# 772100537414
Unscheduled inspection
Start date: 2021-08-27, end date: —, duration: 5
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: Verification of the execution of regulation No. 05-40-050800-05-01 dated 07/27/2021 with a deadline until 11/05/2021 (Notice of Elimination of violations No. P001-6120524317-48474304 dated 08/17/2021). Assessment of the compliance of the work performed with the requirements of the design documentation at the METTOIL Metalworking Plant at the address: Moscow region, Sergiev Posad, Svatkovo village
# 772100364826
Unscheduled inspection
Start date: 2021-07-21, end date: —, duration: 5
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: Verification of the facts set out in the official memo of the head of the ONzS No. 5 dated 07/13/2021, assessment of compliance of the parameters of capital construction facilities with the maximum parameters of permitted construction, established rules of land use and development, documentation on the layout of the territory, and mandatory requirements for the parameters of capital construction facilities at the capital construction facility "Capital construction facility on a storage unit with KN 50:05:0120121:957" at the address: Moscow region, district Sergiev Posad, Svatkovo village