Found 3 inspections:

# 641903999278
Unscheduled inspection
Start date: 2019-10-17, end date: 2019-11-14, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Saratovskoi oblasti
Purpose of inspection: control over the implementation of the regulation GPN 66411 of 021118 on the elimination of violations of fire safety requirements on the implementation of measures to ensure fire safety at protective facilities and to prevent the threat of fire


# 00170802201267
Unscheduled inspection
Start date: 2017-10-23, end date: 2017-11-20, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Saratovskoi oblasti
Purpose of inspection: control over the implementation of the regulation GPN 79711 dated 071016 on the elimination of violations of fire safety requirements on the implementation of measures to ensure fire safety at protective facilities and to prevent the threat of fire


# 64150601357625
Unscheduled inspection
Start date: 2015-11-23, end date: 2015-12-11, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Saratovskoi oblasti
Purpose of inspection: instructions of the Chief State Inspector of the Russian Federation for Fire Supervision, Lieutenant General of the Internal Service B. A. Borzov, dated 02102015, 43473719, pursuant to the Instructions of the Deputy Chairman of the Government of the Russian Federation D. O. Rogozin, dated 22092015, RDP46456


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.