# 161903019900
Unscheduled inspection
Start date: 2019-08-26, end date: 2019-09-20, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: The purpose of the audit is to protect the rights and interests of employees on the basis of ch7 st360 of the Labor Code of the Russian Federation The tasks of the audit are to ensure compliance with and protection of labor rights and freedoms of citizens including the right to safe working conditions The subject of the audit is compliance with mandatory requirements or requirements established by municipal legal acts
# 16170701789390
Unscheduled inspection
Start date: 2017-07-18, end date: 2017-07-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, verification of the construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 06062017 case 151120170053 prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of the compliance of works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts
# 16170701761959
Unscheduled inspection
Start date: 2017-07-04, end date: 2017-07-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, verification of the construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 06062017 case 151120170053 prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of the compliance of works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts