# 002005150314
Unscheduled inspection
Start date: 2020-10-20, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001903222303
Unscheduled inspection
Start date: 2019-09-10, end date: 2019-09-16, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: compliance of the work performed and the building materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or information models in the event that the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used, the need for a construction permit to comply with the requirements set out in Parts 2 3 and 3_1 of Article 52 Urban Planning Code of the Russian Federation
# 001902471339
Unscheduled inspection
Start date: 2019-02-19, end date: 2019-02-25, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to carry out federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of an inspection program, which should be notified to the legal entity in any available way at least three working days before the start of the inspection. The purpose of this audit is to prevent identify and suppress violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, hereinafter referred to as the contractor. The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work the requirements of the project documentation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, the fulfillment of the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 001801973983
Unscheduled inspection
Start date: 2018-11-06, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001800559621
Unscheduled inspection
Start date: 2018-07-30, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001800559620
Unscheduled inspection
Start date: 2018-07-30, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001800058883
Unscheduled inspection
Start date: 2018-01-30, end date: 2018-02-05, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Prevention detection and suppression of violations of the legislation on urban planning, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer (hereinafter referred to as the contractor), Compliance of completed works and applied building materials during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and the fulfillment of the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 00170701645779
Unscheduled inspection
Start date: 2017-07-18, end date: 2017-08-14, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 5_1 of Article 6 of the Urban Planning Code of the Russian Federation
# 272100051193
Unscheduled inspection
Start date: 2021-03-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272100040650
Unscheduled inspection
Start date: 2021-03-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272100040652
Unscheduled inspection
Start date: 2021-03-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272100040651
Unscheduled inspection
Start date: 2021-03-23, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 272100040648
Unscheduled inspection
Start date: 2021-03-23, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 272100040647
Unscheduled inspection
Start date: 2021-03-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272100040646
Unscheduled inspection
Start date: 2021-03-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272100040640
Unscheduled inspection
Start date: 2021-03-23, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 272100051183
Unscheduled inspection
Start date: 2021-03-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272100051180
Unscheduled inspection
Start date: 2021-03-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272100051177
Unscheduled inspection
Start date: 2021-03-23, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 272100051171
Unscheduled inspection
Start date: 2021-03-23, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002005150329
Unscheduled inspection
Start date: 2020-10-20, end date: 2020-10-26, duration: 5
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The real test is conducted for the purpose of implementing the Federal state construction supervision within the competence of Rostekhnadzor in the construction, reconstruction of all the objects referred to in paragraph 51 of article 6 of the town planning code of the Russian Federation on the basis of the audit programme what not less than three business days prior to its implementation to notify the legal entity in any way allow you to control the notification is received by the addressee Objective of this review is to prevent detection and suppression approved developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer hereinafter called the contractor violations of the legislation on town-planning activities including technical regulations and project documentlibraries of this review is of the compliance of contractors and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of this Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices energy resources the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002005150325
Unscheduled inspection
Start date: 2020-10-20, end date: 2020-10-26, duration: 5
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The real test is conducted for the purpose of implementing the Federal state construction supervision within the competence of Rostekhnadzor in the construction, reconstruction of all the objects referred to in paragraph 51 of article 6 of the town planning code of the Russian Federation on the basis of the audit programme what not less than three business days prior to its implementation to notify the legal entity in any way allow you to control the notification is received by the addressee Objective of this review is to prevent detection and suppression approved developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer hereinafter called the contractor violations of the legislation on town-planning activities including technical regulations and project documentlibraries of this review is of the compliance of contractors and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of this Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices energy resources the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002005150321
Unscheduled inspection
Start date: 2020-10-20, end date: 2020-10-26, duration: 5
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The real test is conducted for the purpose of implementing the Federal state construction supervision within the competence of Rostekhnadzor in the construction, reconstruction of all the objects referred to in paragraph 51 of article 6 of the town planning code of the Russian Federation on the basis of the audit programme what not less than three business days prior to its implementation to notify the legal entity in any way allow you to control the notification is received by the addressee Objective of this review is to prevent detection and suppression approved developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer hereinafter called the contractor violations of the legislation on town-planning activities including technical regulations and project documentlibraries of this review is of the compliance of contractors and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of this Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices energy resources the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002005150304
Unscheduled inspection
Start date: 2020-10-20, end date: 2020-10-26, duration: 5
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The real test is conducted for the purpose of implementing the Federal state construction supervision within the competence of Rostekhnadzor in the construction, reconstruction of all the objects referred to in paragraph 51 of article 6 of the town planning code of the Russian Federation on the basis of the audit programme what not less than three business days prior to its implementation to notify the legal entity in any way allow you to control the notification is received by the addressee Objective of this review is to prevent detection and suppression approved developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer hereinafter called the contractor violations of the legislation on town-planning activities including technical regulations and project documentlibraries of this review is of the compliance of contractors and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of this Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices energy resources the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002005150314
Unscheduled inspection
Start date: 2020-10-20, end date: 2020-10-26, duration: 5
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The real test is conducted for the purpose of implementing the Federal state construction supervision within the competence of Rostekhnadzor in the construction, reconstruction of all the objects referred to in paragraph 51 of article 6 of the town planning code of the Russian Federation on the basis of the audit programme what not less than three business days prior to its implementation to notify the legal entity in any way allow you to control the notification is received by the addressee Objective of this review is to prevent detection and suppression approved developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer hereinafter called the contractor violations of the legislation on town-planning activities including technical regulations and project documentlibraries of this review is of the compliance of contractors and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of this Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices energy resources the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002005150297
Unscheduled inspection
Start date: 2020-10-20, end date: 2020-10-26, duration: 5
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The real test is conducted for the purpose of implementing the Federal state construction supervision within the competence of Rostekhnadzor in the construction, reconstruction of all the objects referred to in paragraph 51 of article 6 of the town planning code of the Russian Federation on the basis of the audit programme what not less than three business days prior to its implementation to notify the legal entity in any way allow you to control the notification is received by the addressee Objective of this review is to prevent detection and suppression approved developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer hereinafter called the contractor violations of the legislation on town-planning activities including technical regulations and project documentlibraries of this review is of the compliance of contractors and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of this Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices energy resources the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002005150287
Unscheduled inspection
Start date: 2020-10-20, end date: 2020-10-26, duration: 5
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The real test is conducted for the purpose of implementing the Federal state construction supervision within the competence of Rostekhnadzor in the construction, reconstruction of all the objects referred to in paragraph 51 of article 6 of the town planning code of the Russian Federation on the basis of the audit programme what not less than three business days prior to its implementation to notify the legal entity in any way allow you to control the notification is received by the addressee Objective of this review is to prevent detection and suppression approved developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer hereinafter called the contractor violations of the legislation on town-planning activities including technical regulations and project documentlibraries of this review is of the compliance of contractors and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of this Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices energy resources the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 281904049230
Unscheduled inspection
Start date: 2019-12-05, end date: 2020-01-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of conformity committed by the developer, the technical customer, the person carrying out the construction, performed during the construction of the capital construction facility, and to ensure that the completed facility meets the requirements of the design documentation, including energy efficiency requirements and equipment requirements for the capital construction facility. The results of such work meet the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with energy metering devices.7 The subject of this audit is to verify that the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, meet the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility. construction of metering devices for used energy resources
# 001903222303
Unscheduled inspection
Start date: 2019-09-10, end date: 2019-09-16, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: compliance of the work performed and the building materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or information models in the event that the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used, the need for a construction permit to comply with the requirements set out in Parts 2 3 and 3_1 of Article 52 Urban Planning Code of the Russian Federation
# 281903593894
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-10-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations committed by the developer, the technical customer, and the person carrying out the construction of violations of compliance with the requirements of the project documentation performed during the construction of the capital construction facility, as well as the results of such work, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used.7 The subject of this audit is to verify compliance the performance of work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, meet the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used
# 001903076059
Unscheduled inspection
Start date: 2019-08-29, end date: 2019-08-30, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: actual implementation of the regulation dated 14082017 052816530101
# 281902847564
Unscheduled inspection
Start date: 2019-07-05, end date: 2019-08-01, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations committed by the developer, the technical customer, and the person carrying out the construction of violations of compliance with the requirements of the project documentation performed during the construction of the capital construction facility, as well as the results of such work, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used.7 The subject of this audit is to verify compliance the performance of work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, meet the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used
# 281902718845
Unscheduled inspection
Start date: 2019-05-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 281902475556
Unscheduled inspection
Start date: 2019-02-13, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection:
# 001902471340
Unscheduled inspection
Start date: 2019-02-19, end date: 2019-02-25, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to carry out federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of an inspection program, which should be notified to the legal entity in any available way at least three working days before the start of the inspection. The purpose of this audit is to prevent identify and suppress violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, hereinafter referred to as the contractor. The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work the requirements of the project documentation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, the fulfillment of the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902471339
Unscheduled inspection
Start date: 2019-02-19, end date: 2019-02-25, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to carry out federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of an inspection program, which should be notified to the legal entity in any available way at least three working days before the start of the inspection. The purpose of this audit is to prevent identify and suppress violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, hereinafter referred to as the contractor. The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work the requirements of the project documentation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, the fulfillment of the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 001801973983
Unscheduled inspection
Start date: 2018-11-06, end date: 2018-11-12, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: a the compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation including energy efficiency requirements with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used b the availability of a construction permit c the fulfillment of the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 001801973977
Unscheduled inspection
Start date: 2018-11-06, end date: 2018-11-12, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: a the compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation including energy efficiency requirements with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used b the availability of a construction permit c the fulfillment of the requirements established by parts 2 3 and 3_1 of Article 52
# 281802044720
Unscheduled inspection
Start date: 2018-11-09, end date: 2018-12-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations committed by the developer, the technical customer, and the person carrying out the construction of violations of compliance with the requirements of the project documentation performed during the construction of the capital construction facility, as well as the results of such work, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used. 7 The subject of this audit is verification of compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 281801861632
Unscheduled inspection
Start date: 2018-10-09, end date: 2018-11-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: checking the completed construction of the facility and deciding whether to issue an opinion on the compliance of the constructed work facility with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the objectives of this audit are to prevent identify and suppress violations of compliance by the developer, technical customer, and the person carrying out the construction during the construction of a capital construction facility, as well as the results of such work, the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used 7 The subject of this audit is to verify the compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the technical regulations project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources
# 281801858889
Unscheduled inspection
Start date: 2018-10-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 281801340208
Unscheduled inspection
Start date: 2018-09-14, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection:
# 281801340130
Unscheduled inspection
Start date: 2018-09-14, end date: 2018-10-11, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: checking the completed construction of the facility and deciding whether to issue an opinion on the compliance of the constructed work facility with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the objectives of this audit are to prevent identify and suppress violations of compliance by the developer, technical customer, and the person carrying out the construction during the construction of a capital construction facility, as well as the results of such work, the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used 7 The subject of this audit is to verify the compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the technical regulations project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources
# 281801339758
Unscheduled inspection
Start date: 2018-09-14, end date: 2018-10-11, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: checking the completed construction of the facility and deciding whether to issue an opinion on the compliance of the constructed work facility with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the objectives of this audit are to prevent identify and suppress violations of compliance by the developer, technical customer, and the person carrying out the construction during the construction of a capital construction facility, as well as the results of such work, the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used 7 The subject of this audit is to verify the compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the technical regulations project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources
# 281801339561
Unscheduled inspection
Start date: 2018-09-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001800559621
Unscheduled inspection
Start date: 2018-07-30, end date: 2018-08-03, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation
# 001800559620
Unscheduled inspection
Start date: 2018-07-30, end date: 2018-08-03, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation
# 281800461380
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-07-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: checking the completed construction of the facility and deciding whether to issue an opinion on the compliance of the constructed work facility with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the objectives of this audit are to prevent identify and suppress violations of compliance by the developer, technical customer, and the person carrying out the construction during the construction of the capital construction facility, as well as the results of such work, the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources
# 281800461197
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-07-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: checking the completed construction of the facility and deciding whether to issue an opinion on the compliance of the constructed work facility with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the objectives of this audit are to prevent identify and suppress violations of compliance by the developer, technical customer, and the person carrying out the construction during the construction of a capital construction facility, as well as the results of such work, the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used 7 The subject of this audit is to verify the compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the technical regulations project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources
# 281800470082
Unscheduled inspection
Start date: 2018-06-21, end date: 2018-07-18, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations committed by the developer, the technical customer, and the person carrying out the construction of violations of compliance with the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources, performed during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources. The purpose of this work is to verify the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used.
# 281800376274
Unscheduled inspection
Start date: 2018-05-17, end date: 2018-06-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: checking the completed construction of the facility and resolving the issue of issuing an opinion on the compliance of the constructed work object with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the objectives of this audit are to prevent identify and suppress violations of compliance by the developer, the technical customer, the person carrying out the construction during the construction of a capital construction facility, as well as the results of such work, to the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with metering devices for energy resources used, the subject of this audit is to verify the compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of the design documentation, including requirements for energy efficiency and requirements for the equipment of the capital construction facility with metering devices for energy resources used
# 281800376209
Unscheduled inspection
Start date: 2018-05-17, end date: 2018-06-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: The objectives of this audit approved on 01/122016 are to prevent identify and suppress violations committed by the developer, the technical customer, and the person carrying out the construction of violations of compliance with the requirements of the technical regulations of the project documentation performed during the construction of the capital construction facility, as well as the results of such work, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources. The purpose of the audit is to verify the compliance of the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used.
# 001800165188
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-06, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Prevention detection and suppression of violations of the legislation on urban planning, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer (hereinafter referred to as the contractor), Compliance of completed works and applied building materials during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and the fulfillment of the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 001800165194
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-06, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Prevention detection and suppression of violations of the legislation on urban planning, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer (hereinafter referred to as the contractor), Compliance of completed works and applied building materials during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and the fulfillment of the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 281800210918
Unscheduled inspection
Start date: 2018-03-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 281800074830
Unscheduled inspection
Start date: 2018-03-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 281800074804
Unscheduled inspection
Start date: 2018-02-12, end date: 2018-03-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: implementation of the inspection program approved by 26072016 The objectives of this audit are to prevent identify and suppress violations committed by the developer, the technical customer, the person carrying out the construction of violations of compliance performed during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources. The subject of this audit The purpose of this work is to verify the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used.
# 281800074813
Unscheduled inspection
Start date: 2018-02-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001800058883
Unscheduled inspection
Start date: 2018-01-30, end date: 2018-02-05, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Prevention detection and suppression of violations of the legislation on urban planning, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer (hereinafter referred to as the contractor), Compliance of completed works and applied building materials during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and the fulfillment of the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 28170802941007
Unscheduled inspection
Start date: 2017-12-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 28170802407615
Unscheduled inspection
Start date: 2017-09-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 28170802407953
Unscheduled inspection
Start date: 2017-09-26, end date: 2017-10-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: upon notification of the start of construction
# 00170701645779
Unscheduled inspection
Start date: 2017-07-18, end date: 2017-08-14, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 5_1 of Article 6 of the Urban Planning Code of the Russian Federation