the purpose of exploration and extraction of groundwater in the valley of the B Satanka creek for water supply to the population and other consumers in accordance with the license HUB 02464 VE valid from 19032012 to 31122031 The order was issued on December 28, 2017 on the basis of the inspection act dated 28122017 0737 The deadline for the execution of the order expires 16042018
# 271800312196
Unscheduled inspection
Start date: 2018-04-05, end date: 2018-05-03, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Habarovskomu krayu
Purpose of inspection: Control of the execution of regulation 471 of 29062017 paragraphs 1234689101112131415161718192021222324 25262728293031323334353637 detection and suppression of violations of the requirements of sanitary and epidemiological legislation
# 271800031795
Unscheduled inspection
Start date: 2018-02-13, end date: 2018-03-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of a notice on the completion dates of works subject to inspection dated 15.012018 bn bx 261 dated 23.012018 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities including technical regulations and project documentation 7 The subject of this inspection is to verify the compliance of work and application construction materials during the construction of the Facility as well as the results of such work meet the requirements of technical regulations and project documentation
# 271800026673
Unscheduled inspection
Start date: 2018-02-13, end date: 2018-03-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of JSC Urgalugol on the completion of the construction of a capital construction facility dated 15.012018 bn vx 173 dated 18.012018 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities including technical regulations and design documentation The subject of this inspection is to verify the compliance of work and the use of building materials during the construction of the Facility as well as the results of such work to the requirements of the technical regulations of the project documentation
# 271800062147
Unscheduled inspection
Start date: 2018-02-15, end date: 2018-03-16, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of JSC Urgalugol on the completion of the construction of a capital construction facility dated 15.012018 bn bx 362 dated 29.012018 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities including technical regulations and project documentation The subject of this inspection is to verify the compliance of work and the use of building materials during the construction of the Facility as well as the results of such work to the requirements of the technical regulations of the project documentation
# 271800053068
Unscheduled inspection
Start date: 2018-02-01, end date: 2018-02-28, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Habarovskomu krayu
Purpose of inspection: To establish compliance with the non-compliance of the object with the mandatory requirements of sanitary and epidemiological legislation, to consider a written collective appeal from citizens sent by the Council of Deputies of the urban settlement of the working settlement of Chegdomyn of the Verkhnebureinsky district of the Khabarovsk Territory bx14087 dated 29.012018 on atmospheric air pollution from boiler room emissions 2
# 271800544995
Unscheduled inspection
Start date: 2018-01-22, end date: 2018-01-26, duration: —
Authority: Upravlenie lesami Pravitelstva Habarovskogo kraya
Purpose of inspection: Verification of the execution of the previously issued order dated 17072017 515117 On the elimination of deficiencies and Violations Identified as a result of Federal State Forest Supervision and Federal State Fire Supervision in Forests for Compliance with the Requirements of forest Legislation the deadline for eliminating the identified violations expired on 17.012018
# 27170803018487
Unscheduled inspection
Start date: 2017-12-28, end date: 2018-01-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program of the Facility dated September 14, 2017. The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and design documentation. The subject of the inspection is to verify the compliance of the work performed and the building materials used during the construction of the Facility and also, the results of such work meet the requirements of the technical regulations of the design
# 00170802976425
Unscheduled inspection
Start date: 2017-12-04, end date: 2017-12-29, duration: —
Authority: Departament Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Dalnevostochnomu federalnomu okrugu
Purpose of inspection: verification of regulation 07201 of 25072017
# 27170803002887
Unscheduled inspection
Start date: 2017-12-13, end date: 2018-01-17, duration: —
Authority: Gosudarstvennaya inspekciya truda v Habarovskom krae
Purpose of inspection: protection of the rights and interests of an employee Tasks supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms The subject of verification is compliance with mandatory requirements established by municipal legal acts
# 27170802823495
Unscheduled inspection
Start date: 2017-11-01, end date: 2017-11-29, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Habarovskomu krayu
Purpose of inspection: Control over the execution of the order on the elimination of identified violations of mandatory requirements of sanitary and epidemiological legislation from 19122016 1485 prevention detection suppression of violations of mandatory requirements of sanitary legislation legislation in the field of consumer protection and technical regulation or the establishment of their absence
# 27170802537885
Unscheduled inspection
Start date: 2017-10-04, end date: 2017-10-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this audit is carried out in order to carry out regional state construction supervision on the basis of the program of inspections of the capital construction facility dated February 21, 2017. The objectives of this audit are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and design documentationthe subject of this audit is to verify the compliance of work and the use of building materials during the construction of the Facility as well as the results of such work to the requirements of the technical regulations of the project documentation
# 27170802519868
Unscheduled inspection
Start date: 2017-10-04, end date: 2017-10-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program of the Facility dated April 24, 2017. The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and design documentationthe subject of this inspection is to verify the compliance of the work performed and the building materials used during the construction of the Facility and also, the results of such work meet the requirements of the technical regulations of the project documentation
# 27170802519855
Unscheduled inspection
Start date: 2017-10-04, end date: 2017-10-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this audit is carried out in order to carry out regional state construction supervision on the basis of the program of inspections of the capital construction facility dated December 22, 2016. The objectives of this audit are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and design documentationthe subject of this audit is to verify the compliance of work and the use of building materials during the construction of the Facility as well as the results of such work to the requirements of the technical regulations of the project documentation
# 27170802537860
Unscheduled inspection
Start date: 2017-10-02, end date: 2017-10-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program of the Facility dated September 14, 2017, the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and design documentationthe subject of the inspection is to verify the compliance of the work performed and the building materials used during the construction of the reconstruction of the Facility as well as the results of such work meet the requirements of the technical regulations of the project documentation
# 27170802506666
Unscheduled inspection
Start date: 2017-09-19, end date: 2017-09-22, duration: —
Authority: Upravlenie lesami Pravitelstva Habarovskogo kraya
Purpose of inspection: Verification of the execution of a previously issued prescription from 17072017 515217
# 27170802519801
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of completion of construction of a capital construction facility dated September 13, 2017 0113 vx 4339 dated September 13, 2017 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and design documentationthe subject of this inspection is to verify compliance with the implementation of works and the use of building materials during the construction of the Facility as well as the results of such work to the requirements of technical regulations of the project documentation
# 27170802519798
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of completion of construction of a capital construction facility dated September 13, 2017 0113 vx 4339 dated September 13, 2017 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and design documentationthe subject of this inspection is to verify compliance with the implementation of works and the use of building materials during the construction of the Facility as well as the results of such work to the requirements of technical regulations of the project documentation
# 27170802519788
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of completion of construction of a capital construction facility dated September 13, 2017 0113 vx 4339 dated September 13, 2017 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and design documentationthe subject of this inspection is to verify compliance with the implementation of works and the use of building materials during the construction of the Facility as well as the results of such work to the requirements of technical regulations of the project documentation
# 00170801950087
Unscheduled inspection
Start date: 2017-09-01, end date: 2017-09-15, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution of JSC "Urgalugol" previously issued by the Far Eastern Department of Rostechnadzor regulation PA71474 dated June 27, 2017 item 11, the deadline for which expired on July 10, 2017 items 1 3 4 10, the deadline for which expired on July 25, 2017 item 2, the deadline for which expired on August 1, 2017 items 5 8 9, the deadline for the execution of which expires on September 1, 2017, the objectives of this audit are to monitor the measures taken by the legal entity to comply with the order
# 27170801912618
Unscheduled inspection
Start date: 2017-08-31, end date: 2017-09-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the program for conducting inspections of the Facility dated July 11, 2017, the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and design documentationthe object of the inspection is to verify the compliance of the work performed and the building materials used during the construction of the reconstruction of the Facility as well as the results of such work meet the requirements of the technical regulations of the project documentation
# 27170701822905
Unscheduled inspection
Start date: 2017-08-03, end date: 2017-08-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program of the Facility dated June 26, 2017, the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including technical regulations and design documentationthe subject of the inspection is to verify the compliance of the work performed and the building materials used during the construction of the reconstruction of the Facility as well as the results of such work meet the requirements of the technical regulations of the project documentation