# 002005200095
Unscheduled inspection
Start date: 2020-10-22, end date: 2020-10-29, duration: 6
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this inspection is being carried out in order to monitor the execution by JSC MSK Energy of the previously issued instruction dated 09092020 532166B03262020 on taking measures aimed at eliminating violations, including those entailing an immediate threat of harm to the life and health of citizens, hereinafter referred to as the Instruction, the deadline for which expired on the basis of a reasoned submission by Deputy Head Uchevatkin AA dated 19102020 Sl210672r on the need to carry out an unscheduled on-site inspection of the fulfillment by a legal entity of a previously issued instruction on taking measures aimed at eliminating violations, including those entailing an immediate threat of harm to the life and health of citizens, the deadline for which has expired. The purpose of this audit is to establish the facts of the failure of JSC MSK Energy to comply with the prescriptionthe purpose of this audit is the fulfillment of the Prescription by a legal entity
# 001903643816
Unscheduled inspection
Start date: 2019-10-03, end date: —, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002005200095
Unscheduled inspection
Start date: 2020-10-22, end date: 2020-10-29, duration: 6
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this inspection is being carried out in order to monitor the execution by JSC MSK Energy of the previously issued instruction dated 09092020 532166B03262020 on taking measures aimed at eliminating violations, including those entailing an immediate threat of harm to the life and health of citizens, hereinafter referred to as the Instruction, the deadline for which expired on the basis of a reasoned submission by Deputy Head Uchevatkin AA dated 19102020 Sl210672r on the need to carry out an unscheduled on-site inspection of the fulfillment by a legal entity of a previously issued instruction on taking measures aimed at eliminating violations, including those entailing an immediate threat of harm to the life and health of citizens, the deadline for which has expired. The purpose of this audit is to establish the facts of the failure of JSC MSK Energy to comply with the prescriptionthe purpose of this audit is the fulfillment of the Prescription by a legal entity
# 002004464508
Unscheduled inspection
Start date: 2020-08-03, end date: 2020-08-28, duration: 20
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is conducted in order to verify the progress of preparation of electric power facilities for operation in the autumn-winter period of 2020-2021 on the basis of the order of the Acting Head of the Federal Service for Environmental Technological and Nuclear Supervision dated July 08, 2020 267 in pursuance of the instruction of the Government of the Russian Federation dated July 03, 2020 YUBP97109 the objectives of this audit are to prevent identify and suppress violations of mandatory requirements in The subject of this audit is compliance by a legal entity in the course of carrying out activities with mandatory requirements in the electric power industry when preparing electric power facilities for operation in the autumn-winter period of 2020-2021
# 002004483628
Unscheduled inspection
Start date: 2020-08-31, end date: 2020-09-09, duration: 8
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out as part of the implementation of federal state energy supervision the registration number of the function in the federal state information system "Federal Register of State and Municipal Services of Functions" 313853436 Establish that this audit is carried out in order to monitor the progress of preparation of electric power facilities for operation in the autumn-winter period of 2020-2021 on the basis of an order from the Government of the Russian Federation dated 03072020 YUBP97109 and an order from the Federal Service for Environmental Technological Development and Nuclear Supervision from 08072020 267 "On monitoring the progress of preparation of electric power and heat supply facilities for operation in the autumn-winter period of 2020-2021"The purpose of this audit is to monitor the progress of preparation of electric power facilities for operation in the autumn-winter period of 2020-2021. The purpose of this audit is compliance by a legal entity in the process of carrying out activities with mandatory requirements for the safe conduct of work at electric power facilities, safety requirements in the field of electric power aimed at ensuring reliable power supply in preparing enterprises for the upcoming winter period
# 502004353860
Unscheduled inspection
Start date: 2020-03-10, end date: 2020-04-06, duration: —
Authority: Glavnoe upravlenie Moskovskoi oblasti Gosudarstvennaya zhilischnaya inspekciya Moskovskoi oblasti
Purpose of inspection: Compliance with mandatory requirements or requirements established by housing legislation legislation on energy conservation and energy efficiency enhancement Verification of facts stated in the application of other persons Verification of compliance with mandatory requirements for the provision of public utilities to owners and users of premises in apartment buildings and residential buildings Verification of compliance with mandatory requirements for determining the amount and payment of utility bills Verification of compliance with mandatory requirements for ensuring energy efficiency of apartment buildings and residential buildings, their equipment with metering devices for used energy resources and the operation of such devices, verification of compliance with the requirements of housing legislation of the Russian Federation
# 231904208487
Unscheduled inspection
Start date: 2019-11-07, end date: 2019-12-04, duration: —
Authority: Departament po nadzoru v stroitelnoi sfere Krasnodarskogo kraya
Purpose of inspection: the inspection is carried out in order to fulfill the inspection program notification of the completion dates of the works to be checked during the construction reconstruction of the capital construction facility
# 001903643816
Unscheduled inspection
Start date: 2019-10-03, end date: 2019-10-04, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the fulfillment by JSC MSK Energy of the previously issued instruction dated 14082019 312047VNP06672019, hereinafter referred to as the Instruction, the deadline for which has expired. The purpose of this audit is to establish the facts of the failure of JSC MSK Energy to comply with the prescriptionthe subject of this audit is the fulfillment of the Prescription by a legal entity
# 501903725388
Unscheduled inspection
Start date: 2019-09-13, end date: 2019-10-10, duration: —
Authority: Glavnoe upravlenie Moskovskoi oblasti Gosudarstvennaya zhilischnaya inspekciya Moskovskoi oblasti
Purpose of inspection: Compliance with the instructions of state control bodies, supervision of municipal control bodies, Verification of the fulfillment of prescriptions, verification of the implementation of measures according to the prescription
# 231903047515
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-10-22, duration: —
Authority: Departament po nadzoru v stroitelnoi sfere Krasnodarskogo kraya
Purpose of inspection: the inspection is carried out in order to fulfill the inspection program notification of the completion dates of the works to be checked during the construction reconstruction of the capital construction facility
# 231902991750
Unscheduled inspection
Start date: 2019-08-20, end date: 2019-09-16, duration: —
Authority: Departament po nadzoru v stroitelnoi sfere Krasnodarskogo kraya
Purpose of inspection: the inspection is carried out in order to fulfill the inspection program notification of the completion dates of the works to be checked during the construction reconstruction of the capital construction facility
# 001902903142
Unscheduled inspection
Start date: 2019-08-06, end date: 2019-08-14, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The audit is conducted in order to monitor the progress of preparation of electric power facilities for operation in the autumn winter period of 2019-2020. The subject of this audit is compliance by a legal entity in the process of carrying out activities with mandatory requirements for the safe conduct of work at electric power facilities, safety requirements in the field of electric power industry aimed at ensuring reliable power supply in the preparation of enterprises for the upcoming autumn winter periodthe purpose of this audit is to monitor the progress of preparation of electric power facilities for operation in the autumn-winter period of 2019-2020
# 50190803444105
Unscheduled inspection
Start date: 2019-06-21, end date: 2019-07-18, duration: —
Authority: Glavnoe upravlenie Moskovskoi oblasti Gosudarstvennaya zhilischnaya inspekciya Moskovskoi oblasti
Purpose of inspection: Compliance with mandatory requirements or requirements established by housing legislation legislation on energy conservation and energy efficiency enhancement Verification of the facts stated in the citizens' appeal Verification of compliance with mandatory requirements for determining the amount and payment of utility bills Verification of compliance with mandatory requirements for ensuring energy efficiency of apartment buildings and residential buildings, their equipment with metering devices for energy resources used and the operation of such devices Verification of compliance with regulatory rules and requirements for the operation of housing stockconfirmation of compliance with the requirements of housing legislation of the Russian Federation
# 50190803409318
Unscheduled inspection
Start date: 2019-04-30, end date: 2019-05-03, duration: —
Authority: Glavnoe upravlenie Moskovskoi oblasti Gosudarstvennaya zhilischnaya inspekciya Moskovskoi oblasti
Purpose of inspection: Compliance with the instructions of state control bodies, supervision of municipal control bodies, Verification of the fulfillment of prescriptions, verification of the implementation of measures according to the prescription
# 50190803409316
Unscheduled inspection
Start date: 2019-04-30, end date: 2019-05-03, duration: —
Authority: Glavnoe upravlenie Moskovskoi oblasti Gosudarstvennaya zhilischnaya inspekciya Moskovskoi oblasti
Purpose of inspection: Compliance with the instructions of state control bodies, supervision of municipal control bodies, Verification of the fulfillment of prescriptions, verification of the implementation of measures according to the prescription
# 50190803409314
Unscheduled inspection
Start date: 2019-04-30, end date: 2019-05-03, duration: —
Authority: Glavnoe upravlenie Moskovskoi oblasti Gosudarstvennaya zhilischnaya inspekciya Moskovskoi oblasti
Purpose of inspection: Compliance with the instructions of state control bodies, supervision of municipal control bodies, Verification of the fulfillment of prescriptions, verification of the implementation of measures according to the prescription
# 50190803409313
Unscheduled inspection
Start date: 2019-04-30, end date: 2019-05-03, duration: —
Authority: Glavnoe upravlenie Moskovskoi oblasti Gosudarstvennaya zhilischnaya inspekciya Moskovskoi oblasti
Purpose of inspection: Compliance with the instructions of state control bodies, supervision of municipal control bodies, Verification of the fulfillment of prescriptions, verification of the implementation of measures according to the prescription
# 50190803375088
Unscheduled inspection
Start date: 2019-03-16, end date: 2019-04-12, duration: —
Authority: Glavnoe upravlenie Moskovskoi oblasti Gosudarstvennaya zhilischnaya inspekciya Moskovskoi oblasti
Purpose of inspection: Compliance with mandatory requirements or requirements established by housing legislation legislation on energy conservation and energy efficiency enhancement Verification of the facts stated in the citizens' appeal Verification of compliance with mandatory requirements for determining the amount and payment of utility bills Verification of compliance with mandatory requirements for ensuring the energy efficiency of apartment buildings and residential buildings, their equipment with metering devices for energy resources used and the operation of such devices Verification of rights and legitimate interests the interests of citizens and the state in the provision of housing and communal serviCescheck compliance with the requirements of housing legislation of the Russian Federation
# 50190803375086
Unscheduled inspection
Start date: 2019-03-16, end date: —, duration: —
Authority: Glavnoe upravlenie Moskovskoi oblasti Gosudarstvennaya zhilischnaya inspekciya Moskovskoi oblasti
Purpose of inspection:
# 50190803382117
Unscheduled inspection
Start date: 2019-03-16, end date: 2019-04-12, duration: —
Authority: Glavnoe upravlenie Moskovskoi oblasti Gosudarstvennaya zhilischnaya inspekciya Moskovskoi oblasti
Purpose of inspection: Compliance with mandatory requirements or requirements established by housing legislation legislation on energy conservation and energy efficiency enhancement Verification of the facts stated in the citizens' appeal Verification of compliance with mandatory requirements for determining the amount and payment of utility bills Verification of compliance with mandatory requirements for ensuring energy efficiency of apartment buildings and residential buildings, their equipment with metering devices for energy resources used and the operation of such devices Verification of compliance with regulatory rules and requirements for the operation of housing stockconfirmation of compliance with the requirements of housing legislation of the Russian Federation
# 50190803382116
Unscheduled inspection
Start date: 2019-03-16, end date: 2019-04-12, duration: —
Authority: Glavnoe upravlenie Moskovskoi oblasti Gosudarstvennaya zhilischnaya inspekciya Moskovskoi oblasti
Purpose of inspection: Compliance with mandatory requirements or requirements established by housing legislation legislation on energy conservation and energy efficiency enhancement Verification of the facts stated in the citizens' appeal Verification of compliance with mandatory requirements for determining the amount and payment of utility bills Verification of compliance with mandatory requirements for ensuring energy efficiency of apartment buildings and residential buildings, their equipment with metering devices for energy resources used and the operation of such devices Verification of compliance with regulatory rules and requirements for the operation of housing stockconfirmation of compliance with the requirements of housing legislation of the Russian Federation
# 50190803382111
Unscheduled inspection
Start date: 2019-03-16, end date: —, duration: —
Authority: Glavnoe upravlenie Moskovskoi oblasti Gosudarstvennaya zhilischnaya inspekciya Moskovskoi oblasti
Purpose of inspection: