# 362101338987
Unscheduled inspection
Start date: 2021-11-18, end date: 2021-03-11, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This inspection is carried out in order to evaluate the work performed and make a decision on issuing an opinion on the compliance of the constructed, reconstructed capital construction facility with the requirements of the design documentation based on the notice of completion of construction (reconstruction) of the capital construction facility.
The objectives of this audit are to prevent, identify and suppress violations of the legislation on urban development, including the requirements of the project documentation, committed by the developer, the technical customer, as well as the person carrying out construction (reconstruction) on the basis of a contract with the developer or the technical customer.
The subject of this audit is compliance with mandatory requirements or requirements established by municipal legal acts.
# 362100131208
Unscheduled inspection
Start date: 2021-04-08, end date: 2021-05-06, duration: 20
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This inspection is carried out in order to implement the program of inspections during the construction of a capital construction facility, developed on the basis of a notice of the beginning of construction (reconstruction).
The objectives of this audit are: prevention, detection and suppression of violations of the legislation on urban development, including the requirements of project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction (reconstruction) on the basis of an agreement with the developer or the technical customer.
The subject of this audit is: compliance with mandatory requirements or requirements established by municipal legal acts.
# 362100023521
Unscheduled inspection
Start date: 2021-02-15, end date: 2021-02-19, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This inspection is carried out in order to carry out a program of inspections during the construction of a capital construction facility, developed on the basis of a notice of the start of construction.
The objectives of this audit are: prevention, detection and suppression of violations of urban planning legislation, including technical regulations, and project documentation committed by the developer, technical customer, and the person carrying out construction (reconstruction) on the basis of a contract with the developer or technical customer.
The subject of this audit is: compliance with mandatory requirements or requirements established by municipal legal acts.
# 362005259069
Unscheduled inspection
Start date: 2020-12-02, end date: 2020-12-14, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This inspection is carried out in order to evaluate the work performed and make a decision on issuing an opinion on the compliance of the constructed reconstructed capital construction facility with the requirements of technical regulations and design documentation on the basis of a notice of completion of construction of a capital construction facility. The tasks of this inspection are the prevention identification and suppression of violations committed by the developer by the technical customer as well as by the person carrying out construction reconstruction on the basis of an agreement with the developer or technical the customer of violations of the legislation on urban planning activities, including technical regulations and project documentation assessment of compliance of the constructed reconstructed capital construction facility with the requirements of project documentation The subject of this audit is compliance with mandatory requirements or requirements established by municipal legal acts
# 362005185512
Unscheduled inspection
Start date: 2020-10-15, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection:
# 362004521638
Unscheduled inspection
Start date: 2020-08-26, end date: 2020-09-18, duration: 18
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This audit is carried out in order to implement the program of inspections during the construction of a capital construction facility developed on the basis of a notice of the beginning of construction. The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as the person carrying out construction reconstruction on the basis of an agreement with the developer or the technical customer. The verification is compliance with mandatory requirements or requirements established by municipal legal acts
# 362004521627
Unscheduled inspection
Start date: 2020-08-26, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection:
# 361904059700
Unscheduled inspection
Start date: 2019-11-15, end date: 2019-11-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This audit is carried out in order to implement the program of inspections during the construction of a capital construction facility developed on the basis of a notice of the beginning of construction reconstruction The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including the requirements of project documentation, committed by the developer, the technical customer, as well as the person carrying out construction reconstruction on the basis of an agreement with the developer or the technical customer is compliance with mandatory requirements or requirements established by municipal legal acts
# 361904059697
Unscheduled inspection
Start date: 2019-11-15, end date: 2019-11-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This audit is carried out in order to implement the program of inspections during the construction of a capital construction facility developed on the basis of a notice of the beginning of construction reconstruction The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including the requirements of project documentation, committed by the developer, the technical customer, as well as the person carrying out construction reconstruction on the basis of an agreement with the developer or the technical customer is compliance with mandatory requirements or requirements established by municipal legal acts
# 36160700057704
Unscheduled inspection
Start date: 2016-08-17, end date: 2016-09-13, duration: —
Authority: Upravlenie po voprosam migracii Glavnogo upravleniya Ministerstva vnutrennih del Rossiiskoi Federacii po Voronezhskoi oblasti
Purpose of inspection: verification of compliance with the requirements of migration legislation