Found 62 inspections:

# 142101465731
Unscheduled inspection
Start date: 2021-12-17, end date: 2021-12-30, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: verification in connection with the notification received by the Department of State Construction and Housing Supervision of the Republic of Sakha (Yakutia): a) compliance of the constructed capital construction facility with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources; b) elimination by the developer, technical customer, person carrying out construction identified during construction control and state construction supervision of all violations of compliance of completed works with the requirements of regulatory legal acts and project documentation; c) execution of executive documentation related to the performance of all construction work, as well as the use of building materials (products), prevention, detection and suppression of violations committed by the developer, the technical customer, as well as by a person carrying out construction on the basis of a contract with a developer or customer (hereinafter referred to as the contractor), violations of legislation on urban planning activities, including project documentation, compliance with mandatory requirements and (or) requirements established by municipal legal acts


# 142101465927
Unscheduled inspection
Start date: 2021-12-16, end date: 2021-12-30, duration: 11
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: verification in connection with the notification received by the Department of State Construction and Housing Supervision of the Republic of Sakha (Yakutia): a) compliance of the constructed capital construction facility with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources; b) elimination by the developer, technical customer, person carrying out construction identified during construction control and state construction supervision of all violations of compliance of completed works with the requirements of regulatory legal acts and project documentation; c) execution of executive documentation related to the performance of all construction work, as well as the use of building materials (products), prevention, detection and suppression of violations committed by the developer, the technical customer, as well as by a person carrying out construction on the basis of a contract with a developer or customer (hereinafter referred to as the contractor), violations of legislation on urban planning activities, including project documentation, compliance with mandatory requirements and (or) requirements established by municipal legal acts


# 142100245834
Unscheduled inspection
Start date: 2021-06-07, end date: 2021-06-21, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: inspections in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Republic of Sakha (Yakutia), on April 28, 2021, compliance with the mandatory requirements in the field of construction and applied building materials (products), the established procedure for construction and reconstruction of the facility during the construction of the capital construction facility, the technical customer, the person carrying out the construction capital construction, prevention, detection and suppression of violations of the legislation on urban planning activities, including project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer (hereinafter referred to as the contractor), 1) compliance of the work and the construction materials used during construction, reconstruction the capital construction project, as well as the results of such work, meet the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of the Urban Planning Code of the Russian Federation), including energy efficiency requirements and equipment of the capital construction facility with metering devices for used energy resources; 2) availability of a construction permit; 3) compliance with the requirements established by parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.


# 142005206680
Unscheduled inspection
Start date: 2020-11-03, end date: 2020-11-17, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of a capital construction facility as well as the results of such work with the requirements of the design documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the design documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including among the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in the prescription and on notification of the elimination of the prescription


# 142005215700
Unscheduled inspection
Start date: 2020-11-06, end date: 2020-12-03, duration: 20
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is the compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to works on the organization of construction in the case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity


# 142005258250
Unscheduled inspection
Start date: 2020-11-13, end date: 2020-11-27, duration: 11
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 142005178336
Unscheduled inspection
Start date: 2020-10-09, end date: 2020-10-14, duration: 4
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 142005203404
Unscheduled inspection
Start date: 2020-10-27, end date: 2020-11-11, duration: 15
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 142005176905
Unscheduled inspection
Start date: 2020-10-12, end date: —, duration:
Authority:
Purpose of inspection:


# 142005176902
Unscheduled inspection
Start date: 2020-10-12, end date: 2020-11-09, duration: 20
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is the compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to works on the organization of construction in the case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity


# 142004487129
Unscheduled inspection
Start date: 2020-08-17, end date: 2020-09-04, duration: 15
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, of violations of the legislation on urban development, including technical regulations and design documentation1 compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation in including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation


# 142004477391
Unscheduled inspection
Start date: 2020-07-24, end date: —, duration:
Authority:
Purpose of inspection:


# 142004477388
Unscheduled inspection
Start date: 2020-07-24, end date: —, duration:
Authority:
Purpose of inspection:


# 142004477387
Unscheduled inspection
Start date: 2020-07-24, end date: —, duration:
Authority:
Purpose of inspection:


# 142004465043
Unscheduled inspection
Start date: 2020-07-20, end date: —, duration:
Authority:
Purpose of inspection:


# 142004465030
Unscheduled inspection
Start date: 2020-07-20, end date: 2020-07-24, duration: 5
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 142005258293
Unscheduled inspection
Start date: 2020-06-17, end date: 2020-07-02, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 142004445073
Unscheduled inspection
Start date: 2020-06-17, end date: —, duration:
Authority:
Purpose of inspection:


# 142004415656
Unscheduled inspection
Start date: 2020-05-29, end date: 2020-06-26, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: verification of the completed capital construction facility for a compliance of the constructed capital construction facility with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation b elimination by the developer by the technical customer by the person carrying out construction of all violations of compliance of the completed works with the requirements of technical regulations norms and rules of other regulatory legal acts and design documentation in the execution of executive documentation related to the performance of all construction works as well as the use of building materials and products Upon notification of completion of construction by the Department of Gosstroyzhilnadzor of the Russian Federation


# 142004322310
Unscheduled inspection
Start date: 2020-02-20, end date: —, duration:
Authority:
Purpose of inspection:


# 141904135263
Unscheduled inspection
Start date: 2019-12-25, end date: 2020-01-29, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: verification of the completed capital construction facility for a compliance of the constructed capital construction facility with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation b elimination by the developer by the technical customer by the person carrying out construction of all violations of compliance of the completed works with the requirements of technical regulations norms and rules of other regulatory legal acts and design documentation in the execution of executive documentation related to the performance of all construction works as well as the use of building materials and products Upon notification of completion of construction by the Department of Gosstroyzhilnadzor of the Russian Federation


# 141904134998
Unscheduled inspection
Start date: 2019-12-19, end date: 2020-01-23, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: verification of the completed capital construction facility for a compliance of the constructed capital construction facility with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation b elimination by the developer by the technical customer by the person carrying out construction of all violations of compliance of the completed works with the requirements of technical regulations norms and rules of other regulatory legal acts and design documentation in the execution of executive documentation related to the performance of all construction works as well as the use of building materials and products Upon notification of completion of construction by the Department of Gosstroyzhilnadzor of the Russian Federation


# 141904135013
Unscheduled inspection
Start date: 2019-12-19, end date: 2020-01-23, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: verification of the completed capital construction facility for a compliance of the constructed capital construction facility with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation b elimination by the developer by the technical customer by the person carrying out construction of all violations of compliance of the completed works with the requirements of technical regulations norms and rules of other regulatory legal acts and design documentation in the execution of executive documentation related to the performance of all construction works as well as the use of building materials and products Upon notification of completion of construction by the Department of Gosstroyzhilnadzor of the Russian Federation


# 141903981164
Unscheduled inspection
Start date: 2019-11-20, end date: 2019-11-26, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is1 compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used2 availability of a construction permit3compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction and reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in in case of involvement by the developer or the technical customer on the basis of a contract of an individual or a legal person4 according to the instruction 040888819 dated 08102019


# 141903981159
Unscheduled inspection
Start date: 2019-11-20, end date: 2019-11-26, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is1 compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit3compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction and reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in in case of involvement by the developer or the technical customer on the basis of a contract of an individual or a legal person4 verification according to the instruction 040889019 dated 08102019


# 141903660687
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-10-08, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is the compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in in case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity


# 141903660624
Unscheduled inspection
Start date: 2019-09-25, end date: —, duration:
Authority:
Purpose of inspection:


# 141903681974
Unscheduled inspection
Start date: 2019-09-26, end date: 2019-10-09, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is the compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in in case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity


# 141903661468
Unscheduled inspection
Start date: 2019-09-26, end date: —, duration:
Authority:
Purpose of inspection:


# 141902938221
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-08-16, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer (hereinafter referred to as the contractor) 1 compliance of the work and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 the availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation 4 according to the program of inspections according to the program Development of PPR PPR geodetic or technological maps MGN access Axis breakdown Preparatory work Excavation Artificial structures Drainage Road clothing and pavement External water supply and sanitation networks Landscaping and landscaping Works on the implementation of construction control of persons engaged in construction Work on the organization of construction production


# 141902938039
Unscheduled inspection
Start date: 2019-08-12, end date: —, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:


# 141902858417
Unscheduled inspection
Start date: 2019-07-11, end date: 2019-07-25, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and project documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, of compliance of the work and the construction materials used in the construction process of reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation in including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 6 of Article 52 of the Urban Development Code of the Russian Federation to the inspection program


# 141902651436
Unscheduled inspection
Start date: 2019-04-12, end date: 2019-05-16, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor 1 compliance of the work and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 the availability of a construction permit 3 the fulfillment of the requirements established by parts 2 3 and 31 6 of Article 52 of the Urban Planning Code of the Russian Federation verification of the completed construction of a capital construction facility for a compliance of the constructed capital construction facility with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation b elimination by the developer, the technical customer, the person carrying out construction, of all violations of compliance of the completed works with the requirements of technical regulations, norms and rules of other regulatory legal acts and project documentation identified during construction control and state construction supervision. c execution of executive documentation related to the performance of all construction work as well as the use of building materials and products Upon notification of completion Construction Department of gosstroizhilnadzor YAN


# 141802217704
Unscheduled inspection
Start date: 2018-12-12, end date: 2019-01-16, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: verification of the completed capital construction facility for a compliance of the constructed capital construction facility with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation b elimination by the developer by the technical customer by the person carrying out construction of all violations of compliance of the completed works with the requirements of technical regulations norms and rules of other regulatory legal acts and design documentation in the execution of executive documentation related to the performance of all construction works as well as the use of building materials and products Upon notification of completion of construction by the Department of Gosstroyzhilnadzor of the Russian Federation


# 141801964589
Unscheduled inspection
Start date: 2018-10-19, end date: —, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:


# 141801964577
Unscheduled inspection
Start date: 2018-10-19, end date: 2018-10-29, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban planning activities, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, 1 compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 6 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program


# 141801053062
Unscheduled inspection
Start date: 2018-09-11, end date: 2018-09-21, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development activities, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, 1 for compliance of the work and the construction materials used in the construction process of reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of the design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in the case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity


# 141801408031
Unscheduled inspection
Start date: 2018-09-11, end date: 2018-09-21, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development activities, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, 1 for compliance of the work and the construction materials used in the construction process of reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of the design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in the case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity


# 141800710400
Unscheduled inspection
Start date: 2018-08-29, end date: 2018-09-03, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor 1 compliance of the work performed and the building materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 the availability of a construction permit 3 the fulfillment of the requirements established by parts 2 3 and 31 6 of Article 52 of the Urban Planning Code of the Russian Federation According to the prescription and notification of elimination


# 141800531651
Unscheduled inspection
Start date: 2018-07-12, end date: —, duration:
Authority:
Purpose of inspection:


# 141800531641
Unscheduled inspection
Start date: 2018-07-12, end date: 2018-07-19, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: also by a person carrying out construction on the basis of a contract with a developer or customer, hereinafter referred to as the contractor, violations of legislation on urban planning activities, including technical regulations and design documentation 1 compliance of work performed and construction materials used during construction, reconstruction of a capital construction facility, as well as the results of such work with the requirements of technical regulations, design documentation, including energy efficiency and equipment requirements of the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 fulfillment of the requirements established by Parts 2 3 and 31 6 of Article 52 of the Urban Planning Code of the Russian Federation As prescribed by


# 141800375447
Unscheduled inspection
Start date: 2018-05-21, end date: 2018-05-30, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban planning activities, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, 1 compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 6 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program


# 141800261215
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-04-26, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban planning activities, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, 1 compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 6 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program


# 14170803018652
Unscheduled inspection
Start date: 2017-12-25, end date: —, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:


# 14170802940258
Unscheduled inspection
Start date: 2017-12-04, end date: 2017-12-29, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, and the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor.


# 14170802976601
Unscheduled inspection
Start date: 2017-12-19, end date: 2017-12-29, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and project documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, of compliance of the work and the construction materials used in the construction process of reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation in including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 6 of Article 52 of the Urban Development Code of the Russian Federation to the inspection program


# 14170802976584
Unscheduled inspection
Start date: 2017-12-19, end date: 2017-12-25, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor, including technical regulations and project documentation1 of the conformity of work performed and construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work to the requirements of technical regulations and project documentation in including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 the availability of a construction permit 3 the fulfillment of the requirements established by parts 2 3 and 31 6 of Article 52 of the Urban Planning Code of the Russian Federation in the regulations


# 14170802882026
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-11-28, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, and the person carrying out construction on the basis of a contract with the developer or customer, hereinafter referred to as the contractor. The subject of this audit is the conformity of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction and reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in the case of involvement by the developer or the technical customer on the basis of a contract of an individual or a legal entity 4 according to the inspection program


# 14170802757432
Unscheduled inspection
Start date: 2017-10-20, end date: 2017-10-31, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, and the person carrying out construction on the basis of a contract with the developer or customer, hereinafter referred to as the contractor. The subject of this audit is the conformity of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction and reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in the case of involvement by the developer or the technical customer on the basis of a contract of an individual or a legal entity 4 according to the inspection program


# 14170802771158
Unscheduled inspection
Start date: 2017-10-19, end date: 2017-11-16, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: verification of the completed capital construction facility for a compliance of the constructed capital construction facility with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation b elimination by the developer by the technical customer by the person carrying out construction of all violations of compliance of the performed works with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation for the execution of executive documentation related to the performance of all construction work as well as the use of building materials and products According to the notice bn dated 03102017 No. 14678 dated 04102017 on the completion of construction of the Department of Gosstroizhilnadzor of the Russian Federation


# 14170802627539
Unscheduled inspection
Start date: 2017-10-10, end date: 2017-10-23, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor, including technical regulations and project documentation1 of the conformity of work performed and construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work to the requirements of technical regulations and project documentation in including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 the availability of a construction permit 3 the fulfillment of the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation on the inspection program


# 14170701791690
Unscheduled inspection
Start date: 2017-07-19, end date: 2017-08-15, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation, including technical regulations and project documentation1, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or customer, hereinafter referred to as the contractor, to ensure that the work performed and the building materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, comply with the requirements of technical regulations and project documentation including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 the availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation the availability of a certificate of admission to construction and reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in case of involvement by the developer or the technical customer on the basis of the contract of the natural or legal person According to the program of inspections


# 14170701791622
Unscheduled inspection
Start date: 2017-07-19, end date: —, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:


# 14170701791733
Unscheduled inspection
Start date: 2017-07-12, end date: 2017-08-08, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation, including technical regulations and project documentation1, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or customer, hereinafter referred to as the contractor, to ensure that the work performed and the building materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, comply with the requirements of technical regulations and project documentation including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 the availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation the availability of a certificate of admission to construction and reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in case of involvement by the developer or the technical customer on the basis of the contract of the natural or legal person According to the program of inspections


# 14170701770888
Unscheduled inspection
Start date: 2017-07-11, end date: —, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:


# 14170701770880
Unscheduled inspection
Start date: 2017-07-11, end date: —, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:


# 14170701556709
Unscheduled inspection
Start date: 2017-04-25, end date: —, duration:
Authority:
Purpose of inspection:


# 14170701556669
Unscheduled inspection
Start date: 2017-04-25, end date: 2017-05-03, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor, including technical regulations and project documentation1 compliance of the work performed and the building materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation in including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction and reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in case of involvement by the developer or by a technical customer on the basis of an agreement between an individual or a legal entity, as prescribed by


# 14170701295463
Unscheduled inspection
Start date: 2017-01-18, end date: —, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:


# 14160701150809
Unscheduled inspection
Start date: 2016-11-24, end date: 2016-12-20, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and project documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, for compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in case of involvement by the developer or the technical customer on the basis of the contract of an individual or legal entity According to the order


# 14160700985354
Unscheduled inspection
Start date: 2016-09-30, end date: —, duration:
Authority:
Purpose of inspection:


# 14160601709764
Unscheduled inspection
Start date: 2016-07-12, end date: 2016-07-15, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is the conformity of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work for the organization of construction in case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.