Found 12 inspections:

# 772100800281
Unscheduled inspection
Start date: 2021-09-21, end date: 2021-10-04, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 772100233434
Unscheduled inspection
Start date: 2021-05-25, end date: 2021-06-07, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772004206708
Unscheduled inspection
Start date: 2020-01-20, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803421032
Unscheduled inspection
Start date: 2019-05-22, end date: 2019-06-11, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803135930
Unscheduled inspection
Start date: 2018-05-15, end date: 2018-06-08, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803058985
Unscheduled inspection
Start date: 2018-01-16, end date: 2018-02-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170802489305
Unscheduled inspection
Start date: 2017-09-18, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701712922
Unscheduled inspection
Start date: 2017-06-15, end date: 2017-06-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701524978
Unscheduled inspection
Start date: 2017-04-10, end date: 2017-04-10, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701405287
Unscheduled inspection
Start date: 2017-02-21, end date: 2017-02-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77160701041682
Unscheduled inspection
Start date: 2016-10-31, end date: 2016-11-01, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: elimination of violations specified in the instruction issued by Mosgosstroynadzor prevention detection and suppression of violations of technical regulations and project documentation committed by the audited person verification of elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 77160700867324
Unscheduled inspection
Start date: 2016-09-26, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.