# 772005186595
Unscheduled inspection
Start date: 2020-10-19, end date: 2020-11-16, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development by the audited person The subject of the audit is the fulfillment by the developer of the requirements of part 31 of Article 52 of the Urban Planning Code compliance with the performance of works and applied building materials during the construction reconstruction of the capital construction facility as well as the results of such works the requirements of the project documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance with the completed works with the requirements of the project documentation identified during construction control and state construction supervision
# 77180803233431
Unscheduled inspection
Start date: 2018-09-24, end date: 2018-09-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803178582
Unscheduled inspection
Start date: 2018-07-16, end date: 2018-07-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used