Found 4 inspections:

# 772101383289
Unscheduled inspection
Start date: 2021-11-26, end date: —, duration:
Authority:
Purpose of inspection:


# 772101228184
Unscheduled inspection
Start date: 2021-10-20, end date: 2021-11-18, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the person being checked; The subject of the audit: the fulfillment by the developer of the requirements of part 3.1 of Article 52 of the Urban Planning Code compliance with the performance of works and applied building materials during construction reconstruction of the capital construction facility, as well as the results of such work to the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used, including verification of the elimination of violations of compliance of completed works with the requirements of the design documentation identified during construction control and state construction supervision


# 772100374947
Unscheduled inspection
Start date: 2021-07-27, end date: 2021-08-23, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the person being checked; The subject of the audit: the fulfillment by the developer of the requirements of part 3.1 of Article 52 of the Urban Planning Code compliance with the performance of works and applied building materials during construction reconstruction of the capital construction facility, as well as the results of such work to the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used, including verification of the elimination of violations of compliance of completed works with the requirements of the design documentation identified during construction control and state construction supervision


# 77180803190321
Unscheduled inspection
Start date: 2018-07-31, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.