# 772100473263
Unscheduled inspection
Start date: 2021-08-17, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100373116
Unscheduled inspection
Start date: 2021-07-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100301576
Unscheduled inspection
Start date: 2021-06-28, end date: 2021-07-23, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772105335319
Unscheduled inspection
Start date: 2021-01-28, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772005271819
Unscheduled inspection
Start date: 2020-12-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005234697
Unscheduled inspection
Start date: 2020-11-19, end date: 2020-12-16, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person The subject of verification is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of project documentation identified during construction control and state construction supervision
# 772005243677
Unscheduled inspection
Start date: 2020-11-24, end date: 2020-11-30, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person The subject of verification is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of project documentation identified during construction control and state construction supervision
# 772005194033
Unscheduled inspection
Start date: 2020-10-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004495650
Unscheduled inspection
Start date: 2020-08-18, end date: 2020-09-07, duration: 15
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notice from the developer of the customer. The objectives of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development activities by the person being audited. The subject of the audit is to verify the compliance of the work performed and the building materials used during the construction reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources
# 772004459423
Unscheduled inspection
Start date: 2020-07-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004292488
Unscheduled inspection
Start date: 2020-02-11, end date: 2020-03-11, duration: 20
Authority: Komitet goroda Moskvy po obespecheniyu realizacii investicionnyh proektov v stroitelstve i kontrolyu v oblasti dolevogo stroitelstva
Purpose of inspection: the purpose and objective of this audit is to verify compliance with the mandatory requirements of legislation on participation in the shared construction of apartment buildings and or other real estate objects. The subject of an unscheduled documentary audit is compliance with the requirements of legislation on participation in the shared construction of apartment buildings and or other real estate objects
# 771802186061
Unscheduled inspection
Start date: 2018-12-03, end date: 2018-12-28, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: control of the execution of the prescription
# 771800185087
Unscheduled inspection
Start date: 2018-03-19, end date: 2018-04-13, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: control of the execution of the prescription
# 771800185051
Unscheduled inspection
Start date: 2018-03-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701349646
Unscheduled inspection
Start date: 2017-02-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701349635
Unscheduled inspection
Start date: 2017-02-06, end date: 2017-03-03, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: kontrolya za ispolneniem predpisanii GPN 27411 ot 19022016g ob ustranenii narushenii obyazatelnyh trebovanii pozharnoi bezopasnosti
# 77160700083152
Unscheduled inspection
Start date: 2016-08-25, end date: 2016-09-21, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po gorodu Moskve
Purpose of inspection: proverka ispolneniya Predpisanii 30063381 30063382 300633821 30063380 30063379 ot 01062016g
# 77160601530641
Unscheduled inspection
Start date: 2016-02-16, end date: —, duration: —
Authority: —
Purpose of inspection: