Found 45 inspections:

# 782101440938
Unscheduled inspection
Start date: 2021-12-10, end date: —, duration: 16
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: Completion of work on the preparation of the construction site in accordance with the Construction Organization Project. Completion of work on the construction of zero-cycle structures (earthworks, pile foundation, monolithic structures below 0.00) 13 stage of construction. Compliance of the work performed and the construction materials and products used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation.


# 782101440999
Unscheduled inspection
Start date: 2021-12-10, end date: —, duration:
Authority:
Purpose of inspection:


# 782101514596
Unscheduled inspection
Start date: 2021-12-27, end date: —, duration: 4
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: Completion of work on the preparation of the construction site in accordance with the Construction Organization Project. Completion of work on the construction of zero-cycle structures (earthworks, pile foundation). Completion of work on the installation of load-bearing structures below 0.00). Compliance of the work performed and the construction materials and products used during construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation.


# 782100641961
Unscheduled inspection
Start date: 2021-09-09, end date: —, duration: 10
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: Verification of compliance with the requirements of Regulation No. 1/306Pr20-21 dated 08/04/2021.


# 782100794549
Unscheduled inspection
Start date: 2021-09-20, end date: —, duration:
Authority:
Purpose of inspection:


# 782100350661
Unscheduled inspection
Start date: 2021-07-15, end date: —, duration:
Authority:
Purpose of inspection:


# 782100408897
Unscheduled inspection
Start date: 2021-07-29, end date: —, duration: 10
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: Completion of work on the installation of external and internal engineering networks. Landscaping of the territory. Determination of compliance of the work performed and the construction materials used in the construction of a capital construction facility, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, compliance with the requirements of Parts 2, Part 3, Part 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.


# 782100291964
Unscheduled inspection
Start date: 2021-06-15, end date: —, duration: 19
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: compliance with the mandatory requirements of fire safety, sanitary and epidemiological safety, and environmental safety. Determination of compliance of the constructed capital construction facility with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used.


# 782100337208
Unscheduled inspection
Start date: 2021-06-30, end date: —, duration: 20
Authority: Severo-Zapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Industrial safety


# 782100246003
Unscheduled inspection
Start date: 2021-05-28, end date: —, duration: 18
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: Completion of work on the installation of load-bearing structures of the building (walls, columns, floors). Completion of work on the installation of external enclosing structures and internal partitions. Prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the requirements of the project documentation performed during the construction of the capital construction facility. Determination of compliance of the work performed and the construction materials used in the construction of a capital construction facility, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, compliance with the requirements of Parts 2, Part 3, Part 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.


# 782100191156
Unscheduled inspection
Start date: 2021-04-11, end date: —, duration: 20
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: Verification of compliance with the requirements of Regulation No. 1/306Pr9-21 dated 03/24/2021. Prevention, as well as detection and suppression of violations of compliance of works performed during construction, reconstruction of capital construction facilities with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer.


# 782100109845
Unscheduled inspection
Start date: 2021-04-06, end date: —, duration: 19
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: Completion of the complex of works on earthworks, installation of pile foundations of parking lots. prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the requirements of the project documentation performed during the construction of the capital construction facility. Determination of compliance of the work performed and the construction materials used in the construction of a capital construction facility, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, compliance with the requirements of Parts 2, Part 3, Part 3.1 of Article 52 of the Urban Planning Code.


# 782100031540
Unscheduled inspection
Start date: 2021-02-24, end date: 2021-03-24, duration: 20
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: Completion of work on the installation of load-bearing structures of a building above m. 0.000. Determination of compliance of the work and the construction materials used during the construction of a capital construction facility, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, compliance with the requirements of parts 2, Part 3, Part 3.1 of Article 52 of the Urban Planning Code.


# 782005228049
Unscheduled inspection
Start date: 2020-11-16, end date: 2020-12-11, duration: 20
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: determination of compliance of the work and construction materials used in the construction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements compliance with the requirements of h2 h 3 h 31 st 52 of the Urban Planning Code, prevention as well as identification and suppression of violations of compliance by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer During the construction of the capital construction facility, the requirements of the project documentation are met


# 782005228034
Unscheduled inspection
Start date: 2020-11-16, end date: 2020-12-11, duration: 20
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: determination of compliance of the work and construction materials used in the construction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements compliance with the requirements of h2 h 3 h 31 st 52 of the Urban Planning Code, prevention as well as identification and suppression of violations of compliance by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer During the construction of the capital construction facility, the requirements of the project documentation are met


# 782005218702
Unscheduled inspection
Start date: 2020-11-03, end date: 2020-11-30, duration: 20
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: determination of compliance of the constructed capital construction facility with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, as well as identification and suppression of violations of compliance of works performed during the construction of the capital construction facility with the requirements of technical regulations and other normative legal acts committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer. project documentation


# 782004476548
Unscheduled inspection
Start date: 2020-08-04, end date: 2020-08-28, duration: 19
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: determination of compliance of the work and construction materials used in the construction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements compliance with the requirements of h2 h 3 h 31 st 52 of the Urban Planning Code, prevention as well as identification and suppression of violations of compliance by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer during the construction of a capital construction facility, the requirements of technical regulations, other normative legal acts and project documentation


# 782004514912
Unscheduled inspection
Start date: 2020-08-27, end date: 2020-09-22, duration: 20
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: determination of compliance of the work on the installation of a 100 monolithic frame walls columns pylons ceilings to the device of external enclosing structures actual performance as well as the construction materials used during the construction of a capital construction facility as well as the results of such work with the requirements of design documentation including energy efficiency requirements compliance with the requirements of h2 h 3 h 31 st 52 of the Urban Planning Code The tasks of this audit are prevention as well as identification and the suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of the compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other normative legal acts and design documentationthe completion of work on the installation of a 100 monolithic frame walls columns pylons ceilings The installation of external enclosing structures the actual execution


# 782004514455
Unscheduled inspection
Start date: 2020-08-25, end date: 2020-09-21, duration: 20
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: Determination of compliance of the work and construction materials used in the construction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements compliance with the requirements of h2 h 3 h 31 st 52 of the Urban Planning Code, prevention as well as identification and suppression of violations of compliance by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer during the construction of the capital construction facility, the requirements of technical regulations, other normative legal acts and design documentationthe completion of work on the installation of load-bearing structures of the building above otm 0The completion of work on the installation of external enclosing structures, roof installation of internal and external engineering networks and systems Installation of engineering equipment


# 782004402043
Unscheduled inspection
Start date: 2020-07-01, end date: 2020-07-27, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 782004402052
Unscheduled inspection
Start date: 2020-03-31, end date: —, duration:
Authority:
Purpose of inspection:


# 782004323717
Unscheduled inspection
Start date: 2020-02-12, end date: 2020-03-12, duration:
Authority: Gosudarstvennaya inspekciya truda v gorode SanktPeterburge
Purpose of inspection: The purpose is to carry out federal state supervision over the employer's compliance with labor legislation and other regulatory legal acts containing labor law norms in connection with the receipt of applications


# 782004245451
Unscheduled inspection
Start date: 2020-01-15, end date: 2020-02-07, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 782004245458
Unscheduled inspection
Start date: 2020-01-16, end date: 2020-02-08, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781904251781
Unscheduled inspection
Start date: 2019-12-23, end date: 2020-01-27, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781904251917
Unscheduled inspection
Start date: 2019-12-23, end date: 2020-01-27, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781903874703
Unscheduled inspection
Start date: 2019-10-16, end date: 2019-11-12, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781903959918
Unscheduled inspection
Start date: 2019-10-17, end date: 2019-11-12, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781903959787
Unscheduled inspection
Start date: 2019-10-17, end date: 2019-11-12, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781903959817
Unscheduled inspection
Start date: 2019-10-17, end date: 2019-11-12, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781903858855
Unscheduled inspection
Start date: 2019-09-30, end date: 2019-10-24, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781903625434
Unscheduled inspection
Start date: 2019-08-14, end date: 2019-09-10, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: determination of compliance of the work performed and the construction materials used in the construction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements compliance with the requirements of h2 h 3 h 31 st 52 of the Urban Planning Code


# 781902874591
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-07-19, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781902874584
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-07-19, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781902874572
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-07-19, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781902874501
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-07-19, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781902874482
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-07-19, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781902853903
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-07-19, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: Prevention, as well as detection and suppression of violations of compliance of works performed during construction reconstruction of capital construction facilities with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer


# 781902751275
Unscheduled inspection
Start date: 2019-05-30, end date: 2019-06-26, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: Compliance with the requirements in the field of environmental protection provided for in the project documentation Prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer, the customer, of compliance with the work performed during construction reconstruction of capital construction facilities with the requirements of design documentation and other regulatory legal acts Compliance of the constructed capital construction facility with the requirements of design documentation in the field of environmental protection


# 781902744294
Unscheduled inspection
Start date: 2019-05-13, end date: 2019-06-07, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: determination of compliance of the work performed and the construction materials used in the construction of a capital construction facility as well as the results of such work with the requirements of design documentation compliance with the requirements of h2 h 3 h 31 st 54 of the Urban Planning Code


# 781902744378
Unscheduled inspection
Start date: 2019-05-24, end date: 2019-06-20, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: determination of the compliance of the work and the construction materials used in the construction of the capital construction facility as well as the results of such work with the design documentation compliance with the requirements of h2 h 3 h 31 st 54 of the Urban Planning Code


# 781902744314
Unscheduled inspection
Start date: 2019-05-24, end date: 2019-06-20, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: determination of compliance of the work performed and the construction materials used in the construction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements compliance with the requirements of h2 h 3 h 31 st 54 of the Urban Planning Code


# 781902632707
Unscheduled inspection
Start date: 2019-04-05, end date: 2019-05-02, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: determination of compliance of the work performed and the construction materials used in the construction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements compliance with the requirements of h2 h 3 h 31 st 54 of the Urban Planning Code


# 781902458664
Unscheduled inspection
Start date: 2019-01-21, end date: 2019-02-15, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: determination of compliance of the work performed and the construction materials used in the construction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements compliance with the requirements of h2 h 3 h 31 st 54 of the Urban Planning Code


# 00170701413651
Unscheduled inspection
Start date: 2017-02-22, end date: 2017-03-24, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: the purpose of the audit is to control the activities of a legal entity in compliance with the requirements of legislation on urban planning, mandatory norms and rules in the field of fire safety during the construction of a capital construction facility the subject of the audit is an unscheduled inspection according to the developer's notices "on completion of construction of a capital construction facility" dated 28112016g 040788071600 and "on elimination of violations during the construction of a capital construction facility" dated 22112017g 040774491650 for compliance fire safety requirements of technical regulations and regulatory documents provided for in the design documentation of the capital construction facility


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.