# 022101317982
Unscheduled inspection
Start date: 2021-11-15, end date: —, duration: 20
Authority: Gosudarstvennyi komitet Respubliki Bashkortostan po zhilischnomu i stroitelnomu nadzoru
Purpose of inspection: s celyu: po izvescheniyu № 2 ot 26.10.2021g. o srokah zaversheniya rabot, podlezhaschih proverke (fundament, kolonny, montazh karkasa zdaniya v osyah 1/0-7 ryadah A/0-G, Montazh perekrytiya pervogo etazha iz profilirovannogo lista v osyah 1-7, armirovanie perekrytiya pervogo etazha v osyah 1-7), vh. № 28423 ot 26.10.2021g. -- zadachami nastoyaschei proverki yavlyayutsya: vyyavlenie, preduprezhdenie i presechenie dopuschennyh narushenii zakonodatelstva o gradostroitelnoi deyatelnosti, v tom chisle tehnicheskih reglamentov i proektnoi dokumentacii.--soblyudenie obyazatelnyh trebovanii ili trebovanii, ustanovlennyh municipalnymi pravovymi aktami;
# 742201533564
Unscheduled inspection
Start date: 2022-01-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 022101317982
Unscheduled inspection
Start date: 2021-11-15, end date: —, duration: 20
Authority: Gosudarstvennyi komitet Respubliki Bashkortostan po zhilischnomu i stroitelnomu nadzoru
Purpose of inspection: s celyu: po izvescheniyu № 2 ot 26.10.2021g. o srokah zaversheniya rabot, podlezhaschih proverke (fundament, kolonny, montazh karkasa zdaniya v osyah 1/0-7 ryadah A/0-G, Montazh perekrytiya pervogo etazha iz profilirovannogo lista v osyah 1-7, armirovanie perekrytiya pervogo etazha v osyah 1-7), vh. № 28423 ot 26.10.2021g. -- zadachami nastoyaschei proverki yavlyayutsya: vyyavlenie, preduprezhdenie i presechenie dopuschennyh narushenii zakonodatelstva o gradostroitelnoi deyatelnosti, v tom chisle tehnicheskih reglamentov i proektnoi dokumentacii.--soblyudenie obyazatelnyh trebovanii ili trebovanii, ustanovlennyh municipalnymi pravovymi aktami;
# 742100554701
Unscheduled inspection
Start date: 2021-09-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742100345862
Unscheduled inspection
Start date: 2021-07-15, end date: 2021-07-21, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Sootvetstvie vypolneniya rabot po montazhu oborudovaniya, elektromontazhnym rabotam, elektroosvescheniyu, montazhu okon, dverei, vorot, vnutrennei otdelke, montazhu pozharnoi avtomatiki, montazhu sistemy pozharotusheniya i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov. 2. Nalichie razresheniya na stroitelstvo. 3. Vypolnenie trebovanii ch.ch. 2,3 i 3.1 st.52 Gradostroitelnogo kodeksa RF.
# 742100306054
Unscheduled inspection
Start date: 2021-07-07, end date: —, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:
# 742100278263
Unscheduled inspection
Start date: 2021-06-18, end date: 2021-06-24, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work on the installation of RMU metal structures, installation of metal structures for external networks, installation of external ventilation and sewerage networks, earthworks, installation of foundations of the welding site, general construction works of the KTP and the construction materials used during construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of this Code of the project documentation (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) the information model (if the formation and maintenance of the information model are mandatory in accordance with the requirements of this Code), including the requirements energy efficiency (with the exception of capital construction facilities, which are not subject to energy efficiency requirements) and the requirements for equipping the capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Compliance with the requirements of Parts 2.3 and 3.1 of art.52 of the Urban Planning Code of the Russian Federation.
# 742100194362
Unscheduled inspection
Start date: 2021-05-20, end date: —, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:
# 742100161609
Unscheduled inspection
Start date: 2021-04-14, end date: 2021-05-13, duration: 20
Authority: Gosudarstvennaya inspekciya truda v CHelyabinskoi oblasti
Purpose of inspection: Osuschestvlenie federalnogo gosudarstvennogo nadzora za soblyudeniem yuridicheskim licom ili individualnym predprinimatelem obyazatelnyh trebovanii trudovogo zakonodatelstva i inyh normativnyh pravovyh aktov, soderzhaschih normy trudovogo prava., Prikaz Rostruda №74/2-11-21-PR ot 07.04.2021
# 742100098993
Unscheduled inspection
Start date: 2021-04-07, end date: 2021-04-13, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the excavation work, the installation of foundations of the RMU and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Articles 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and equipment requirements of the capital construction facility construction of metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.
# 792100036969
Unscheduled inspection
Start date: 2021-02-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742005179934
Unscheduled inspection
Start date: 2020-10-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742005180092
Unscheduled inspection
Start date: 2020-10-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742005179914
Unscheduled inspection
Start date: 2020-10-16, end date: 2020-10-22, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot po montazhu osnovnyh metallokonstrukcii i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 nastoyaschego Kodeksa i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF
# 742004366008
Unscheduled inspection
Start date: 2020-03-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742004176328
Unscheduled inspection
Start date: 2020-01-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741904010697
Unscheduled inspection
Start date: 2019-12-04, end date: 2019-12-10, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot pri ustroistve transhei ustroistve osnovaniya pod trubu ukladki truby prisypki truby peschanoi smesyu i obratnoi zasypke ot kolodca Kl7 do Kl9 ot Kl38 do Kl33 ot Kl35Kl62 do zdaniya 17 pri ustroistve kolodcev K7 K8 K9 K35 K36 K37 i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 nastoyaschego Kodeksa i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741904010578
Unscheduled inspection
Start date: 2019-12-04, end date: 2019-12-10, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: Sootvetstvie vypolneniya rabot pri ustroistve transhei ustroistve osnovaniya pod trubu ukladki truby prisypki truby peschanoi smesyu i pri obratnoi zasypke ot V29PG do zdaniya 17 ot V211Ug36Ug37 do V213PG pri ustroistve kolodca V213PG i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 nastoyaschego Kodeksa i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741904043227
Unscheduled inspection
Start date: 2019-12-11, end date: 2019-12-17, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot v zdanii sklada ishodnyh pri montazhe vnutrennego osvescheniya v osyah AV121 v zdanii nasosnoi stancii pozharotusheniya s rezervuarami pri montazhe oborudovaniya i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 nastoyaschego Kodeksa i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741903981728
Unscheduled inspection
Start date: 2019-11-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741903981685
Unscheduled inspection
Start date: 2019-11-27, end date: 2019-12-03, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot pri ustroistve transhei ustroistvo osnovaniya ukladka i prisypka truby obratnoi zasypke ot kolodca K166 do K167 pri ustroistve kolodca Kl67 i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 nastoyaschego Kodeksa i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741903924236
Unscheduled inspection
Start date: 2019-11-06, end date: —, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:
# 741903983506
Unscheduled inspection
Start date: 2019-11-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741903811074
Unscheduled inspection
Start date: 2019-10-23, end date: 2019-10-29, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot pri montazhe kran balok v osyah BV18 A1B1 1117 ognezaschite metallicheskih konstrukcii i nanesenie emali v osyah A1B1 1171 BV28 i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 nastoyaschego Kodeksa i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741903083971
Unscheduled inspection
Start date: 2019-09-11, end date: 2019-09-17, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: Sootvetstvie vypolneniya rabot pri ustroistve transhei podsypke ukladki truby pri prisypke truboprovoda peskom pri obratnoi zasypke ot UG24 do V29PG pri ustroistve kolodcev V215 V29PG i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741903085542
Unscheduled inspection
Start date: 2019-09-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741902928536
Unscheduled inspection
Start date: 2019-08-14, end date: 2019-08-20, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot pri montazhe sistemy vodyanogo ohlazhdeniya i gidravliki pechei 5 4 3 v osyah B47 na otm +0000 pri ognezaschite metallicheskih konstrukcii v osyah A1B1 1151 i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741902955195
Unscheduled inspection
Start date: 2019-08-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741902954876
Unscheduled inspection
Start date: 2019-08-21, end date: —, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:
# 741902978798
Unscheduled inspection
Start date: 2019-08-28, end date: 2019-09-03, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot pri prokladke gruppovyh setei rabochego i avariinogo osvescheniya montazhe svetilnikov montazhe kabelnyh konstrukciikronshteiny kabelnye lotki pri prokladke gruppovyh rabochih i avariinyh rozetochnyh setei montazhe derzhatelei zazemleniya shin zazemleniya pri montazhe trubnyh trass i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741902839820
Unscheduled inspection
Start date: 2019-07-10, end date: 2019-07-16, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot pri ustroistve transhei ustroistve osnovaniya pri ukladke truby prisypke peschanoi smesyu pri obratnoi zasypke ot kolodca Kl1 do Kl7 ot Kl13 do Kl3 ot Kl59 do Kl54 ot Kl16 do Kl20 i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741902816714
Unscheduled inspection
Start date: 2019-07-04, end date: 2019-07-10, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: Sootvetstvie vypolneniya rabot pri ustroistve transhei podsypki ukladki truby prisypki pri obratnoi zasypke ot Ug18do Ug19 ot Ug16 do Ug15 ot V21 do Ug14NS ot V26 do Ug24 i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741902641524
Unscheduled inspection
Start date: 2019-04-18, end date: 2019-04-24, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot pri obratnoi zasypke uchastka kolodcev K15K16rz montazhe kolodcev K15 K16rz pri ukladke truby na uchastke K1K8 ustroistve zaschitnogo sloya pri obratnoi zasypke montazhe kolodcev K1K8 i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF
# 741902651869
Unscheduled inspection
Start date: 2019-04-24, end date: 2019-04-30, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot pri ukladke truby obratnoi zasypke montazhe kolodcev na uchastke ot V24PG do ug21 i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741902651846
Unscheduled inspection
Start date: 2019-04-24, end date: 2019-04-30, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot pri ustroistve transhei ustroistve osnovaniya ukladke i prisypke truby pri obratnoi zasypke ot kolodca gasitelya do K63 i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741902651797
Unscheduled inspection
Start date: 2019-04-24, end date: —, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:
# 741902562198
Unscheduled inspection
Start date: 2019-03-13, end date: 2019-03-19, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot pri ukladke truby obratnoi zasypke transhei ot kolodca K64 do ruchya i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741902562146
Unscheduled inspection
Start date: 2019-03-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741902562056
Unscheduled inspection
Start date: 2019-03-13, end date: 2019-03-19, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot pri ustroistve transhei ustroistve osnovaniya pod trubu ukladke truby i prisypki peschanoi smesyu ot kolodca KL55 do kolodca KL46 i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741902483005
Unscheduled inspection
Start date: 2019-02-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741902437587
Unscheduled inspection
Start date: 2019-01-22, end date: 2019-01-28, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot pri razrabotke grunta i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741902437655
Unscheduled inspection
Start date: 2019-01-22, end date: 2019-01-28, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot pri razrabotke grunta i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23i 31 st52 Gradostroitelnogo kodeksa RF
# 741802344148
Unscheduled inspection
Start date: 2018-12-27, end date: 2019-01-31, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po CHelyabinskoi oblasti
Purpose of inspection: proverka provoditsya s celyu vypolneniya trebovaniya Magnitogorskoi prirodoohrannoi prokuratury 92018 ot 18122018g zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie narushenii zakonodatelstva Rossiiskoi Federacii v oblasti sanitarnoepidemiologicheskogo blagopoluchiya naseleniyaPredmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii i ili trebovanii ustanovlennyh municipalnymi pravovymi aktami provedenie meropriyatii po predotvrascheniyu prichineniya vreda zhizni zdorovyu grazhdan vreda zhivotnym rasteniyam okruzhayuschei srede obektam kulturnogo naslediya pamyatnikam istorii i kultury narodov Rossiiskoi Federacii muzeinym predmetam i muzeinym kollekciyam vklyuchennym v sostav Muzeinogo fonda Rossiiskoi Federacii osobo cennym v tom chisle unikalnym dokumentam Arhivnogo fonda Rossiiskoi Federacii dokumentam imeyuschim osoboe istoricheskoe nauchnoe kulturnoe znachenie vhodyaschim v sostav nacionalnogo bibliotechnogo fonda
# 741800241764
Unscheduled inspection
Start date: 2018-03-26, end date: —, duration: —
Authority: —
Purpose of inspection: